Effort estimation models

Does anyone use any new good effort estimation models for DI? I have a couple manual stuff ... what does everyone else use..
thanks

Not getting your point. Is the question how long it usually takes to build a dataflow? I personally divide the target tables in three categories:
simple....1 day
complex...3 days
fact table...5 days
Obviously development could be done within minutes, but the refinements, documentation, delta logic, testing,.... takes its time.

Similar Messages

  • Effort Estimation for a New BI implimentation Project

    Dear Experts,
    I need Effort Estimation model excel sheet or any other doc for a New BI implimentation Project.
    I want to know how much time it will take for the following 2 scenarios.
    1. Activatating the business content Object in BI7 for all BC extracotrs in ECC.
    2. If content is not suitable for the requirment then what is the time frame for creating the Customized BI objects and DS,ES and all in ECC.
    I knew it the sam has been circulated to their personal e-mail ids earlier from this forum.
    <removed>
    Thanks,
    APC
    Edited by: Arun Varadarajan on Mar 24, 2009 5:20 PM

    look into this link
    http://www.slideshare.net/arun_bala1/asap-methodology

  • BW ESTIMATION MODEL- Effort Estimate

    Hi Gurus,
              As i am creating a BW estimation model I have put the following effort for complexities for differnt tasks. Please suggest if you think the estimation should be differnt to what I have estimated as I am a rookie in these area.
                                 Complexity(in Man Hrs)          
    Type                           High      Medium      Low
    Set up Technical Enviroment     16     12     8
    Define Source System     24     18     11
    Define Extract Structure     24     18     8
    Define Info Object             5     2     1
    Data Staging                     16     12     8
    Transformation and Mapping     24     16     8
    Build/Activate Data Targets     16     12     8
    Define/Update Update Rules     24     16     8
    Reports                             24     16     8
    Process Chains                  24       16     8
    Thank you so much for your help in advance.
    Regards,
    Sanjeev

    Hi Sanjeev,
    In my opinion
    Define Extract Structure 24 18 8
    (refine it whether you are creating a generic extractor or just activating business content datasource, if generic extractor then the complexity could be based on the number of tables, fields)
    Build/Activate Data Targets 16 12 8
    (segregate based on ODS, Infocube, Multicube)
    Process Chains 24 16 8
    (may need more time)
    For all the above acitivities, are you including the time for design, development, testing, transportation (not as simple as R/3), documentation.
    If you have included the time for all the above, I think the time is convservative and based on the activities you should relook at the same by a factor of 1.5 to 2 depending on the object type.
    Hope it helps.
    Cheers
    Anurag

  • Effort Estimation of BI Objects

    Hi,
    Could you please guide me with effort estimation of BI objects basing on the complexities(High/Medium/Low). I need a template with number of man days/hours for each BI object.
    Regards
    Lakshmi
    [email protected]

    Hi Lakshmi,
    check out this threads....
    BW ESTIMATION MODEL- Effort Estimate
    hope this helps you....

  • SSM Effort Estimation

    Hi All,
    Can you please share the components/objects that should be considered while doing Effort Estimation for SSM projects.
    For Eg :- No. of KPI.
    Regards,
    Niksha

    Niksha,
    You have to start with defining the initial deliverables, both on the business side (how many scorecards, KPIs, and how many areas will be involved with the initial rollout) and the technical side ( how many models, what other data systems need to be connected for initial data).
    I agree with the other responses above, they offer good guidance and things to consider. The amount of effort that it takes is very dependent upon the initial deliverables and the scope of the project. Strategy Management works best with an incremential implementation that allows for a quick start and then to build on the progress you've made, and build out by including more departments/LOB/regions/etc.
    On the business side, as pointed out in a previous response, the organization needs to have defined goals and objectives - the strategy drives the measurements, On the technical side, there is the design of the dimensional models and the connections to other systems or databases to bring in the data.
    By setting an incremential approach and phased roll-out, you get the best results for your efforts.
    Regards,
    Bob

  • BI Estimation Model

    Many of you had gone through the BI implementation. I am looking for a Project effort estimation tool that is refined and worked for you. Please post your estimation experience with your model. If you have tool (probably Excel based), please send it to [email protected] I will be able to award points only If I have a reply posted !
    Thanks
    AB

    Hi,
    I am also in need of the same, Can you please send the same to [email protected]
    thanks
    Bala
    Message was edited by:
            v b
    Message was edited by:
            v b

  • Best Practice for Portal Patches and effort estimation

    Hi ,
    One of our client is applying the following patches
    1. ECC 6.0 SP15(currently SP14)
    2. ESS MSS SP15(currently SP14 with some level of functional customization )
    3. EP 7 SP18(currently SP14)
    We would like to kwow the best practice for applying portal patches and the effort estimation for redoing the portal devt on the new patch.
    o   What is the overall level of effort with applying Portal patches?
    o   How are all the changes to SAP objects handle?  Do they have to be
         manually re-entered?
    o  What is the impact of having a single NWDI instance across the
        Portal Landscape during the Patch process?
    Regards,
    Revathi Raju.

    Hi Revathi,
    o What is the overall level of effort with applying Portal patches?
    overall effort to apply the patch is apprx 1/2-1 days for NW7 system. This is exclude the patch files download because it's based on your download speed.
    o How are all the changes to SAP objects handle? Do they have to be
    manually re-entered?
    Depending on your customization. Normally it wont effect if you created the customzation application apart from SAP standard application
    o What is the impact of having a single NWDI instance across the
    Portal Landscape during the Patch process?
    Any change that related to NWDI, you might be need to re-deployed from NWDI itself.
    Thanks
    Regards,
    AZLY

  • Portal patches and effort estimation

    Hi ,
    One of our client is applying the following patches
    1. ECC 6.0 SP15(currently SP14)
    2. ESS MSS SP15(currently SP14 with some level of functional customization )
    3. EP 7 SP18(currently SP14)
    We would like to kwow the best practice for applying portal patches and the effort estimation for redoing the portal devt on the new patch.
    o What is the overall level of effort with applying Portal patches?
    o How are all the changes to SAP objects handle? Do they have to be
    manually re-entered?
    o What is the impact of having a single NWDI instance across the
    Portal Landscape during the Patch process?
    Regards,
    Revathi Raju.

    Hi Revathi,
    o What is the overall level of effort with applying Portal patches?
    overall effort to apply the patch is apprx 1/2-1 days for NW7 system. This is exclude the patch files download because it's based on your download speed.
    o How are all the changes to SAP objects handle? Do they have to be
    manually re-entered?
    Depending on your customization. Normally it wont effect if you created the customzation application apart from SAP standard application
    o What is the impact of having a single NWDI instance across the
    Portal Landscape during the Patch process?
    Any change that related to NWDI, you might be need to re-deployed from NWDI itself.
    Thanks
    Regards,
    AZLY

  • Effort estimation (Aufwandschu00E4tzung) for WDA

    Hi,
    is there any best practice out there how we can calculate a effort estimation for a the development of a WDA application? Any Excel-Tool, anything?
    I thought about calculating for every screen (if it contains for example 3 tabstrips i would calculate alltogeather 4 screens) and add some time for the component. But this is by far too vaguely, isn't it?
    How do you do this usually?
    Thanks in advance.

    Hi Axel,
    the time one needs for developing a Web Dynpro ABAP Application mainly depends on the answers to the following questions:
    Are there good enough APIs that can be used for handling most of the business logic required?
    How flexible should the application be? Do you need to generate the ui or is it sufficient to have fixed screens?
    Can components be used again?
    --> Ask your developers, not excel
    ~Silke

  • Effort estimation of developments

    Hi all,
    Could anyone please provide me with some inputs or documents/ templates on Effort estimation of developments in ABAP??
    I have done the initial analysis, but not sure what should be the base of measuring the complexity and time for an object?
    How an object can be further divided and the total time be measured?
    Also please let me know about the marginal timings and all...
    Thanks in advance,
    Anshumita

    Hi
        First the know the complexity of the object.
    Based on complexity only we can estimate the hours.
    Generally for
    simple - 5-6 days
    Medium : 8-9 days
    Complex : 15-18 days
    This can vary from company to company.
    Guidelines for complexity :
    Tables,Transactions involved that is the scracth development or any developed object there for reference like that.
    regards,
    kumar

  • BW Estimation Model

    HI Gurus,
               I am currently trying to build a BW Estimation model . I would be greateful if you'll could suggest me as to the different objects types and the complexity factors for each objects.  I have labeled some tasks related to Info Objects , data targets and Info source. I am looking for suggestions in the Source connection, Update rules, Transfer Rules, Reports ,I want to know as to which tasks for these objects can be labelled as High or Medium or Low complexity?..If anyone of you could share any estimation model , or if anyone of you could provide me with your valuable input , I would really appreciate that.
    Thanks a lot,
    sanjeev

    Hi sanjeev
    Under normal circumstances You can use the following as a rule of thumb.
    1) Source system -> Medium complexity depending on which source system to attach. If You are planning on attaching a SAP related source system complexity is low - if You are planning on using a 3 party source system via DBConnect or UDI complexity is medium to high depending on parameters such as accessibility, data capture etc.
    2) Updaterules -> In general low however as UR are normally used to conduct transformations they can easily be high (ex. if You need to program start routines, return tables etc.) I would look in to the need for data transformation and rate it according to this.
    3) Transfer rules -> Same as for update rules.
    4) Reports -> Medium to high complexity depending of the requirements. If You need to create a simple report without any execution logic it is quite simple to do - however if You need to apply some VBA coding or user exits it can easily be more complex.
    In general You can say that all standard functionality will normally be rated as low to medium. As soon as You need to expand this with either coding or custom made objects the complexity increases.
    Hope it helps
    Regards
    /Frank

  • SAP BW support project-Effort estimation template

    Hi,
    I have to prepare effort estimation template for the sap bw support project.
    I  have prepared the list of activities which covers the different phases
    of the knowledge transition.It would be great if I can get some sample templates
    for sap bw support effort estimation.
    Thanks,
    shital

    Hi Shital,
    I have a couple of sample estimation plans. Send an email to the mail id on my SDN business card, and I'll get back to you with the docs.

  • Effort estimation for upgrading Sap Net weaver 7.0 to EHP2 SP6

    HI,
    We have BI 7.0 on SAP Netweaver 7.0, we want to upgrade it ot EHP2 SP6.
    Current patch level is 16 & oracle 10.2.2.0 database.
    Can anyone tell me  how much the time effort is needed.
    my customer wants an effort estimation for upgrading EHP2.
    please give me some bried idea about this acitivity.
    Regards,
    Maqsood

    > I would like to have details information with respective to time effort estimation during EHP2 upgrade process as below
    >
    > 1. initialization   -1. what system dos in this phase - 2. how much time system takes - 3. impact on server ( like availabel or not available)
    > 2. extraction - . what system dos in this phase - 2. how much time system takes - 3. impact on server ( like availabel or not available)
    > 3. configuration -. what system dos in this phase - 2. how much time system takes - 3. impact on server ( like availabel or not available)
    > 4. checks - . what system dos in this phase - 2. how much time system takes - 3. impact on server ( like availabel or not available)
    > 5. preprocessing -. what system dos in this phase - 2. how much time system takes - 3. impact on server ( like availabel or not available)
    > 6. dowtime -. what system dos in this phase - 2. how much time system takes - 3. impact on server ( like availabel or not available). In general how much downtime system takes during this phase.
    > 7. postprocessing -. what system dos in this phase - 2. how much time system takes - 3. impact on server ( like availabel or not available)
    > 8. Finalization -. what system dos in this phase - 2. how much time system takes - 3. impact on server ( like availabel or not available)
    Nobody can tell you any time values. This depends on the used hardware, the speed of the underlying I/O subsystem, the number of processes you use, the speed of the server, number of languages etc. etc.
    1 - 5 is done online, nobody will notice because all the work is done in a shadow instance .Downtime says it all and 7 and 8 are postprocessing work.
    To try that do a copy of the production to a sandbox and play with the values and see yourself how much time you need.
    Markus

  • Upgrade Effort Estimation

    Dear All,
    For system that is termed complex (e.g. Interface =400, Language=10 ,Custom Object = 20,000, Unicode Conversion - 15,000, DB = 4TB etc) is there a best practice/thumb rule published as to how efforts required for SPDD/SPAU can be estimated ?.
    Regards,
    Neeth

    Hi Neeth,
    Yes!! there is best practice for effort estimation. Before that FYI, SPDD/SPAU means stanadard objects adjustments not custom objects.
    Iff you want the estimation for SPDD/SPAU first count the Standard repository(SPAU),datadictionary objects(SPDD), for this
    1.Run SPDD tcode in your system which ur going to upgrade, it will give the objects, save those objects into excel document, count the objects
    2.In the similar way run SPAU tcode, get the object count.
    Here in both spdd/spau there will be subcategories,
    for SPDD:
    With Modification Assistant
    Without Modification Assistant
    Deleted Objects
    for SPAU:
    Note Corrections
    With Modification Assistant
    Without Modification Assistant
    Translations
    Reset Objects
    Deleted Objects
    In the both of the above categories no need to take care about
    a.Deleted objects
    b.Reset objects
    Finish the above task, then let me know the object count and given mandays to finish this, then i will assist you accordingly.
    Regards
    Arani Bhaskar

  • P2V Effort Estimation

    I would like to understand if you have experience with P2V pricing.
    Example: How much do I need to spend to get my one Physical Machine converted to Virtual Machine.
    I have my ESXi environment, P2V tools are already in place.
    Looking for rough figure along with efforts(Man Days) needed
    Below are areas I foresee of Effort Estimation
    Activity                            Man Hrs/Server
    Data Collection (Inventory)    
    Application Compatibility    
    Utilization    
    Capacity Planning Per Server(CPU,RAM,DisksSpace)    
    Conversion from Physical to Virtual using Conversion Tool    
    Post Build testing (Stress test, UAT)    
    Operational Acceptance    
    Build ESXi Host   
    Avinash S. ITIL,PMP

    Hi,
    IF it's a report u can estimate it through se30(runtime analysis).  U will get percentages in that tool.
    u go se30 and enter u r programe or transaction and click 'analyge'  button on the bottom.
    Reward points if useful.
    Regards
    (YUGANDHAR.P)

Maybe you are looking for

  • HT201263 Having trouble forcing a reset on a disabled iPod touch 4th gen

    My sons iPod touch 4th gen is disabled as he forgot his pass code. I have tried to force a reset but the iPod has never been synced before with any pc it comes up with error asking for pass code. What can I do?

  • What is the key for skinning of paging navbar in 11.1.1.7?

    Hi jdev 11.1.1.7 Know we have pagination in af:table in 11.1.1.7 what is the key for skinning for these word in table navbar: 1-page 2-of 3-of in parathesis and items in paranthesis 4-tooltip of hover on page number inputtext (go to page) Thanks

  • Linking photo from iWeb08

    Hi guys, need help... Just upgraded to iLife 08, the problem is, I used to be able to link photo from my .mac page to , say, forums with scripts like [img]http://web.mac.com/jemmer/iWeb/Album/a%20day%20%40%20D-bay%20vol.1files/Photo1211A.jpg[/img] Bu

  • Error : Cannot connect to the server temporarily

    Hi, A particular PC is giving an error " cannot connect to the server temporarily", the user is able to login on another PC and no one is able to login to lync 2010 ( internal user ) on this particular PC. Options tried: 1) Deleted sip folder under a

  • How do I acces Creative Zen M300 music on the MicroSD Card

    I recently received the M300 as a gift and transferred over 8GB of music to the microSD card. The player can see the music if I access it through the MicroSD menu option. However, I have only been able to figure out how to play individual songs this