Equpment PRT actual hours consumption, confirmation
Hi,
Equipment PRT assgined to Maintenance Order operation. For the PRT created measurement counter of same unit as we defined in operation and the counter reading initialized . The same counter is assigned to PRT.
Now we need to confirm the actual duration of the PRT. How can i approach.
Send me any solutions if you find with screenshots or testing notes.
PRT Usage field: ARBI
Maintenance Order operation unit: HR (hours)
Measurement counter unit: HR (hours)
Regards
Chinnu
Hi,
Create the Equipment as PRT. Create Measuring point & counter plan for that equipment. Assign those in Equipment master.
Further more, assign that PRT in routing. Give the usage value & everything in routing. This will be done by PP guys. Based on the production confirmation, measurement document will be created.
Either running Deadline monitoring manually or automatically through background job, maintenance order can be created automatically.
Hope this will help you.
Regards,
Maheswaran.
Similar Messages
-
PM module- After upgrade ECCC6, Actual hours confirm displaying in PM order
Hi PM Gurus,
After Upgrade from 4.6C to ECC6.
I have ceated a PM order & done the time confirmation by IW41.
In Order - Opeartion Tab page , does not show actual hour confirmed for a particular operation.
But we can see Actual work hour in other way" Extrasu2014Order Documentsu2014Completion Confirmations"
Please provide if there is any OSS note is available for this problem or any other solution.
thanks
with regards
LokeshHi,
The intention is that this actual work field is only made available (on operation overview) for historical orders. For normal orders, confirmations are made and these figures are accumulated to give a 'actual work' value. This can be seen on the operation detail screen. It is never possible to enter data directly in this field.
It is possible this actual work field was visable on some releases at particular patch levels but this was an error. The table control settings allow access to this field but the program logic will always overwrite any user settings with ''invisable' setting for this field.
A modification would be required to make it visable.
-Paul -
Batch wise actual material consumption and activity cost
hi
my client is steel industry, client requirement is heat wise actual material and machine cost. Heat is a batch number, how i can check batch wise actual material consumption and machine cost.
regards
imdadHi Imdad
Whats the batch definition in your case?? have you designed One batch per Prod order or One batch per GR?
If its one batch per Prod order - you can directly see the prod order.. however, chances are less for this as Steel company might be using PCC i.e. repetitive mfg
If its one batch per GR - Then you will have to track using the Confirmation no because each Confirmation will trigger the Goods Issue and Activity Confirmations...
Using Table AFRU - You can track the individual Confirmation no and also the Activity Qty confirmed....COSS / COSSD will have the Activity Cost
If any goods mvt are posted during the Confirmation, you would see a Mat Doc No populated in the field "Mat Doc"
Br, Ajay M -
Actual hours impact on Variance analysis
Hi:
When we talk about actual activity hours then in how many ways it can impact variance calculation. We have aggregated our work centers and hence define an aggregated machine hour for it. Is it ok? E.g
A work center X constitute of 3 machine aggregated
A
B
C
Machine hours has been entered in for X after combining the hours required by A,B,C . Please guide.
BrHi:
May i please know the advantages of entering actual hours at process order confirmation time. At client side they have a practice of entering the same hours as shown planned in CORR. They do not enter standard hours. Moreover may i please know the impact planned hours correct entry in operation. Please guide me.
Br -
Actual Hours difference between IW38 and IW47
Hello all.
I have a unique situation that I am trying to handle. Am trying to see if someone here knows what is happening.
I have a Work Order. In the "Costs" tab and in the "Quantities" Sub tab
Planned hours of Word=36 hrs
Actual Hours=35 hours.
But when I run IW47 to see all the confirmations to this order, it only shows 3 confirmations totalling 14 Hours.
While in the order the actual hours is 36. I am not sure what happened to the remaining 21 Hours. Can someone please tell me what else could be going on here.Hello,
I was also facing the same issue for actual work hours difference in iw37 and iw48 .
But following sap note has solved the problem.
146929
Missing or incorrect actual values in activity
Cheers!!!!
Regards,
Piyush -
ML81N- actual hours show up as 1 ACT on PM order
Hello all,
When confirming hours via service entry sheet the actual hours that were posted disappear in the actual posting the PM order.
In ML81N i confirm 3 line items,
line 1: 2H on 15.02.2010
line 1: 6H on 16.02.2010
line 1: 4H on 18.02.2010
All these confirmations are displayed on the PM order as 1 ACT. The thing is, when using ML81N and cofirming towards a WBS element, the Hours DO show up when checking the postings on the WBS element...and not everything is combined into 1 ACT.
I suspect this has to do with the settings in the service master or maybe the customizing regarding completion confirmations or maybe even with the setup of the PO. But so far i have not been able to discover the cause of this issue.
I hope somebody can help me.
Thanks in advance for your help
Kind regards,
PeterMore information:
I have tested several scenario's and i have determined thatit has to do with the PO created. I have found 1 PO that gives me the desired result (the good PO). I tried to copy the PO exactly, but i can not get it to work:
I believe i made the same settings
Account assignment: U
Item category: D
no usage of service master
Good PO:
Booked on WBS element directly: hours show in CJI3 on actual postings
Booked on PM order: hours show in actual postings of PM order
My own PO:
booked on WBS element directly: hours do not show in CJI3. booking is 1ACT
booked on PM order: hours do not show in PM order. Booked is 1 ACT.
The service ordered is different between them. so different vendor, service, material group. but i can not imagine that that's the reason.
I hope this information will help you finding the solution
regards,
Peter -
Idle hours in confirmation in CN25
Hi Experts,
How do i calculate the idle hours during confirmation.
For eg. if for completion of a particular activity it requires 8 hours in a day and if labour are only devoting 4 hours working and remaining 4 hours he is remained idle due to some training issue, then how will i calculate cost seperately for the idle hours and costseprately the 4 hours which he utilized in working in confirmation screen in CN25.
Any help will be appreciated
Regards
SimonHi
Thanks for inputs,
The scenario which i am facing is that, though the employee was present for the entire shift i.e for 8 hours but due to some emergency he needs to devote half the time i.e 4 hours in training and 4 hours in completion of the work. Now my client want that he should confirm 4 hours which he actually devoted on the work so that the cost can be calculated and the remaining hours i.e 4 which is he attended for the training needs to be confirmed as well and the training 4 hours should not effect the actual costing of that particular activity but should be shown seperately as the labour cost incurred for training.
The issue is the time not spent on the actual work and it could be training or machines not working or any other cause.
look forward for your inputs
Regards
Simon -
Hi,
How the production order actual hours is calculated? In which tcode can i check the actual hours took to complete a production order?
In my scenario, the order wise confirmation is done (CO15) not the operationwiese.
Kindly help.
TIA,
SabithaHi,
In milestone confirmations, planned activities are always posted on the basis of the confirmed quantity. If you have entered activities manually during a milestone operation, planned activities are also confirmed when the preceding operations are automatically confirmed. The exception to this is the setup times, which are always confirmed fully, independently of the entered quantity
You enter a confirmation of 7 pieces for milestone operation 30, which has a planned yield of 10 pieces. Operation 20 is confirmed automatically. The planned machine time for operation 20 is 40 minutes, therefore a machine time of 28 minutes is confirmed
For display of conformations please refer to this link
http://help.sap.com/saphelp_47x200/HELPDATA/EN/b1/c04dd1439a11d189410000e829fbbd/frameset.htm -
Order wise-Planned hours VS Actual Hours report
Hi,
Is there any report which shows me the Orderwise Planned Hours VS Actual hours.
Regards
SBSB,
Have a look at TCode IW37N (Order/operation overview) and display the Work and Actual Work fields.
You can probably use IW37 too..
PeteA -
Plan v/s actual materail consumption report for production order - urgent
Dear all Hi,
Is there any report or T code from which i can get the plan v/s actual material consumption for a production order or wbs element after completion of order, please suggest / help, the requirement is very urgent.
thanks in advanceHi shaiz,
You can get that in COOIS tcode
Select components again List
then give the plant,Order details
execute
You can find 2 fields reqmn qty(nothing but planned) & qty Withdrawn(Actual consumption) in the report
Hope this hepls
Rgds,
SVP -
How Actual hours for a Particular Activity is getting Calculated in CJ20N?
Hi Experts,
i have a small issue in PS module.In Cj20n after creation of project, under the activity the actual hours are differing from those of CATS hours.How or from where the actual hours are getting populated.The value is getting stored in AFVGD-ISMNW.
Plz help............hi
have you transfering the actual time after entering and approval to the PS. by the t code CAT5 - Transfer -
How get the actual hours worked by the employee in SAP.
Hello Experts,
How to get the actual hours worked by employee in a month.( Any infotypes or tables or fm)
I have report to get planned hours of the employee
Thanks and Regards
ReddyHello expert,
I am a technical guy, I dont have functional knowledge and HR functional support is not available at the moment..
I have requriement to develop a report to caluclate the actual night shift hours worked by the employee...
I have report : RPTEDT00 where in I have actual hours worked day and night..
But I am not able to find how do in my custom program from the program reference...So I want to know is there any way where in I see this data in tables or infotypes
Thanks and Regards
Reddy -
Total Planned and Total Actual Hours for service order
Hi,
Is there is any table in which I can directly find the Total Planned and Total Actual Hours for service order.Pl suggest.
Regards
SBSorry SB, didn't read your post properly... I thought it was costs you were after...
AFVV holds the total actual work at operation level.
PeteA -
CAT2 - Actual hours exceeds Planned hours.
Hi All,
I am maintaining seperate data entry profile for Time Administrator. When i posted time entry for a subcontractor using the time administrator profile, it throws error message saying "Actual hour exceed Planned hours". I had checked the planned hours in CJ20N for the personnel no. it has surplus hours.
Then why it showing error message.
Regards,
Shadeesh.GWhat is CJ20N ?
We see the message "Actual hour exceed Planned hours" as a warning when the number of hours entered in CAT2 exceeds the Planned Hours in the employee's Daily Work Schedule.
Are you getting a "Warning" or an "Error" ?
Warnings and Errors are part of Time Management configuration. For example, if you use IT2005 to record Overtime, you can select "NoMessage/Warning/Error" through the Daily Work Schedule (V_T550A). -
PP - Cube for Actual Capacity Utilization (in hours per confirmation)
Hi,
I need to extract the exact operation confirmation times for PP orders from ECC6. For example, if a single order started at 11:00am and then was confirmed twice before being finished in the evening, the client wants to see the actual times used for each operaiton. This way they want to subtract from 24 hours and see the idle time of the production operation.
For this purpose I have checked all the cubes under 'Production/process orders' infoarea. The cube '0PP_C03 Plan/Actual Comparison Operation/Work Center View' seems to have the operation time but in days. This is first of all causing a rounding off problem and secondly it does not show the time gaps between confirmations on the same operation.
Any help will be highly appreciated.
Regards,
Adeel HashmiHello ,
Method 1 :
1- Create a one Multi provider .
2- Copy the standard cube 0PP_C03 and make your own Cube with necessary fields ( enhance it as per your requirement ).
This New Cube should be Virtual Cube .
3- Create a Report on Mutiprovider ( which you created in step1 )
4-select the relevant char and key figure as per requirement .
5- you can use the selection and formula in report for time difference ..
In this method restrict the query on virtual cube only .
Method 2 :
From R/3 you have record like this :
Operation 1( O1) ---> 11:00 :00
Operation 1( O1) --> 14:00:00
Operation 2( O2) --> 10:30:00
Operation 2( O2) --> 13:30:00
1- Create a one Key figure with Data Type TIMS .
2- Include this key figure in the Cube which you have created in above steps ( Method1 )
3-Write a routine to fillt he data for Keyfigure ..if O1 record find calculate time difference .
4-Now you have time difference in BW for operation
5-Add new keyfigure in MP and use in Report .
Hope this helps .
Regards
Vikas Sharma
Robert Bosch
Maybe you are looking for
-
Transport Error-The creation of the export DataSource failed
Hi Experts, I am transporting a DSO from DEV to QA in 7.0 system.While transporting the DSo i am getting the below mentioned error. The creation of the export DataSource failed Reading the Metadata of APMD0009 ... Creating DataSource 8APMD0009 ... Pa
-
Network home folders: iCloud password question re-appears at every logon
Hello, Is there any way to enable iMessage and Facetime together with Network home folders. Im using Mavericks server (Directory services enabled) and two Mavericks clients. Every time a user that was using machine A logs on to machine B the iClouds
-
Project Locked by another user
Ok, I kind of broke my MacBook Pro and had to buy another one. I took the HDD out of my old MacBook and connected it to my new MacBook through a SATA to USB converter. I am trying to get my iMovie projects off the old drive but it tells me that the p
-
Problem with printing report document issue
hi i want to implement "Print all" button functionality in my simple school management software where the report printing of whole students of same class can be done with a single "print all" button function. how can i implement this? i am lacking lo
-
Failed to retrieve data from the database. [Database Vendor Code: 916]
I am recieving this error when the report is called from my asp.net application. Out of 50 or so reports, this is the only one that I am having an issue with, and I imagine the reason is that the strored procedure it calls joins to a 2nd database fo