Hi gurus,
I'm working in SRM 5.0, ECS, backend ECC 6.0.
I need to set up the 'Plan Driven Procurement scenario'.
In ECC I created entries in V_T160EX and V_T160PR and I have mantained TBE11 and TBE31 accordingly to SAP note 656597.
I used ME51N to create a purchase requisition (without items release strategy) which is getting copied to EPRTRANS table.
A purchase requisitions (with items release strategy) is getting copied to EPRTRANS table when I Save the PR?
or when I release the single items?
Points will be rewarded
Thanks in advance
Gg

Hi Disha,
you said:
The table EPRTRANS will be populated only when all the items(which have a release strategy) in the PR will be released.
Do you mean that if a PR contains two items (both with release strategy) and only the first has been released, EPRTRANS will not be populated until I release the second item?
Is that correct?
Thanks in advance
Points will be rewarded
Gg

Similar Messages

  • Purchase requsitions into table EPRTRANS when using release strategy

    Hi,
    We are working with release strategy.
    It is not passible to insert purchase requsitions into the table EPRTRANS when I choose e.g.a material group which
    has been declared as a relevant criteria for release strategy. How can this problem be achived ?
    Regards
    Alexander
    Edited by: AlexanderZiegler on Sep 23, 2009 11:25 AM

    pls. comment out this perform
         PERFORM bbp_release_check USING l_xeban
                                         l_yeban
                                CHANGING no_update
                                         now_released.
         IF no_update = 'X'.                   " preq not yet released
           CONTINUE.
         ENDIF.

  • PO and SchdAgreem Release Strategy at Item Level

    Hello!!
    I have the request to setup a the release strategy for the PO and Schedule agreements at line item level....
    as far I know for PurReqs is possible to do that... but for PO and SAs it is only at header level...
    Do you know if is possible to do that in configuration??

    Hi,
    Release strategy for PO & SA is only at Header level, since these documents are external purchase documents.
    But, PR is internal purchase document and release strategy is possible at both item and header level.
    i think, it is not possible to do release strategy at item level for PO & SA as you said,
    Regards,
    Srinu.K

  • With a lock item in a purchase order, release strategy works?

    Dear All,
    I have a very important question for myself.
    I have a purchase order with only one item.
    I have set this item to locked.
    Release strategy works without problems.
    Is this situation correct?
    I don't understand it but maybe the release strategy works normally too....
    Please help me with a explanation
    Thanks in advance

    Yes, if a release strategy is applied to a PO, then even if you block / delete an item, it will still have the release strategy.
    This is standard behaviour, because you can later remove the deletion indicator or unblock the PO, whence the PO will again have to go through the Release Procedure.

  • PR Item Level Release WF not working after Release Strategy change

    Hi Experts,
               I did PR item Level Release Standard Work flow and it was working fine now due to client requirement we changed the release strategy and now when the PR workflow triggers it gives the Below mentioned error.
    I really don't understand y after changing the release strategy workflow is not working and giving the following error.
    Even if i restart the workflow in SWPR the same error is occuring.
    Exception occurred    - Error when starting work item 000000390118
    PROCESS_NODE     - Error when processing node '0000000003' (ParForEach index 000000)
    CREATE                   -  Error when creating a component of type 'Step'
    CREATE_VIA_WFM  -  Agent determination for step '0000000003' failed
    EVALUATE_AGENT_VIA_RULE - Error in resolution of rule 'AC00000148' for step '0000000003'
    AC00000148             -  Object type 'TS' not valid
    Executing flow work item   - Work item 000000390118: Object FLOWITEM method EXECUTE cannot        be executed
    Executing flow work item   - Error when processing node '0000000003' (ParForEach index 000000)
    Regards,
    Hari

    Hello Hari,
    please set a breakpoint at function module
    ME_REL_GET_RESPONSIBLE
    and see what happends in section
        CASE t16fc-frgwf.
    * keine Ermittlung
          WHEN space.
            RAISE nobody_found.
    * Ermittlung über T16fW
          WHEN '1'.
    If using the T16FW-table, it should go to '1', otherwise it may that a user exit under '9' is used. So please check this.
    Best wishes,
    Florin

  • PO Release Strategy not changed after deletion of few line items with less

    Subject : PO Release Strategy not changed after deletion of few line items with less Total PO
    Dear Friends
    We have issue with PO Release strategy. We have created the PO. with release strategy  with multiple approvers.  After approval of first approval manager , one of the PO line item got deleted and Total PO value is reduced . The new PO value should have changed the PO release strategy. But it is not changed. Old release strategy only showing in the PO which is wrong. 
    Details of the PO
    PO no 4500000123 with 5 line items Total PO value : 100,000 USD Release strategy : AB
    PO line item 5 deleted. Now total PO value changed to 50,000 USD and the PO release strategy should have been changed to AA but not changed. Still showing PO release strategy AB only.
    Are there any OSS notes available to correct his bug.
    Please let me know if you need more details
    Thanks in Advance
    Thanks
    MVS

    Hi,
    release indicators  change it to 4.It may works. Please explore to all 6 indicators..........
    i.e,
    1-cannot be changed
    2-changable,no new determination of strategy
    3-changable,new release in case of strategy
    4-changable,new release in case of strategy or value change
    5-changable,new release if new strategy/outputted
    6-changable,new release if new strategy or value changed/ outputted......
    And check   Characteristic description and value in Classification  of Release strategies ........
    I hope this will help you. Thanking you.
    Regards,
    Venkat.

  • Item wise release strategy

    Hi Experts,
    I made item wise release strategy and used material group in class ,however when add this CEBAN-MATKL it doesn't find release strategy  when remove this release strategy is working  is it need to add something into material master data ?Need your advice
    Thanks in advance

    create release class, FRG_EBAN is available in system
    create release characterisitics .. here what ever name you give, you have to make it 'reference to table CEBAN' and corresponding CEBAN field , in additional data
    create a release group and attach the release class created
    create release codes, and while doing it you have to specify for which release group it is valid
    create release indicator , here specify the changeability
    create release strategy with release codes, release prerequisites, release statuses etc
    if you are transporting this, in the operational client, using CL24N  assign char values for each characterisitcs of release strategy. ( you need not assign char value when that characterisitic is not present int he document e.g.if account assignment is a char, then for release strategy for document without account assignment should not have any value for that char)
    if you ensure this much your release strategy should work ok

  • Release strategy determination for PO item level characteristic value

    Hi Experts
    I have user material group as release characterstic for PO.
    I have created two line items with two different material groups.
    How the release strategy determination occurs when the two different material groups are linked to two different strategies?
    regards
    ramSiva

    Hi,
    in this case system is NOT able to find the release startegy.
    Please take care of the following explanation (see note 365604)
    o  For OVERALL RELEASE (purchase order and purchase requisition) the
       item fields such as Plant and Material Group will be aggregated
       to header level.
       For example you use Plant/material group
    as one of your characteristics. If all
    items do not belong to the same plant/material group
    then
    *******the relase strategy will not be found***********
    unless you have maintained a blank value as one
    of your allowed values for the characteristic Plant/material group
    . If all items
    belong to the same plant7material group
    then that plant is aggregated to the
    header; if one or more is different then a blank is aggregated to
    the header.
    If you use an overall release strategy all
    characteristics which you have defined in the customizing (CEKKO-MATKL
    must have the same value. If one item has material class x and the
    other y the system does not know with which material class it should
    look for a release strategy. Now the system sets the material class
    to 'blank' and tries to find a release strategy. If you do not have
    defined a blank entry in the customizing (Transaction: OMGS
    : OLME >release procedure for PO > rel. strategy ) the
    system won't find a release strategy.
    you need
    to add a blank value to your allowed characteristic values in your
    release strategy.  To do this you can define a blank value in your
    characteristic (CT04).  On the values screen leave the char.value
    blank and add a description and save.  Now in OMGS you can select
    this value as an allowed value for the characteristic.
    (Example:
    To avoid this you can do the following:
    - go into transaction CT04
    - enter the characteristic 'CEKKO-MATKL'
    - click on the tab 'values'
    - set a flag in 'additional values'
    - in the column 'Char. value' do not enter anything
    - in the column 'Description' enter a text like 'no material class'
    - save this setting
    Now
    - go into transaction OMGS -> button 'release strategy'
    -> button 'classification'
    - double click on CEKKO-MATKL' and set a flag in 'no material class' )
    Please also have a look into the attached note 365604 point  2d).
    BR
    Nadia Orlandi

  • To  avoid deleted item of P.O in release Strategy

    Dear all
    We are facing a problem. our user deleting the line item of a P.O  and this is routed through release strategy. Is there any configuration that , any deleted item in P.O can by pass release strategy. Shall be grateful, if you could kindly urgently help me,
    Kind Regards - P.L.dey

    Thanks ....I have seen the structure for the PO release.I have gone thouogh the parameters of the function module of the user exit...But to me it is not clear how to incorporate the Deletion indicator of the PO item in the code...
    Hope to hear from you.......
    Regards

  • Item category control the release strategy?

    Hi,
    Currently the purchase of a material needs to be released.
    My issue is that as soon as I change the item category in the sales order,
    the material does not need to be released.
    How does item category control the release strategy?
    Sincerely,
    Ketan

    Hi Ketan,
    You can set item category in the characteristic of a release strategy.
    In your case, I guess the item category characteristic is already created. So you can just add the desire value into the characteristic.
    Go to SPRO > IMG > Material Management > Purchasing > Purchase Requisition > Release Procedure > Procedure With Classification > Set Up Procedure With Classification > Release Strategies
    Select the related release strategy, double click to view the detail. You will see there are 4 buttons in the bottom of the screen. Choose 'Classification' and enter you value of item category.
    Thanks & regards,
    JT

  • Processor of PR item level release strategy

    Hi All,
    I need to pass the Processor determined from an item level Purchase Requisition release strategy to a WF container.  The event is RELEASESTEPCREATED in BUS2009. I have created an import element container called 'Processor' from ABAP dict. data type  MEACTOR.
    In the binding for the WF trigger RELEASESTEPCREATED I cannot bind the 'Processor' wf container to the Event Object. 
    What are the steps which I must follow to add the 'Processor' to the RELEASESTEPCREATED event?
    The release strategy in SPRO for item level Purchase Req release is complete and the Set-up procedure for Workflow is complete.  
    Thanks
    Mike

    Hi,
    Go to SWO1, enter BUS2009. Click on create subtype icon there. Then enter all fields as say ZBUS2009. Now save your new BO. then implement and release it , i.e;
    Edit> Change Release Status> Object type> to implemented. Again Edit> Change Release Status> Object type> to Released. Then go to events in this objects. Click on event RELEASESTEPCREATED. Then click on event parameter and create a event parameter.
    Hope this solves your problem.
    Don't forget to delegate ZBUS2009 with BUS2009 in SWO6.
    Let me know if you have any queries.
    Regards,
    Raj

  • Release strategy for PR with multiple item category

    Hello,
    I'm trying to create a global release strategy for a PR based on the item category.   I have defined a caracteristic with different item categories (A and K).
    If I create a PR with item category A, the correct strategy is triggered as well as for an PR with item category K.  The problem is when I create a PR with 2 positions, one A and one K, there is no strategy triggered.
    How can I change my settings that there is also a strategy triggered in this case ?
    Thank you in advance for you help.
    Kind regards

    Hi,
    Solution is very small. Please maintain a blank entry too in the characteristics value. It will start working.
    Sanjeev

  • PR release strategy reset after change in quantity/inclusion of line item

    If a user adds a line item or increases the quantity of an existing line item to a fully released purcahse requisition, then the system does not render the PR for reapproval. Is there any way to configure SAP such that the release strategy resets if any of the above changes are made in a fully approved PR?

    Hi,
    the release strategy will ONLY be reset if one of the fields that are contained in your classification are changed.
    For example
    If you strategy is determined by Plant and value, if the plant or value doesn't change then the release strategy will not be affected.
    So if you change qty and do not change value then the release strategy will not be reset. This is a basic limitation of the design.
    But if you ARE changing one of the characteristic values of your strategy and you are saying that the release strategy is not being reset, then something else is wrong.
    Steve B

  • Release strategy - item level

    hii all
    can some body tel me , how and where we have to configuration for PR release strategy at item overview level.
    And the same item level release strategy is posssible to configure for PO also??
    If not y what is reason???
    Thanks in advance
    SAP-MM

    hi
    > how and where we have to configuration for PR release strategy at item overview level.
    http://www.sapstudymaterials.com/2008/08/purchase-requisition-pr-release.html
    >And the same item level release strategy is posssible to configure for PO also??
    hi we cant have itemised release for PO
    logically thinking PR can have multiple item and no fixed vendors and even not sure for placing order
    so the realing person will decide for the item to be purchase so it has itemised relase
    now in PO ,u will raise PO only when u have confirmed the purchase and the order will be for one vendor
    so for ordering u have to relese the whole po,
    or u can say u will create PO for all the items which have to procure so release will be for whole PO
    go to spro>MM>Purchase Requisition>Release Procedure  read the left side help for WITH and WITHOUT CLASSIFICATION
    Edited by: Kunal Ingale on Mar 9, 2010 6:32 AM

  • PO release strategy - blocking item

    Hi SAPers,
    I've put a PO release strategies on quantities and prices, my problem is that when i have many items in the PO, i don't see which one is blocking !!
    do someone know about a way to identify easily (for users) the blocking item, or even a way to flag the blocking item
    thanks
    zak

    Hi,
    The PO is always released at the header level and not at the item level as is the case with purchase requisitions .
    If you have put quantity as the characteristic  then it will add up the quanitity of all the line items and cheks whether release strategy is applicable.
    Kindly award points if helpful.

Maybe you are looking for

  • Windows Vista and Windows 8

    I have a Windows Vista Full Installer disc and a Windows 7 Upgrade Disc. I am currently running a Mid-2012 MacBook Pro 13" with Mountain Lion, Boot Camp Version 5. Can I install Windows Vista through Boot Camp, then upgrade to Windows 7 or Windows 8

  • Vendor Customer Clearing

    Hi, We have Customer in one Co. Code and Vendor in another Co. Code. Basically, it's finished goods AR & AP process. Line items between different Co. Codes some times match and some times NOT. Can anybody please let me know how we can clear these Ven

  • How can I force users to enter specifc format?

    I'm using Livecycle Designer ES2 provided with Acrobat X Pro.  I have a form where the age field is calculated from the date of birth field.  The date of birth field (DOB) is a date/time field.  The age field (Age) is a numeric field. Problem is: whe

  • Multiple day events

    I exported an .ics event from my work calendar and e-mailed it to my Mac at home. It was a vacation starting on Fri 12/18/2009 at 6:30 (when I start my work day), and ending on Mon 12/21/2009 at 3:00. My wife and I share our iCal via our .mac account

  • How to create an XML/RSS feed from a SQL recordset?

    I've been trying to find either a tutorial or extension that will allow me to take a SQL recordset, and create my RSS feed on the fly.  Not having much luck... anyone out there have a suggestion??