Hi all,
I wanna know if its possible to configure that an Entry Sheet could only be printed after released?
If so, how could this be made?
Regards.
Gregory.
Edited by: Gregory Mayorga on May 28, 2010 4:21 PM

Hi,
In the IMG ->External services management->Messages->output control for                
SES->Define access sequence for SES -> select access sequence 0001->                     
select (for example) table 506 ->fields                                                                               
...here you will see that you can add KZABN to communication                
structure KOMKBES.  If the entry sheet was accepted, KZABN with "A" must be checked. Please create also a condition record accordingly (MN13).
Please check additionally:
spro  > material management   > external services Management   >                        
messages   > define condition table for service entry sheet   > create                  
condition table                                                                               
There is on acceptance on the right hand pannel under field                             
catalog, please make sure you select this field and move them to the                    
left hand panel                                                                               
If this is setup correctly , then please check the following:                                                                               
- the output type use for service entry sheet. If it is NEU (SAP                        
  standard) , check the access sequence assigned                                                                               
- check the configuration of access sequence, whether this customzied                   
  condition is assigned?                                                                               
- If it is assign, whether the exclusive flag is setup                                                                               
if the above customizing is correct, the next step is to check the                      
output condition record via txn MN15 (to display)  
Please also check the flags which you have assigned to your message determination schema in the customizing under "Assign Schema to Service Entry Sheet "                                 
Regards,
Edit

Similar Messages

  • Will it be possible to create new version of document only after releasing

    Dear Expert,
                      is it possible to create a new version of the document only after release of the document...i don't want document version should be created other then release status.
    Bhuwan

    Hello,
    Since you are a technical consultant also, probably you are in a better position to deside how to achieve this.
    You will have to develop a user exit which will check status/ Release Indicator of  Document when new version option is clicked through CV01N/ 2N/ 3N/ 4N transaction and take necessary action. 
    Regards,
    Milind Dumbre

  • Entry Sheet Not Subject to Release strategy

    Hi Gurus,
    I have a situation ,an end user is trying to release the Service Entry Sheets,but he gets an error saying "Entry Sheet Not Subject to Release strategy message 0k000,i dont know what exactly is going on???
    Can some one help me out with this.
    Thanks,
    Srikanth

    Hi
    Check out the release statergy with classification values and also check - your service sheet falls under this criteria. 
    Regards
    Anand

  • Service entry Sheet was reversed after the invoice as posted and rebooked

    Hi..
    Service entry sheet was reversed after the invoice as posted and rebooked with final entry marked.  The rebook transaction created a different $ amount than the original SES.  The difference between the 2 amounts is causing a GRIR out of balance on the PO.  MR11 does not indicate a GRIR out of balance.
    why did SES rebook a different value?
    How can we clean up the GRIR out of  balance?
    Please help...
    Mercy

    This is a standard SAP procedure.
    SAP Note 440942 is helpful to sort this out.
    Thanks,
    Mercy

  • VALUE IN PO HISTORY OF SERVICE ENTRY SHEET EXIST EVEN AFTER DELETION OF SES

    Respected All,
    My client has prepared a down payment request , prepared a service purchase order against that vendor, created service entry sheet.
    Later on he came to know that the qty he has entered is wrong ,so  he reversed all the goods receipt(done 102 Mvt) , deleted the service entry sheet and now trying to create new SES against the same line through ML81N.
    But the Qty column after selection of services is coming blank, i have checked the po history, in that the GR Qty and value is zero and service Qty is zero but service value and down payment column still contains the value, though we have reversed the service entry seet.
    please guide me what to do to reflect the qty part in ML81N again.
    Thanks and Regards
    Abhay Mahodaya

    can you see the material document with reverse movement ( 102 ) ,corresponding to your cancelation of SE sheet in the P.O history tab?
    also check whether the 'actual quantity' in the Service entry extreme right column shows zero.
    check in the deleted SE sheet history tab 'change document' button whether the last row change mentioned is setting deletion indicator

  • Release campaign only after releasing parent marketing plan

    Hi,
    My requirement is, campaign should be released only after parent MP is released. System doesn't allow to release campaign without releasing parent MP by standard. But I am using all user statuses in campaign and MP. I have blocked all system statuses which appears in drop down as standard. How can I get this standard functionality with user status profile?
    Please suggest.
    Regards,
    Nikhil

    Resolved by coding.

  • Service entry sheet printout

    Dear Expert,
    is there is anyway to print the service entry sheet
    please i want an answer ASAP

    If you want to take another print out goto ml83 and from there select processing status (from message parameters) 1 or 2 and then again you can take the printout of service entry sheet.
    hope this will help
    Regards,
    E-Jad

  • Budget check only after release?

    hi,
    i maintain cost activity  in project and when i save it, it checks against the budget...
    is it possible such that it will check the cost activity only upon release of the activity? in other words, i can save it (even if it has greater amount than budget) as long as it is only CRTD... but when it is REL (released), it will already check against budget.
    note that AVAC is already activated in order to check the other objects in the project...

    Dear Ramesh,
    To my knowledge u can activate availability control on networks, only for Materials by using Network type(TC-OPJK) if u define no check here system doesnu2019t check for availability. Pls check, this might help u.
    If this is not the scenario what u are explaining, please explain me the way u have configured availability check on planned values. This will help all to do better R&D on availability check for planned values.
    Thanks & Regards,
    //sam

  • Purchase Order Printout only after po release

    Dear All,
    Plz help me with the below mention problem :
    i donot want the purchase order to get printed untill the po get released completely, plz suggest me required configuration need to be done regarding this
    regds
    joy

    Hi Joy,
    You can adopt a release procedure where in you can block a PO for printing unlease its release strategy is fulfilled.
    Please go though below documents and grant me points if it works for you.
    Release Purchase Orders (MM-PUR)
    Technical name: SAP_MM_PUR_PO_RELEASE
    Tasks
    You can use this role to release (approve) purchase orders.
    A purchase order may be blocked via a release procedure (if its total value exceeds a predefined value - say $10,000 - for instance). Before this purchase order can be outputted (printed out or transmitted directly to the vendor), it must be approved (i.e. released).
    Activities in Materials Management
    Activity
    Transaction
    Release purchase order
    ME28
    Regards,
    Subha

  • Commitment only after release of purchaseorder

    I'm investigating the possibilty that commitments are only registrered when a purchase order with release strategy is released.
    is it possible to have no commitments of a purchaseorder until release ??
    I have found this thread which is about the opposite to remove commitment afterwards ?
    Commitment Release on Rejection of Purchase Requisition
    can thid badi also be used to suppres commitments until release ??
    We don't want to use Purchase Requisition if possible and want to create a purchase order directly with status OPEN
    kind regards
    arthur
    Edited by: A. de Smidt on Jun 16, 2010 1:12 PM

    Refer this Wiki
    http://wiki.sdn.sap.com/wiki/display/ERPSCM/CommitmentsinPurchasing

  • Service entry sheet Release strategy Error

    Hi Guys
    I have one scenario where Iam not able to post Service enrty sheet
    We have release strategies A1,A2,A3,A4,A5
    Some service entry sheets are there in the system with each release strategy
    We have deleted A2,A3,A4,A5 and A1 remains there
    While release the service entry sheets which are having Release strategies A2,A3,A4,A5
    We are facing problems not able to release
    please provide any solution to this error ,
    It is not possible to restore previous release strategies A2,A3,A4,A5
    We need to change release strtegy A2,A3,A4,A5 to A1 for existing service entry sheets
    Please suggest solution.
    Thanks in Advance
    SAP MM

    Hi,
    You are created release strategies A1, A2, A3, A4 & A5 and now deleted A2, A3, A4, A5 but A1 remains there in the system.
    You could have take precaution ieu2026u2026all SES should be released 1st and then deleted youu2019re release strategies A2, A3, A4 and A5.
    For quick solution------ >As now deleted A2, A3, A4, A5 and you want to triggers A1 only for all already created service entry sheet(SES) , then just go to all created SES, do some changes( like change quantity and then retrieve the original quantity in SES) by editing SES and see how re- triggers release strategy A1.{ 1st do it for one SES(as SES number created, you will have same SES number after changes in SES) and try  for all SES}
    Regards,
    Biju K

  • Release Procedure for Service Entry Sheet Wr to the Purchasing document

    Hi,
    I have configured the Service entry sheet release procedure on the basis of Purchase order document type by creating Characteristic With table -field (CESSR - BSART) and also class is maintained where the defined characteristic has been assigned.Release group is assigned to the class and all necessary customizing activities carried over. I assigned release group n Strategy thru Cl20n and also checked in Cl30n for the document type where system is exactly proposing only one value for the document type. But when i create Service entry sheet thru ML81N after saving the document i checked for release strategy through Goto-> Service entry sheet -> Release Strategy which is grey mode.
    I tried thru ML85 System says that no suitable purchasing document is available for release.
    thank u
    Nagarjuna
    Edited by: yalamanchi nagarjuna on May 31, 2009 1:33 PM

    the same configuration is not working in DEV environment but working fine in Quality and PRD

  • Release stratedgy of service entry sheet

    Hi,
    I have created release stradegy of service entry sheet.
    I have created
    Group Y1 and Release Strategy 1 (General) the Release Codes FR in the first line and AB in the second line.
    On the Prerequisites dialog box I have marked the small box AB in the second line .
    On the Release Statuses dialog box, I have defined the Release Statuses as under.
    FR     AB     Release indicator
              N = Not accepted
    X          B = Order placed
    X     X     A = Service Accepted
    but when *I simulating the stratedgy it is showing pre requisite AB is missing.*
    *I have checked AB but FR is showing checked in release status dialog box.*
    *In me81n release is possible only for FR.* is showing .
    How I can have release first AB then FR.
    pl help.
    SB

    Hi,
    please check the table T16FV for the release sequence - prerequisits..
    The design is: if there are prerequisite codes necessary for some release step it can always be just one prerequisite code per level.                                                                               
    1)  You  work with release code AB and FR: Please check how many Persons are                         
    authorized to release with AB or FR.                                                                    
    2) If you don't use any prerequisites: AB and FR can release at the                              
    same time.                                                                               
    In customizing (release statuses) you assign release indicators as                                
    follows (example):                                                                               
    AB FR                Release indicat                                                          
    X                        B                                             
            X                 N                       
    X     X                 A                                                                               
    All other combinations will have release indicator N(blocked).                                   
    This way you can guarantee the entry sheet can just be                                    
    released if both AF and AB released.
    Regards,
    Edit

  • Error in releasing service entry sheet

    Dear All,
    While releasing Service Entry Sheet,user is facing the below error.
    BS 007 " Goods receipt for purch order " is not allowed (Internal Order Number)
    If anyone of you people would have face this sort of issue or heard about it then do let me know.
    Thanks in advance
    nainesh
    sap mm

    Nano ,
    Why  the user want to  Do MIGO ,
    Service  entry shhet are meant for service, In STD  SAP you can not have do good recieved  For the service
      The process is  like
    1  Creation of service aster
    2 Create a Service PO
    3 Maintain service entry sheet
    4approve service entry sheet
    5  MIRO
    After you release the serive PO try to do the  MIRO

  • Activty release should be possible only after WBS release

    Hi Gurus
    My customer wants release of activity only after release of WBS element. Is there any user exit available for that or can i write some validation for the same.
    Thanks in advance
    Regards
    Abhijit Sen

    Hi,
    Ofcourse, you can create activities with initial user status which prohibits "release". If activities are assigned to WBS, with release of WBS , the activity also gets released. But how to change the user status (other than manually) is to be figured out.
    Regards
    Muraleedharan.R