Enable Batch Management w/o removing Stock

Hi!
We would like to start using the feature of batch number in SAP BO.
Right now all item are set to "Manage Item by None" on the General Tab under Item Master Data. We manage batches in a separate Excel spreadsheet. Not good, I know
Is there a way to enable Batch Management w/o removing the stock?
If not, what would be the best way to solve the problem?
Thanks for your help,
Christian

Yes that is how we are going to do it:
1. Run an Inventory Audit Report, export it to Excel and divide *** Value/ *** Qty
2. Create a Goods Issue for all Inventory with price calculated in 1.
3. Set "Manage by" in Item Management to "Batches"
4. Run Inventory Audit Report see how much was released at what cost in step 2
5. Create a goods receipt in the same order (and same price)
as stock was released in step 2
Unfortunately I don't see a way to do this other than manually!?

Similar Messages

  • SAP RVBCONVMAT2BM Set Batch Management to materials with stock

    Dear Gurus:
    We are trying to make mass changes in material master, to activate arround 2,000 materials with batch management flag. We heard about the SAP program release RVBCONVMAT2BM, to let us do it in ma massive action.
    Could anyone of you can give me support to get this program?
    In other way, the tasks to be done manually will be not succesful because we currently have more than one month of operations in SAP.

    Hi Jose,
    The report could only be provided by SAP developer after evaluate the specific situation on your system. I think the evaluation process should be very complex and that is why your reported issue has been hold at SAP for such a long time, also only a completed evaluation is done, the SAP developer could provide the report, this is to ensure the data consistency in your system because change the batch management indicator with material stock is a very dangerous bevavior, this could only be done under a strict check. You can't run this report by your own if this is not provided by SAP, because if it cause any serious database inconsistency by running this report without evaluation from SAP developer, then SAP will not responsible for the result and will not help you correct the situation, so I suggest you should better have some pacient and wait for the update from SAP developer, or you may escalate your issue to require a quick process.
    Regards,
    Rachel

  • Regarding batch managment in mm01 after stock had been made

    hi,
    I facing a problem when i tick on batch managment after the stock had come as i had not maintained the view while creating the material.
    But now i want to maintain this field as it is not allowing it.
    plzz help me out as it is really urgent to me.

    Hi,
    Changing from tick to untick or untick to tick of Batch Management indicator follow the procedure (Changing of status in Material Master Record)
    Changing the status of the material from Uncheck to checked or viseversa is possible only if the following conditions are met
    1 Check the Status of material MMBE
    2 There should not be any open Purchase Order Use SE16 & Table EKPO Give the material number for which we have to find the Open Pos; Alternateively ME2M can also be used
    3 There should not be any Open Production Order Use SE16 & Table AFPO Give the material number for which we have to find the Open Production Orders
    4 There sould not be any Sales Order Use SE16 & Table VBAP Give the material Number for which we have to find the Open Sales Orders
    5 There should not be any Purchase Requistion Use SE16 & Table EBAN Give the material Number for which we have to find the Open PRs
    6 There should not be any Stock in Transit MB5T
    7 There should not be any Plant availability Stock MB53
    8 There should not be any Reservation MB25
    9 Previuos Period Stock should be zero Use MM03 with Plant Stock & Storage Loc. View If Stock Exists follow the Procedure mentioned in next chapter to close
    10 Stock requirement should be zero MD04
    11 There should not be any open Delivery Use SE16 & Table LIPS Give the material Number for which we have to find the Open PRs
    12 There should not be any open Warehouse Transfer Request Use SE16 & Table LTBP Give the material Number for which we have to find the Open PRs
    13 There should not be any open Warehouse Transfer Request Use SE16 & Table LTAP Give the material Number for which we have to find the Open PRs
    14 The Batch Corresponding to the plant has to be set for deletion indicator MSC2N
    If previous period stocks exist, we can make a withdrawal posting as follows
    1. Post the same amount to current period stock (for example, using
    movement type 561) so that previous period stock and current period
    stock are identical.
    2. Make a withdrawal posting in the previous period for the stock
    together with posting date (for example, using movement type 562).
    If any of the above Stock Exists it has to be closed;If Any of the stock exists we cannot uncheck.
    After closing all the open items;the related business documents viz Purchase Orders,Production Orders,Delivery,etc has to be Archived
    Archiving has certain criteria while doing Archiving Process-- Systematic Archival is the Key factor i.e relationship diagram has be met.
    SAP Note Number 533383 - Resetting batch management requirement
    Regards,
    Vengat

  • Removal of batch management indicator from material master

    I had removed all batch stock from material code but when trying to remove batch management indicator from material master system is giving the message "batches already exist"
    Please suggest the solution.

    Hi,
       The material is NEW and Batch Managed.  No stocks, orders, batches are existing.
       If the Batch Management indicator is removed in Material Master, is there any way *to see/track the batch/lot * of the product.
    Scenarios: Material is NOT Batch Managed
    1.     How to track a batch received for Purchase order.
    2.     How to track a Batch created in a Production order.
    3.     How to track a Batch in Sales Order.
    Thanks,
    VB

  • Batch Management and Others

    Dear Experts,
    Client system is already having some materials.From these 100 materials ,we would block the 99 materials and the rest material(say X) will be managed in batches.To do this I have thought in the following way:
    1.Posting stock to the  the material X through material to material transfer.
    2.Activate deletion flag to the 99 materials and change the deletion flag message type to Error message from the warning.
    3.Blocking the transaction of these materials for two to three hours.
    4.Create a new material and manage it with batch with classification.(say Y)
    5.Material to material stock tranfer from X to Y.
    6.Change the BOMs where these 99 materials were used.
    7.Material assignment to routing operation does not require change as components were assigned to operation through default first operation,which will be managed by the system itself when I change the BOM.
    Anything more I require to plan..Pl advice
    Regards
    Reshmi

    Dear Rupesh,
    My req is I would like to remove the redundant materials, instead I shall manage these materials through a single material by batch management with classification.but the materials are already in the system without batch management.So until or unless i remove the stock ,the material can not be batch managed.And to remove all materials by a single materials I require the existing stocks of the materials to be updated with the single material,which can be done through material to material transfer.I think I have cleared the issue.
    Regards
    Reshmi

  • Unable to tick batch management

    Dear Expert,
    I unable to tick batch management with error:"Consignment stocks already exist at the customer's."
    However,current/previous stock is zero and no open document in MD04.
    How solve the error?
    Thank you

    MSKU table holds the customer consignment stock.
    Is that really zero there?
    stock  has to be zero  in current and previous period, as you can post to these 2 periods with MM in general.
    If both periods are zero, then youhave no other chance than archiving the special stock using SARA - object MM_SPSTOCK.
    this requires customizing of archives.

  • How to indicate batch managed item in material master

    Dear Frndz,
    where should I have to enable batch management for an item in item master.
    Regards,
    Srini

    Dear Srini,
    You can maintain batch management in Sales:General /Plant (FG),Purchasing view & work scheduling view of Material Master.
    Regards,
    Raja.
    Edited by: Raja on May 12, 2009 7:36 AM

  • Batch management "Display errors" Message no. M3530

    Hi Experts,
    we want to activate batch management in material master data for more than 1000 items. 
    1. Which most of the items having stock without batch in current period and in previous period and few items stock are 0. 
    2. Few of items have the PR, open PO and it included BOM
    I am trying to activate the batch management which the material stock are 0, the system allowing for few items to change and most of items system showing below error.
    Batch management requirement cannot be changed; choose "Display errors"
    Message no. M3530
    please suggest, what are procedure need to follow to activate the batch management in material master.
    Thanks & Regards,
    Sivanandan

    Hi,
    refer below treads -
    Batch management requirement cannot be changed; choose "Display errors
    Activate batch in material master data
    Batch management is not activating in material master

  • Wants to activate batch management for a material which already had a Stock

    hi,
    i want to activate batch management for a material which already has a stock and open Purchasing documents.
    is there any way by which we can do it without removing the same.
    please help.

    program name is RVBCONVMAT2BM
    but i am doubtfull it will be delivered with standard SAP, you need to request you from SAP as they charge for this.
    this program convert the material to batch and all relevant dependant documents will be updated with batch no.
    Regards,
    Pravin Mukkawar
    pasting  some description of the program
    REPORT rvbconvmat2bm.
    Report illustrates the call of function module VBZ0401_CONVERT_OBJECTS
    which sets the batch management flag for one material including
    depending objects. Function module VBZ0401_FILL_BUFFERS helps
    improving the performance.
    then logic......

  • Batch Management-Identified Stock

    Dear Expert
    Process Over View Batch Management: I have given Purchase order for 100 ton Steel Coil for Single Grade NV23S-100L ,Purchase order release with single line item NV23S-100L quantity 100 Ton, once I received the material I  am receiving 10 Coils with same grade but each and every coil have 25-30 Specific Attributes, Like Weight , Heat No, Lot No, Coil Width ,AS,AG etc , which I am sharing with my customer in India when I am selling my Steel Coils and made product , which I want to manage in ByDesign System. I want to manage my inventory behalf of my Coil Grade Specification.
    in SAP By Design, we have  identified stock, I am looking for an option to add 28-30 more fields in Identified Stock Screen , which will reflect into my Inbound Delivery and Goods Receipt and Production, because as per my client requirement I want these more fields on the entry screen ,in this I also want an option of printing so that I can take a preview of it.
    I am working to solve this issue  with SDK ,We have created one business Object MTC  where one complete line item denote with 28-30 fields and the business object instance is Identified Stock ID, I want this Identified Stock Id behave as SAP ByDesign System Identified Stock ID,
    we have identified Stock ID in Inbound, Outbound and Production but there we have one pop with 2-3 fields only I tried to Map my Business Object Instance ID which is Identified Stock ID. The Purpose here for this , Barcode will work in ByDesign System Identified Stock and Product ID basis IN-OUT.  When I am receiving goods my client want to use Barcode Machine and the same for Outbound Delivery and he want to manage this process through Bar Code because of his Product Grade is same but same each product have different 25-30 specification which can be done through Identified Stock ID.
    In ByDesign system we have only Pop Up with 3-4 fields for your reference I am attaching screen shot here as per the Customized solution possible which I am working its not allowing me map my  Business Object Instance ID to System Identified Stock ID because of PSM Issue.
    Kindly please help me if anyone face this issue earlier, or he have some workaround, Please let me know.
    Regards,
    Achyut

    SAP provided two reports which can update or remove BATCH MANAGEMENT INDICATOR and BATCHES without removing the material stocks and documents. We need to close only open physical inventory documents.
    The below reports update, all relevant documents based on batch activation/de-activation:
    u2022 RVBCONVMAT2BM - Sets the batch management requirement indicator.
    u2022 RVBREVMATBM - Removes the batch management requirement indicator
    But,these programns will not be available in standard SAP,they has to procured form SAP.
    more info here:
    Re: Easy or flexible ways to deactivate the batch management!

  • Problems with existing stock and batch management indicator

    Hi,
    We would like to set the batch management indicator for a material.
    However, there is stock on the material for the given plant.
    The different stock categories for the plant/material combination are as follows (according to transaction MMBE):
    Unrestricted use 150
    Reserved (for production ordeers) 42
    Open order qty (incoming PO) 100
    "When I try to set the batch management indicator in MM02 I receive the following error message:
    Material Master Maintenance
    The batch management requirement cannot
    be changed for the following reasons:
    Stocks already exist at plant level.
      Plant SLoc
       PL01 SL01
       PL01 SL02"
    Can someone please guide me in how to remove the stock and the reservations, so that we can set the batch management indicator? Does the reservations of stock have any impact (there are reservations for 5 different production orders for this material)?
    Thanks in advance,
    Lars

    in plant A, you have to add 21 in current period (e.g. with 202 movement), then you issue 171 in previous period. with 201. Result: both periods are zero.
    plant B, just issue 17 in previous period with 201.
    for Plant A   171 with movement 202 back into stock with previous period date, and subsequently 21 goods issue using 201 in current period.
    for plant B: 17 with movement 202 and previous period date.

  • REMOVAL OF BATCH MANAGMENT

    HI,
    I have created a material and maintained the view of batch managment
    in MM01 and now the problem is coming that while creating invoice it gives error of maintainance batch managment.
    now i want to remove the view of batch managment.
    plzz help me out as help will be definately rewarded.

    Hi,
    Changing from tick to untick or untick to tick of Batch Management indicator follow the procedure (Changing of status in Material Master Record)
    Changing the status of the material from Uncheck to checked or viseversa is possible only if the following conditions are met
    1 Check the Status of material MMBE
    2 There should not be any open Purchase Order Use SE16 & Table EKPO Give the material number for which we have to find the Open Pos; Alternateively ME2M can also be used
    3 There should not be any Open Production Order Use SE16 & Table AFPO Give the material number for which we have to find the Open Production Orders
    4 There sould not be any Sales Order Use SE16 & Table VBAP Give the material Number for which we have to find the Open Sales Orders
    5 There should not be any Purchase Requistion Use SE16 & Table EBAN Give the material Number for which we have to find the Open PRs
    6 There should not be any Stock in Transit MB5T
    7 There should not be any Plant availability Stock MB53
    8 There should not be any Reservation MB25
    9 Previuos Period Stock should be zero Use MM03 with Plant Stock & Storage Loc. View If Stock Exists follow the Procedure mentioned in next chapter to close
    10 Stock requirement should be zero MD04
    11 There should not be any open Delivery Use SE16 & Table LIPS Give the material Number for which we have to find the Open PRs
    12 There should not be any open Warehouse Transfer Request Use SE16 & Table LTBP Give the material Number for which we have to find the Open PRs
    13 There should not be any open Warehouse Transfer Request Use SE16 & Table LTAP Give the material Number for which we have to find the Open PRs
    14 The Batch Corresponding to the plant has to be set for deletion indicator MSC2N
    If previous period stocks exist, we can make a withdrawal posting as follows
    1. Post the same amount to current period stock (for example, using
    movement type 561) so that previous period stock and current period
    stock are identical.
    2. Make a withdrawal posting in the previous period for the stock
    together with posting date (for example, using movement type 562).
    If any of the above Stock Exists it has to be closed;If Any of the stock exists we cannot uncheck.
    After closing all the open items;the related business documents viz Purchase Orders,Production Orders,Delivery,etc has to be Archived
    Archiving has certain criteria while doing Archiving Process-- Systematic Archival is the Key factor i.e relationship diagram has be met.
    SAP Note Number 533383 - Resetting batch management requirement
    Reward if found useful.
    Regards,
    Vengat

  • How to remove Batch Management Check in the Material

    I have one requirement to remove batch management check in the materials which should not be deleted.
    I created a testing material with batch management check on and put in material through 561, then did good issue for
    scrapping to remove the stock out. So existing stock is zero in Material Master.
    Then deleted the batch in MSC2N by putting all the delete checks on. There was just one batch created for the material.
    Then ran transaction MM74 to archive, the spool request is as below:
    MCHB: 000000000010000498 2002 1002 D000000200 entry archived                             1 000000000010000498
    Archiving Session Number                                  000004
    Number of Written Data Objects                                1
    Size of Archiving Session in MB                           0,011
    Proportion of Header Data in %                             96,7
    Then in MMPV changed the closing period to may as all the postings were performed in april.
    Now still when I go and remove the batch management check in MM02 Purchasing view, still gives we DISPLAY ERROR message:
    The batch management requirement cannot
    be changed for the follow
    Batches already exist.
    ANY IDEAS why its not allowing me to remove the check as I guess I have performed all the steps required.

    Check whether the batch master is still exists in MSC3N .if it ia archived it should not be avialble in MSC3N
    Refer note:30656
    Reason and Prerequisites
    The message that stocks still exist refers not only to stocks in the current period, but also to stocks in the previous period.
    The reason for checking previous period stocks is that postings can also be made to the previous period when entering goods movements. This would result in inconsistencies if the base unit of measure had meanwhile been changed.
    Solution
    Check whether stocks still exist for the previous period by displaying; for example, the plant stock view or storage location stock view of the material. You do this by selecting "Extras -> Previous period -> Prev. pd SLoc. stock or Prev. pd plant stock".
    If previous period stocks exist, you can make a withdrawal posting as follows:
    1. Post the same amount to current period stock (for example, using movement type 561) so that previous period stock and current period stock are identical.
    2. Make a withdrawal posting in the previous period for the stock together with posting date (for example, using movement type 562).
    You can now try to change the base unit of measure or the batch management requirement indicator again.
    Since the posting of the previous period values to zero is identical with posting to the stocks of the current period, you should reverse the above stock postings (that is, the stock from the previous period should be booked in again) to make sure that the stock values from the previous and the current periods correspond to the state before the change. However, note that the postings are then carried out using the changed master data from the current period (for example, account determination and so on)

  • Remove Batch Management and Split Valuation Dependencies

    Hi,
    I need to remove Batch Management Indicator and Split Valuation for a material. Which one should I do first? Are these dependent on one another?
    Thanks,
    Jograd

    You are correct. It did cause lots of error when i tried to do it in test client.
    I am trying to remove the valuation category of one right now. It has zero stock and no open documents.
    I saw in note Note 155874 - Change valuation category in material master that you need to do this:
    2. If you change from split to joint valuation, no valuation data must
    exist for a valuation type.
    I dont know where to start doing that? Because there is not data for the material. However i noticed that there is valuation for previous period. do i need to delete that too? But there are no stocks for the previous period.
    Please help.
    Thanks,
    Jograd

  • Remove stock and revert it to warehouse to activate batch managmt-BestPract

    Hello,
    My client wants to start using batch management.
    To do so Iu2019ve 3 options:
    1st u2013 Create a new Plant and replicate on it every material. Transfer the existing stocks to the temporary Plant. Activate Batch Management. Transfer from temporary Plant to the original Plant with the respective batches.
    2nd u2013 Create a Sales Order for a temporary Customer with the same internal price and create invoice. Activate Batch Management. Create Purchase Order for a temporary Vendor and make the goods receipt and invoice. Both customer and vendor should balance each other. So does stock accounts.
    3rd u2013 Make a goods issue to a specific cost center. Activate Batch Management. Make a goods receipt with movement 501. In this case Iu2019m not shore about the financial implications.
    Can anyone help based on the experience for each way should I go???
    Thanks,
    BMO.

    SAP provided two reports which can update or remove BATCH MANAGEMENT INDICATOR and BATCHES without removing the material stocks and documents. We need to close only open physical inventory documents.
    The below reports update, all relevant documents based on batch activation/de-activation:
    u2022 RVBCONVMAT2BM - Sets the batch management requirement indicator.
    u2022 RVBREVMATBM - Removes the batch management requirement indicator
    But,these programns will not be available in standard SAP,they has to procured form SAP.
    more info here:
    Re: Easy or flexible ways to deactivate the batch management!