Edit Restrictions in SRM PR in ERP

Hello All,
I find that for all the PRs created in ERP from a SRM shopping cart, few fields like Material, Short Text and Material Group are greyed out. Is this a standard design? What needs to be done to ensure that these fields are in editable mode in ERP ? We are in classic scenario.
Regards
Sathya

Hi Gopal ,
As per your requested SC you are expecting the Follow on PO to be created but its creations the PR.
Kindly first check the configuration in SPRO for the product category you are using.
for for the navigation please follow the below path:
IMG->SRM Server->Cross Application basic settings-> Define Objects in Backend System (Purch. Reqs, Reservations, Purch. Orders)
check the configuration value maintained for the respective product category id  either PR or PO
if the value is maintained as Always PR then it will create the  PR always else PO
Also if the SC is ordered without supplier then again the PR will be created as per the customizing ..
Kindly let me know if in case you need further help.
With Regards,
Rahul

Similar Messages

  • Oracle 10g Enterprise Edition restrictions

    Hi,
    Kindly anyone help me to detail what are the Oracle 10g Enterprise Edition restrictions?
    Any help will be needful for me
    Thanks and Regards

    user598986 wrote:
    Kindly anyone help me to detail what are the Oracle 10g Enterprise Edition restrictions?To add to the other post - the answers are in the following specific doc
    1) Legal restrictions are in the license document you agree when you get the software
    2) General discussion about what is included with the edition, and what is in Options, is found in Licensing manual
    3) General software limits are described in the Limits chapter of the Reference manual
    4) Operating system specific limits are in the Platform or Admini guide for the operating system

  • Unable to edit restrictions, siri, and safari disapeered

    ON my 5s, after few days of updating it -- siri changed to "Voice Control"; and safari and camera disapeered, and searching for it doesn't work. SIri isin't in my options anymore, and when i try to edit restrictions, it asks for passcode but passcode won't work. any fix?

    recovery mode
    open itunes on computer
    plug cable into computer not iOS device
    turn device off
    hold home button and plug cable into IOS device.  do not release home button until an itunes graphic appears on IOS device.
    look to computer should have message about recovery mode click ok and restore
    Peace, Clyde
    if u need an article see
    http://support.apple.com/kb/HT1808

  • Transfer Attachments SRM 7.0 --ERP 6.0

    Hi all,
    we are currently on SRM 7.0 and want to establish Attachment Transfer within classic Scenario from SRM to ERP.
    I am aware of the respective OSS Notes (concerning Flag within TRANSFER BADI SRM and DC10-DC30 within ERP).
    Simple question:
    When an attachment is transferred from SRM to ERP, is just the link been transferred to ERP or the whole document?
    Question regarding file space --> are all documents "doubled" after being transferred or does the ERP just get the respective link to the attachment stored in SRM BDS?
    Thanks and regards
    Andreas

    Hi
    1 When you attach any attacment in SRM,the attachment is transfer as a whole to backend system.
    2 Attachment is stored under  Content Management Server
    Trinath
    Regards

  • SRM 7.0 erp integration

    Hi all,
    is there a standard integration between SRM 7.0 and ERP? Thanks!

    Can we use RFCs just like in SRM 5.0?

  • SRM 7.0 / ERP 6.04: Config. of Central Contract Management

    Hello,
    I want to configure the newly introduced integrated Procure-to-Pay Scenario Central Contract Management.
    I found SAP Note number 1268821 where all tasks are described in order to implement the previous scenario.
    For correct implementation, business function "Purchasing - SAP SRM Integration" (LOG_MM_P2PSE_1) activation is required in the ERP Systems.
    When I run SFW5 t-code in order to activate the previous business function, SAP system gives an alert message.
    What are the consequences of this business function activation ??
    Thank you
    Michele

    Hi Michele,
    I don't think there will be any consequences, we had certain warning messages aswell when we activated the business functions in ECC 6. Reading the warning messages we could conclude it wasn't any serious problem.
    Details on functionalities included in a business function can be viewed here: [http://help.sap.com/erp2005_ehp_04_sp/helpdata/en/42/fbded750e61febe10000000a422035/frameset.htm] -> Business Functions (SAP Enhancement Package 4 for SAP ERP 6.0) -> Business Functions in SAP ERP -> Logistics -> Materials Management -> Procurement - SRM Integration
    Kind regards,
    Tim

  • Labview student edition restricted for sale in uk

    Hi,
    My 30 days trial version is run out, but I need to do more practice on labview. I ordered labview student edition using pearsoned uk and they replied back saying this item is restricted for sale in uk, try ordering from usa supplier.
    Are there any suggestions??
    Best regards
    Solved!
    Go to Solution.

    John - I'm glad to hear you've ordered LabVIEW. Let me know if there's a problem with Journey Ed. If the same thing happens (which I'm pretty sure shouldn't), I'll put you in contact with our sales guys. I'm pretty sure we're allowed to sell it in the uk
    Guru - a bit of advice.. if you're going to be doing something illegal with one of our software products.... Don't talk about it on our forums!!
    Rico P

  • RFC connections in SRM 7.0 = ERP EHP4 system setup

    Hello,
    In SRM 7.0 there is a lot being said about the combination with an ERP EHP4 system. I thought that certain capabilities of SRM <> ERP EHP4 in the area of RFC are not supported anymore. SAP is forcing XI/PI for this.
    When we migrate our R/3 system to EHP4 will we still be able to use the following RFC / iDOC communications?:
    - Purchase Request (R/3 > SRM)
    - Purchase Order (ECS, SRM > R/3)
    - Invoicing (SRM > R/3)
    - Confirmations (SRM <> R/3)
    Anybody has any experience with an EHP4 back-end system? Are there already any plusses for SRM?
    Kind regards,
    Tim

    Hi Rchard,
    SAP promised to release RFC functionalities instead of the current PI obligation for certain new functionality only available on SRM i.c.w. ERP EHP4 with the release of SRM EHP1.
    But what i'm asking is: with an SRM 7.0 (without EHP1, isn't available yet..) can we still utilize RFC for document exchange with R/3 (f.e. Purchase Orders) or does ERP EHP4 require PI?
    Kind regards,
    Tim

  • Attachment restrictions in SRM Portal

    Hi,
    We have a very specific problem regarding the handling of attachments in the SRM portal. The feature is activated and we are storing our documents on  a remote content server.
    However what we would like to do is restrict the access to attachments even though the user has access to the business object. For example one user would have access to say a purchase order and would see that there are 5 attachments attached. Another user with less authorization would have access to the same purchase order and would see only see only three attachments. (preferably this last user would only see the attachments that she or he has uploaded themselves and not that of others.
    Does anyone have any idea if and how this could be done on the SRM portal?
    Thanks.
    Kind Regards,
    Giwan

    Hi Experts,
    To clarify this issue, we're working with the SRM 7.0 Webdynpro applications that have a standard feature to attach documents. In our case it is configured that it should be stored in a Documentum system via the Archive Link interface.
    What we're looking for is further information on how we can restrict the access to these attachements, e.g. by using specific document types and restricting the access by using the proper authorization objects.
    Does anybody have experience with this?
    Any help would be greatly appreciated.
    Best Regards,
    Mark

  • Line item editing restriction

    Hello,
    Can we restrict line item details with reference to a particular field. Requirement is business want to restrict "payment BLOCK"  field in vendor line item. Not restricting for other field  like add text, assignment etc through FBL1N.
    Requirement is to restrcit field "Payment Block Key" in vendor line item.
    Thanks
    Dinabandhu

    Hi,
    Remove the following field from changeable rules  table.
    BSEG-ZLSPR.
    FA Global settings-documnets-Rules for changing documents-line item change rules.
    Rgds
    Swapna

  • External requirement with SRM 7.0 & ERP 6.0 enhancement package 4

    hi experts
    we are using SRM classic scenario with SRM version 7.0 & ECC 6 EHP 5.
    PR with document type NB is updating on SRM successfully.
    but when I try with service PR with item category "D" is not updating.
    i have few query.
    like.
    by this scenario can we transfer PR with item category D with service line?
    please suggest anyone .
    Regards
    Vijay Patil

    Hi,
    Refer to below threads (these are not answered threads, but it may help you).
    http://scn.sap.com/thread/3579279
    http://scn.sap.com/thread/3611581
    Ganapathi

  • SRM catalogue in ERP web dynpro

    Hi Experts!
    II faced a problem which i have no idea how to solve. In SAP tcode IW31 there is button to show SRM catalogue with components. I created similar application to IW31 in web dynpro, but new I would like to add the same function in web dynpro application. Do you have any idea how it can be implemented. I have no idea how to start, any ideas are welcome.
    Regards
    Bartlomiej Lach

    Hi,
    has anyone any idea, maybe you met with some PDF guide?
    Regrads
    Bartlomiej Lach

  • Number of Custom Field Restriction between SRM MDM OCI Mapping to SRM

    Hi Experts,
    We have a project requirement to cater to 70 Plus custom field which is NON Standard fields transferred from SRM MDM to SRM Shopping cart
    We need to understand if this is achievable??? by enhancing OCI mapping and Catalog Transfer BADI.
    We appreciate your response in this regard.
    Regards
    Prashanth

    Hi,
    There are 5 pre defined custom fields in the OCI, NEW_ITEM-CUST_FIELD[1-5] are available, each with different structures (i.e. field length etc) to support different requirements. All are of type CHAR though I am pretty sure.
    These fields can be passed via the OCI interface and then mapped to standard PROCDOC fields using the BBP_CATALOG_TRANSFER Badi.
    Regards,
    Jason

  • SAP SRM - ERP INTEGRATION

    Hello,
    we are designing application architecture. Our landscape is:
    - ECC 6.0
    - SRM 5.0
    - XI 7.0
    We are thinking of using <b>XI as middleware even for those scenario in which in not required</b> (es. Contract Managament):
    In particular every time we have a <b>communication based on IDOC</b> we want to use XI as communication middleware. Pure RFC integration will not use XI.
    Has anyone some experience on this?
    Thanks
    antonio

    Hi
    <u>Some related Links -></u>
    Re: Upgrade SRM on 4.7 to ECC 6.0
    Re: EBP 3.0 Integration with ERP 2004
    SRM@ERP2005
    Re: SRM-R/3 Service Packages
    Problem transferring deletion status to ERP from SRM
    SRM 4.0 (SERVER 5.0) integration
    Re: SRM add-on configuration
    Re: Integration between SRM and 5 R/3 backends
    RFC connection problem during SRM - R/3 integration
    Re: ECC 5.0 & SRM / EBP
    Re: SRM as ADD On in ECC6.0
    <u>Please go through the following SAP OSS Notes, which will help -></u>
    Note 963000 - Usage and release of SRM as AddOn to ECC in ERP2005
    Note 863532 - Release Restrictions mySAP SRM 2005
    Note 931020 - SRM connection to an ERP 2005 (ECC 600) back end
    Note 917523 - Release note SRM Server 5.5 Support Package 05
    Note 1014414 - SRM 5.0 SP stack 08(03/2007) SAPKIBKT08 release/info note
    Note 872533 - FAQ - Middleware
    Note 740536 - No objects in administration console
    Note 874589 - SRM 4.0 connection to an ERP 2005 system
    Note 862290 - Connection to ECC 5.0 back end
    Note 995771 - System Landscape Copy for SAP SRM 4.0 and 5.0
    Regards
    - Atul

  • POR not transfering from SRM to ERP

    Hi Experts,
    We are working with extended classic scenario on SRM 7.0 & ERP EHP4.
    We are creating POR manually in SRM and also recieving POR from SUS system.
    When we accept the POR it is not updating the ERP.
    We have enabled the PI scenario for transfering POR from SRM to ERP by using the Proxy and IDOC(ORDRSP) but the XML is not generated when the POR is accepted.
    Can any one help me how to transfer the POR created in SRM to ERP.
    Is there any way we can generate XML message of POR with status Accepted.
    Regards,
    B.N.Karthikeyan

    Hi,
    I have tried this define event option.
    Still XML not generated for POR.
    Regards,
    B.N.Karthikeyan