ECM: Change Master Record in Production Order

Hi
I have created a Change Master Record and made change to the BOM with respect to that change master record.
Now I want the Change master record (Eg. 001) to be visible in the production order (Master Data tab) when the production order is created.
Also, I would like to know if I can change the change master record (to say, 002) in the Production order so that the BOM with respect to that particular Change master record is selected.
Thanks a lot for your help..
Tom

Hi Jack
I think at the time of creating Change master record u haven't maintained the Object types.
In that View u have to maintain Tick at the check box of Actv., Object  & MgtRec  of Object types-- Bill Of Material & Task List.
This will resolve your problem of Change Master Record Display at the time of Production order Creation at View of Master Data.
Parminder Sikarwar

Similar Messages

  • Problem in Creation of Change Master Record in CC01 (ECM)

    Hi folks,
    me got a problem. whenever i create a Change Master Record using the transactuion code cc01, Change Master is generated but it is not updated to the database and instead throws up a dump error.
    Regards,
    maximus.

    its due to the number ranges that is specified in the partner determination ... chech what is the number range assigned in the parner determination ,,, so once u check that u have to manually enter the number between that range only .. this should solve ur problem...
    path to check the number range is as below :
    spro-img-logistic generalbusiness partner-customers---define account groups and field selection ---    
    at this point click position button at the bottom and give ur account group .. select ur account group and click detail button .. now inside that u can see the specified number range .. dafault is 08 ( means u can specify between 400000 to 499999)..
    and some times  u may not have defined number range... check urs and create accordingly ... this should solve ur problem...
    rewards if solved ..
      thank you
    madhan

  • Bapi for update Master Data in Production order

    Dear All ,
        I am working in a car manufacturing company here production order is made month wise planning qty , but every day its Bom is get changed by Autocad/PLM interface and all changes are being recorded through ECN .
       I have to  generate daily reservation for assemblies for a perticular finish vehical ,so I need to update the Masterdata in production order no through the PLM( VB platform) interface .
      So please suggest me any BAPI so that I can update the master data regular basis in monthly production order  or if you have any better way to map this process into SAP please suggest .
    Thanks in advance .
    regards ,
    Pralay ..

    Not sure what master data in production order you want to change. Anyway if it is at header level, then evaluate BAPI - BAPI_PRODORD_CHANGE.
    Alternatively evaluate the usage of Order Change Management if it is feasible in your solution. Do a search in this forum you will find many threads on it, also read SAP help & do a test a test in your sandbox. If you face a specific issue then do revert

  • FM to change Confirmation number of Production order

    Hello Experts,
    I have a requirement where I need to change the confirmation number ( which is already created for a production order) AFVC-RUECK.  I could see that the confirmation number is not modifiable once it is created and no opition to change it by BDC.  But my requirement is to change it for a production order. 
    1.  Is there any FM or BAPI to change it? 
    2.  Or directly changing in the database table AFVC is the only option?
    3.  Or is there any other method in which we can do it.
    Awaiting your reply,
    Balaji

    Hi Balaji,
    Please check whether the below link is helpful,
    Re: How to modify a wrong confirmation of a production order
    Also for the relevant tables, check the link,
    confirmation number of production order
    Best Regards.

  • I have change some fields in  (Production order component )

    I have change some fields in (Production order component overview)

    Hi,
    do you want to hide or disable the fields or add new fields ??? by the way can you please let us know the transaction that you are referring to ??
    Regards,
    Santosh

  • How to collective read PP master data in Production order?

    Hi: Guys
    Please tell me how to collective read PP master data in production orders. in COHV, I can find out some collective functions but read PP master data.
    Thanks
    Henry

    Read PP master data is only to update routing and BOM in production order if it is already created to effect the changesmade in routing and BOM.    I think in that collective option is not possible.  
    Regards
    KrishnamurthyDSS

  • Manual Change Revision Level in Production Order

    Dear guru ,
    The revision level in the production order (for material to be produced and for the component)  isn't manual changeable.
    Does exist a chance for a manual change of revision level ?
    Thanks in advance.

    Dear Suresh ,
    i know the link with ECM. In production order i can change the component revision level if i work with bom explosion date in read PP master data. But this solution isn't flexible. Imagine that i want to read PP master data with different explosion date for different component ...
    Why in the purchase order the system allow a manual change of revision level and this chance doesn't exist in production order ?
    Thanks in advance.

  • Batch record for production order control

    Hi Experts
    I have a problem, 
    For an production order the system has created the Inspection lot.
    Now  I want take the usage decision   but the system inform me that before in it is necessary u201CCreate and approve batch record firstu201D.
    How  can I solved this problem? The order isnu2019t the process order. 
    Best regards
    Ezio Calvi

    Dear
    You are getting this error becasue you can only carry out the following functions for the batch you have selected when an approved batch record exists (see material master record, Work scheduling view ):
    Making a usage decision for an inspection lot of origin Goods receipt from production
    Changing the batch status from Restricted to Unrestricted
    However, no batch record has been created for the batch you have selected. Therefore, the system does not carry out the function.
    So you need to create and approve the batch record.
    Refer SAP Library, section Basis Services / Communication Interfaces -> SAP ArchiveLink -> SAP ArchiveLink - Scenarios in Applications -> Storage Scenarios PP -> Optical Archiving of Batch Records
    Or Else , check this thread which may help you to trace the problem
    Re:Create and approve batch record first
    Regards
    JH

  • How to change operation dates in Production Order /Capacity Leveling

    Dear Experts ,
    We are using ECC 5.0 .In production order , scheduling happing as Backward  based on the Sales Order Delivery Date .I am doing the following :
    1.Demand as Sales Order with Delievery date : 20.03.2010
    2.Running MRP with Lead Time Scheduling -2  in md02 and converting the Planned Order to Production Order .
    4.Production Order have following dates :
             Basic Finsish Date : 21.03.2010
             Basic Start : the day Pl.Or--Pr.Ord
             Schedule Start : 15.03.2010
             Schedule Finsish : 17.03.2010
            Schedule Release : 13.03.2010
    5.In schedueling margin key :  Float Before Production : 3    , FAP : 3 , Release Period : 2
    6.In material master : Work Scheduling View : Setup : 3 days , Processing : 4 ,Interoperation : 2 for one Base Qty 1
    7.In operation : Op1  : Start Date  : 15.03.2010    Finish Date: 15.03.2010
                             Op2 : Start Date : 16.03.2010      Finish Date : 17.03.2010
                             Op2 : Start Date : 17.03.2010      FD : 17.03.2010
    Question :
    1.How to change the Operation dates  in Production Order Operation over view screen ? Today,  operation over view screen , Start date and Finsih Date  of individual operation are not changable with in Production Basic Start /BF date  or beyond .It is only changing based on the Standard Value : Labor
    2.How to change/re-schedule operation dates d in CM21 (Graphical view -Work Center Capacity load as per   Production Order and Operation combination ) based on capacity availale in advance dates? I am using  Time Profile : SAPSFCZ002 -SFC Graph midterm-3 motnhs and Planning  ,
    How to solve this above issue in scheduling operation and capacity distribution .
    Regards
    JH

    Closing the thread

  • Change Work Center during production order confirmation

    Dear All,
    I must to modeling this situation:
    I created an production order. In routing I used an work center A.
    After I confirmed a half of quantity, the work center A was damaged and I must to change it, with the work center B.
    The system allow this change, but when I checked the costing, the situation isn't real. The system counted the costs just for the work center A, and no for work center B.
    My question is: it's possible to change the work center, during production order confirmation and the costs updated with new cost?
    Thank you for your answer!
    Regards,
    Marian

    once a Order is released, the Process order detaisl for that order is frozen.
    however if you want to do it, change the order status to CRTD after reversing the Movements done.
    Do READ MAster data , this will copy the new Work center , redo the previously done Moevements.
    if the change is long term.
    or
    Just manually add the new work center and do the processing. if the change is temporary.

  • Change Profit center in production order

    Hi
    In production order , profit center is taken from material master, we need a solution to fetch the profit center from cost center instead of material master, assigned in work center, in production order
    selection  of production line from production version assigned to production order
    Is there any std functionality or enhancements possible ?
    now I am working with this SAP note
    Note 150959 - Profit center is incorrect in production order
    Regards
    Devakumar
    Edited by: Devakumar on Feb 22, 2010 11:27 AM

    Then Go to OBA5 enter the KO  Application area
    Add the 367 message and  your user iD enter warning in online and Batch,
    After that You can able to Change the   profit center in Order with warning message in Order

  • Track changes to Quantity in Production Order

    Question.
    Is there a way to track changes made to the quantity field in the Production Order. I can only find changes the order status, not to the order, or any other field for that matter.
    I also checked tables CDHDR/CDPOS but no change is recorded there either.
    Is this a missing feature?

    Fernando Garcia ,
    Try using ORDer chnage management for your production orders. I am not sure if order qty change is tracked there.
    Thanks,
    Ram

  • Changing the Assignment of production order in sales order in MTO scenario.

    Hello all!
    I have following problem:
    After the MRP a production order was created for a sales order. Because of the production in another plant
    the production order which was created automatically had to be technically completed and a new one
    created.
    If you want to check now the availability, the sales order finds nothing, because it's linked to the one,
    which was technically completed. Now is the question how can I change the production order for this
    sales order. (In the production order the correct sales order is connected!)
    As I found out it's connected to the field AUFNR in the table VBEP. But how can I change this
    field within a transaction and not in the database?!?

    No replies

  • How to change Profit center in production order

    Hi guys,
    I have to change Profit center value in production order. Order has been created and released also. How to change, if i directly change system throwing error...Please suggest me in this case.
    RGDS
    Dos

    Then Go to OBA5 enter the KO  Application area
    Add the 367 message and  your user iD enter warning in online and Batch,
    After that You can able to Change the   profit center in Order with warning message in Order

  • Change planning plant in production order

    Hi Gurus,
    my business scenario is the following:
    I have 2 plants that are assigned to 2 different company codes. Plant A (ordering plant) and Plant B (supplying plant).
    The users place a sales order on plant A and through MRP with special procurement key 80 the planned order is turned into a production order in plant B.
    But in the order confirmation the system tries to post the GR in plant A. Is there a way to change the planning plant of the production order at any time i.e in order creation or order confirmation? Because I need the GR against the production order to be done in plant B. Since the subsequent posting according to the business scenario would be after production, the goods should be sold from Plant A to Plant B via a sales order.
    Your help would be greatly appreciated.
    Panos

    Hi Panos,
    SPK 80 doesn't suit your requirement, since by design it is doing GR in the ordering plant.
    Alternatively you need to work with a SPK like 40, that is stock transfer from B to A. Just set up the intercompany process for this stock transfer.
    This way, when MRP in A detects a need for replenishment, a stock transfer requisition from B to A is created. Then MRP in B will create a planned order for production (that you will convert into a production order later). GR is in B. The stock transfer requisition is converted into a stock transfer order, and the actual transfer takes place.
    Check also this for more details:
    http://help.sap.com/saphelp_erp60_sp/helpdata/en/f4/7d2d4d44af11d182b40000e829fbfe/content.htm
    Regards,
    Mario

Maybe you are looking for

  • Help With Airport Extreme and External Hard Drive

    I just purchased the Airport Extreme and I couldn't have been happier. I have attached my western digital external hard drive, but I have run into a slight problem/dilemma which I'm hoping someone who is apple savvy can help me out. I live in a house

  • How  Hash tables can be used  in PI mapping

    Hi Experts, I'm don't have any idea how we store the values in hash tables and how to implement them in mapping. In my scenario I have two fields matnum and quantity.if matnum is not null ,then we have to check whether the matnum exists in hash table

  • How to download HP Wireless Hotspot software

    What is link to downlaod HP Wireless Hotspot software?

  • BC4J application - migration to PostgreSQL

    Hello all, I've got an working(!) application - Win2000, JDeveloper 3.2.3, Oracle 8.1.7, BC4J, DACF. Now I have to migrate to PostgreSQL (and therefore to JDeveloper 9i). Is there someone who has already done this? Could you, please, give me some adv

  • [Solved] Dwm reconfigure after update.

    The problem is simple, after update to last version of Dwm i had to build and install it from scratch. I don't want to do that for any new version of Dwm. Is there a way to avoid that process? Cheers. Last edited by n0dix (2010-06-04 13:40:46)