EDI Message not Transmitted for Scheduling Agreement
Hi guys!
Does anybody know what should I check to see why the EDI message for a delivery line in the scheduling agreement has not been transmitted? Would really save me
Regards,
Ileana
Hi
First check the message whether it has been processed properly or not . goto ME39 , Check the message(Shift +F1)
if the message is in red, check the processing log,
If the message is in yellow , process the same using ME9E
If the message is in grren means the Idoc's are generated.
Now got Transaction WE05 & Check the IDoc's giving the Basic type - DELFOR02
Give from & to dates based on the rpocessing date of the message.
Here check the Idoc's are in Red or green . If in red check the Message in the Status.
Thanks & Regards
Kishore
Similar Messages
-
Document flow is not updated for Scheduling agreement
Hi Gurus,
Can you please advise on the below issue..
Some deliveries created with reference of schedule agreement are not displayed in scheduling agreement in forecast delivery schedule under delivery tab and as well as not updated in document flow for VBFA table.
There are two ways to create delivery with reference of Scheduling agreement , 1) Create Delivery order (Order Type : TAM) with reference of SA, then delivery for TAM order.
2) we can add the line item in existing TAM order with reference of SA .
Advance thanks for your valid points.
Best regards,
Venkat.Hi Ram,
Thanks for the reply, there is no issue in copy control settings.
Best regards,
Venkat. -
Header text not printed for scheduling agreement
Hi All,
I have issue with header text print out for scheduling agreement (SA).
In SA when I am manually writing some note and then taking print out, system is giving me correct output with maual note.
I have one standard text (ST) which I need to be printed in evry SA, so in SPRO I created new head text for vendor and in copying rule for text for SA, I created linkage of SA header text with Vendor head text.
In vendor master, I inserted ST in newly created vendor header text.
So now when ever I create new SA for vendor system will determin header text from vendor master.
Now after creating SA when I check the SA, I am able to my ST in SA, but at the time of print out this ST in not printing.
Please let me know what could be the reson.
Regards,
SameerI dont understand about what you mean by expand.
When you a print PO, PO text (header or item) it will check to the configuration setting.
The system didnt care if its adopted from vendor master or info record, or whatever you make in the copying rule.
In your case : you create a standard text then it get copied into PO , then you set the standard text to the PO for print out, example the standard text : word is
"xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx"
Then in the PO the text appear will be like below(the same, because it get copied)
"xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx"
If you configure it in define text for SA, then it the print out it will also (the same)
"xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx"
So what text need to expand? -
MRP To Generate SCHEDULE LINES for Scheduling Agreement
Hi
I have followed the below steps but still the Schedule lines is not generated for scheduling agreement.
1Maintain MRP views 1,2,3,4 for the material in material mste.(MM01)
2. Maintain Purchase Info Record for the vendor plant & material combination.(ME11)
3. Create Scheduling agreement using ME31L
4. Maintain source list for the material & the scheduling agreement # and Line item set the MRP relevant indicator 2 (Necessary ?) ME01
During Run MRP for the material.the below details entered///
Processing key NETCH Net Change in Total Horizon
Create purchase req. 1 Purchase requisitions in opening period
Schedule lines 3 Schedule lines
Create MRP list 1 MRP list
Planning mode 1 Determination of Basic Dates for Planned
Run MDBT or MD02 but still doesn't create the schedule lines......Anything else missing.
MRP1:
MRP Procedure: PD
MRP Group: 0000 (External Procurement only)
Lot Size: EX (Lot For Lot)
MRP2:
Procurement Type: F
Sched Margin Key: 000
MRP3:
Avilablity chec: 02 (Individual requirement)
MRP: 4
NilRaj,
Source List a Mandatory for Scheduling Agreement, if you want to create automatic Scheduling line.
Plz use (2) in MRP RELEVENT tab in ME01 (Source List).
rest of the thing is ok, make sure a material master(MRP 2 VIEW) in that view you have to give a planed delivery days. it is must.
HOPE IT WILL WORK
Regards:
Poision -
Foreign Trade - Legal Control for scheduling agreements
We are on version 4.6C and I am setting up the legal control for my company. It seems to work quite well for sales orders but then when I went in to configure scheduling agreements it errors and tells me you cannot do legal control for document type "E" which are typically scheduling agreements.
I cannot find any documentation on this. Does anyone know why legal control does not work for scheduling agreements and/or is this functionality available in the Global Trade Services module??
Thanks in advance for any and all help!!
DebbieJean,
I have done a Foreign trade implementation.
The core team of the client are FT experts and they would tell you about the legal requirements. Your job is to map them in SAP FT.
In this process you would gain Knowledge about Foreign trade regulations of that country. Remember its country specific.
The ECCN's are provided by the client. Info abt the same is extensivley available on the NET.
You have to get the list of all the mtrls which fall under the controlled cantegory of the respective commerce ministry and then start the config setting these mtrls as relevant for FT checks.
Thanks
Vishal -
Idoc Message type for Scheduling agreement
Dear Experts,
How to configure to create Idoc for Scheduling agreement (not the releaseed schedule lines) ?
I am trying to use message type ORDERS05 but it is not working.
Will any body guide me preferably step by step process for this ?
Thanks in Advance,
Best Regards,
RajuHi Anji,
Thanks for the Reply. But i think ORDRSP is for Order Confirmations.
But I have to send Outbound Idoc for a Schedule Agreement.
Whether the same Idoc type & Messge type used for SO/PO(e.g ORDERS05, ORDERS/ORDCHG) can be used for Scheduling Agreement.
Please Advice.
Regards,
Anbalagan -
Message type for Scheduling Agreement - Outbound IDoc
Hi All,
I have to create an Idoc for Scheduling Agreement through a Z program based on some conditions. I have bit confusion, whether i can use Idoc type for Orders(e.g ORDERS01..05) & Message type ORDERS / ORDCHG to generate Outbound Idoc.
Already there is process code for for ORDCHG mappig IDOC_OUTPUT_ORDCHG & ORDERS mappig IDOC_OUTPUT_ORDERS. Whether there will be any impact on this.
Appreciate your help.
Regards,
Anbalagan.Hi Anji,
Thanks for the Reply. But i think ORDRSP is for Order Confirmations.
But I have to send Outbound Idoc for a Schedule Agreement.
Whether the same Idoc type & Messge type used for SO/PO(e.g ORDERS05, ORDERS/ORDCHG) can be used for Scheduling Agreement.
Please Advice.
Regards,
Anbalagan -
Confirmation Control for Scheduling Agreement
Hello Experts,
I have got situation for subcontracting scheduling agreement where client doesn't need confirmation control. They want to perform GR against scheduling agreement after creating delivery schedule without extra activity(Confirmation).
Process flow is:
1. Create work order(generates purchase requisition for subcontracting activity)(CO01)
2. Create delivery schedule against purchase requisition for scheduling agreement(ME38)
3. Create delivery to supplier through ME2O
4. Confirm Goods receipt(ME38)
5. Goods receipt(MIGO)
I am trying to avoid step 4.
Standard scheduling agreement setup automaticially fetches confirmation control key 0004. If I am disabling it manually, and not performing step 4, system throws message "no GR relevant item in PO"
Can somebody suggest settings to achieve my scenarion
Thanks and Regards
GyaneshHello PavanKumar,
The inbound delivery is one type of confirmation you are receiving from the vendor so I dont think you will be able to create the inbound delivery without confirmation control key.
Hope this helps.
Arif Mansuri
Reward if answre is helpful. -
Taxes for Scheduling Agreement
Hi,
i have used FM CALCULATE_TAX_ITEM in PO Print program to get the tax amounts. I want the same for Scheduling Agreement. But an error occurs in the same saying ' Tax Code XX Country IN does not exist in procedure TAXINN' . How can i get the tax amounts for the same?? Tax Code is entered and the taxes are calculated & diplayed automatically in the transaction.
Ur valuable inputs awaited..
Thanks & Regards,
Bikash
Message was edited by: Bikash AgarwalHi Brijesh,
This may be the late reply to ur query,
kindly maintain condition record in transaction FV11 for the tax code which u have specified in purchase order.
otherwise u will keep on getting this message for same tax code
regards
satish jadhav -
Error in MIGO for Scheduling Agreement
Dear All,
I have created a Scheduling agreement in LP document type and saved with Net price.
When i do the MIGO the error appears as below.
Transaction cannot be posted due to errors in price determination
Message no. ME573
Diagnosis
The error marked with 'X' occurred during the price determination process for purchasing document 5500000087 00010:
[X] Net price is 0.
[ ] Net price is negative.
and/or there are no valid conditions or the duration of the
contract has ended.
[ ] Effective value is negative.
[ ] Mandatory condition missing.
[ ] Negative delivery costs.
[ ] Delivery costs have been recorded although invoice
receipts are not defined for the item.
[ ] Error during quantity conversion
[ ] Error during currency translation
[ ] Field overflow
[ ] A condition involving delivery costs exists without a
transaction/event key.
[ ]Error during maint. of delivery costs in master conditions
Delivery cost conditions in different validity periods not identical
System Response
The transaction cannot be posted without successful price determination.
Procedure
Check the purchasing document and the associated conditions:
Display purchase order
Display scheduling agreement
If the problem cannot be resolved in this way, contact your system administrator.
The latter can check the Customizing settings for price determination in Purchasing under Conditions -> Define Price Determination Process
When the foregoing steps have been carried out, try posting the transaction again.
Kindly advice how to avoid this error.
RegardsHi
What type of document type are you using for Scheduling agreement? I think you are using time dependent conditions. (see it in document type definition config). If the tick mark is done for time dependent condition then in additional data of scheduling agreement line item pr.date category will be 5-GR date. So Your validity period for condition is not valid for today thats why you are getting error. You need to change validity period for your conditions. Then you will not get error.
Regards
Antony -
P.o for scheduling agreement
Dear SAPians
Is it necessasry to create a Purchase Oredr for scheduling agreement or can it be directly send to a vendorHave you set the condition record on MN11?
Usually is set LPH1 for EDI and LPH2 for printer. Set 3 on dispatch time if you want to execute ME84 and ME9E after (by yourself or via job). If you want to send automatically through ME84 set the dispatch time (mn11) as 4.
Execute ME84. Enter the agreement or the parameters to select the agreements that you want and execute. Check the error messages and if everything is okay run it again unchecking the Test run field.
If you need more information just let us know.
regards. -
LSMW using IDOC method for scheduling agreement
I am using LSMW IDOC method to create Scheduling agreement. i am using message type : PURSAG_CREATE. I have completed the field mapping and when i tried to process the idoc i am getting the following error.
No instance of object type PurchSchedAgreement has been created. External reference: # 1
There are no clue why this error is popping up.
please let me know if anyone faced similar issues.Are you using external number range for scheduling agreement, then you have to pass the SA number too if not then check with your MM functional consultant to change the number range from external to internal provided it is agreed by your customer
-
Over Delivery Tolerance for schedule agreements
Hi,
we have overdelivery tolerance of 10% in schedule agreement and system is allowing to do GR for more the the over delivery tolerance.
can any one tell me how to get the error message while doing GR for more than the over delivery tolerance in case of schedule agreements.See OSS Note 874264 - MB01/MIGO: Default quantity for goods receipt posting
3. The basis used for calculating the over or under delivery tolerance is the quantity ordered, in case of purchase orders, and the suggested quantity, in the case of scheduling agreements. If you want the system response to be the same for scheduling agreements as it is for purchase orders (that is, you need more generous tolerances) see also the SAP Consulting Note 741385.
For items with a confirmation control key, the basis for the calculation of the over or under delivery tolerance is the quantity ordered or the total of the schedule line quantities. -
Delivery Schedule for Scheduling Agreement
Hi Gurus,
Can I do GR for scheduling agreement(with delivery schedule) if the GR is earlier than delivery date? What should I do to be able to do so?
Thank you very muchHi
'Propose all Items" is ticked so that MIGO proposes all the items irrespective of the delivery date and quantity. This means that even if the delivery date has not yet been reached or the complete qty has been received, the system will still allow you to do the GR.
Hope this clarifies.
Thanks -
Release strategy for Scheduling Agreement(SA)
Dear Forum,
This issue is with regards to the release strategy for Scheduling Agreement(SA)
Until now release has only been applicable to contracts at our client site. But we now plan to introduce it for SA as well. Such a feature is available in SAP but the problem is that with the given release strategy GR is not allowed until the release is affected. The system allows you to post the delivery schedule.
Now what I want is that after making the SA the system should not allow to make delivery schedule if release is not affected.
We also have MRP run at client site..Kindly suggest the procedure as, how to configure it.Are der any User Exit for the same,if so please discuss..
Warm Regards
Nainesh
SAP ECC 6.0Hi,
What's the SA Type that was created via MRP.
If it's LP (without release document), release will not do anything BUT
If it's LPA (release document), then you will not be able to Post the GR until release is affected.
Thanks.
Scheduling Agreement can be categories as
1) LP (without release document) and
2) LPA (with release document)
If use LP, you can do GR without release but with LPA, you need to release the schedule line via ME38.
Thanks.
NanoSAP
Posts: 58
Registered: 1/5/09
Forum Points: 6
Re: release strategy for Scheduling Agreement(SA)
Posted: Jun 26, 2009 8:32 AM in response to: sathish.kumar Reply
Dear Mr.Satish,
Thanks a lot for your earliest reply...But my point is i want the system should not allow to make delivery schedule if release is not affected...Though schedule lines are generating through MRP run...Is is possible,by any chance...??
Maybe you are looking for
-
Question of my asa if it support anyconnect vpn
does my asa current license support using cisco any connect or easy vpn cisco ?? http://www9.0zz0.com/2014/03/04/11/979253014.png
-
Why do most of my stacks come ungrouped when I make changes to other files in the same folder?
I have a folder of about 3000 graphics and photos that I use for work. I've meticulously organized them all by using unique file names, keywords, and sorting. However, when I make changes to a set of files (especially using the batch rename tool), a
-
Is passing parameter to ORDER BY clause possible?
I'm using a function to return a ref cursor and currently pass a parameter without any problems. I would like to change the sort on the fly by passing a parameter to the order by clause, but Oracle ignores it. CREATE OR REPLACE PACKAGE pkg_agent_appt
-
How to make changes in default toolbar
hi i m using oracle forms 6 and i want to know either it is possible to change in the default toolbar or not if so plz let me know how to make changes in default toolbar and re-adjust according to my need.i know how to create new toolbar and connect
-
High Res Icon - iPad3 ( not supported yet ? )
I'm trying to include the following to my app XML to allow for the x2 icon for iPad3 <icon> <image144x144>assets/[email protected]</image144x144 <image72x72>assets/icon72.png</image72x72> <image48x48>assets/icon48.png</image48