ERP Project Planning Webcast
If anyone on here works for a company or client that might be interested, my company is hosting a free webcast on ERP project planning for success. Topics to be covered include effective vendor selection, implementing a successful Benefits Realization and ROI program, improving business processes, and leveraging organizational change management.
To learn more, you can visit www.panorama-consulting.com/erpwebcasts.html
Feel free to contact me with questions at [email protected]
Regards,
Eric Kimberling
President
Panorama Consulting Group LLC
www.panorama-consulting
Hi Jassim,
what I can suggest is to take a look at this
ebook . It's an easy task for you to get start. Also a good resource :
Develop Web ERP Software using ASP.Net 3.5, C# & SQL Server
Hope them help.
Best wishes,
Helen Zhou [MSFT]
MSDN Community Support | Feedback to us
Get or Request Code Sample from Microsoft
Please remember to mark the replies as answers if they help and unmark them if they provide no help.
Similar Messages
-
Integrating project planning software with business planning systems (ERP)
Hello there
I have been trying to obtain information about "integrating project planning systems with business planning systems (ERP, PLM)" but I could not find any proper source. Would you help me out on this?
I would like to focus on what benefits can be expected from a close integration of project planning
tools and enterprise information systems such as ERP and what evidence is there that
this is being exploited. If you can help me out with proper sources, I would be appreciated.
Best RegardsHi,
As per my understanding i think you would like to know the benefits of integrating your legacy Project Planning system with the ERP system. Please correct me if am wrong. If that is what you require, please search the forum as i am very sure that there are threads that explain the benefits of integration.
Regards,
Gokul -
SAP IDM 7.0/7.1 Project Plan and Architecture Landscape Diagrams
Need help in identifying whether there is anybody that has a generic project plan along with resources needed in implementing IDM 7.0/7.1. I am also looking for a generic landscape diagram. Any help would be appreciated.
Matt,
Interesting question and one that I think we can answer, but we need a few specifics first (even for a generic)
1. Are you using 7 or 7.1? This is a biggie since there are big differences in implementation.
2. What's your source for Identity data? What are your targets? Even a basic of (Source is HR, targets are ERP, LDAP and badging app)
3. What workflows are you implementing?
4. What is your development approach? Dev / QA / Prod? This can be important too.
For architecture info, take a look at some of the documents available from SAP.
Anyway, a very generic would be:
1.0 Identify requirements
1.1 Sources
1.2 Targets
1.3 Workflows
2.0 Development Environment
2.1 Install Core Components
2.2 Install IdM
2.3 Connector creation
2.3.1 Source (X)
2.3.2 Target A
2.3.3 Target B
2.4 Workflow creation
2.4.1 Notification Tasks
2.4.2 Self Service Tasks
2.5.3 ...
2.6 Unit Testing
3.0 QA
Feel free to contact me if you have further questions -
ERP project - one project?
Hi, I am planning to develop an ERP project for Windows using Visual Studio 2008? I just wanted to know what's the way to do it? is it just one project or many projects in one Solution? or it's many Solutions?Jassim Rahma
Hi Jassim,
what I can suggest is to take a look at this
ebook . It's an easy task for you to get start. Also a good resource :
Develop Web ERP Software using ASP.Net 3.5, C# & SQL Server
Hope them help.
Best wishes,
Helen Zhou [MSFT]
MSDN Community Support | Feedback to us
Get or Request Code Sample from Microsoft
Please remember to mark the replies as answers if they help and unmark them if they provide no help. -
Integrating project planning software with business planning systems (PLM)
Hello there
I have been trying to obtain information about "integrating project planning systems with business planning systems (ERP, PLM)" but I could not find any proper source. Would you help me out on this?
I would like to focus on what benefits can be expected from a close integration of project planning
tools and enterprise information systems such as ERP and what evidence is there that
this is being exploited. If you can help me out with proper sources, I would be appreciated.
Best Regards
Edited by: warhammer on Jul 16, 2010 10:14 PMDear Warhammer,
Please find some useful info in the following links.
1.http://wiki.sdn.sap.com/wiki/pages/viewpage.action?pageId=56766
2.http://directory.partners.extranet.microsoft.com/collateral/4956/MSP_SAP_Integration_TheProjectGroup_e-v1.ppt.
Regards
Prasad K
Edited by: Prasad K on Jul 19, 2010 5:28 AM
Edited by: Prasad K on Jul 19, 2010 5:32 AM
Edited by: Prasad K on Jul 19, 2010 5:32 AM -
OBIEE 10g to 11g Upgrade Project plan
Hello All,
I am a technical consultant working on OBIEE/OBIA and the management needs a project plan for upgrading OBIEE suite 10g to OBIEE 11g (11.1.1.6).
Can you please share some details as -task list and approx hours required. I have a rough idea of task list in terms environment setup, installations, configuration, custom code migration, testing etc. I want present a professional plan that is being followed by others. Dont want to look odd one out. Your help is appriciated.
Thanks you !See this in the log:
*02712: Expected oracle.biee.admin:type=BIDomain.BIInstance.ServerConfiguration,* Oracle instance, found 0*
You will have to look into why the upgrade utility isnt seeing any instance recognized - it will only work with 1 instance registered and for some reason it cant find any in your configuration.
You could try looking in Oracle® Fusion Middleware Error Messages Reference 11g Release 1 (11.1.1.6.0) for details on the error.
Ensure the service instance name is present in jps-config.xml. -
Dears,,
One of our clients uses Google Chrome
as their standard navigator to open PWA 2013 that we have deployed for them.
Every thing went fine until we tried to open a project plan using Project Professional 2013 from PWA using the Edit in Project Professional option, we had the below error:
"Project Web App was unable to find the specified Project.
the project was not found on Project Web App. some possible reasons include:
The Project has not yet been saved successfully to the server.
The Project has been deleted on the server.
you don’t have adequate permissions to open this project.
if the project is available in the local cache, you can click the globe in the status bar and select "Work offline", and then open the project, if the problem continues, contact
your administrator."
Please note that IE is working fine with this scenario,
the belwo screenshot shows the error that appears to the users.
Ibrahim Al-Masri Technology Manager at MethodCorpHi All,
As Gary and Guillaume suggested, have you tried to install IE tab extension for chrome?
See the link below:
http://www.ietab.net/
and also im with what Dale has posted
(why don't you just tell the PM to use Internet Explorer instead of Google Chrome?
I suspect that this problem reveals that PWA does not work perfectly in browsers other than the Internet
Explorer,
so I would simply mandate that all PMs and TMs need to use Internet Explorer for Project Server.
Just a thought. Hope this helps.)
from my side , i have tested it and it works perfect.
Karim El Zarka, MCTS Sharepoint 2010 , MCITP SharePoint Administrator 2010 Whenever you see a reply and if you think is helpful, click "Vote As Helpful"! And whenever you see a reply being an answer to the question of the thread, click "Mark
As Answer -
Project Server 2010 Timesheets not Updating Project Plans
We have several project plans that are not getting updates from approved timesheets.
Troubleshooting steps I've taken:
1) Verified the timesheet/task submissions by the resources
2) Verified they have been approved
3) Verified they have been accepted by the Status Manager and processed
4) All project plans have been published (I even used ProjTool ON the App server to do a full publish of all plans as a second step of publishing)
5) Verified OLAP was built successfully overnight (and every night)
6) Tasks have both remaining work and NO actual work in the Resource Usage view
7) Had a user recall and resubmit his timesheet using "Send Timesheet" to see if the task updates would come through - they did not (I am Status Manager and the timesheet shows Approved), and even published the plan and rebuilt the OLAP again,
just in case.
8) Verified that no tasks are marked for closure under Close Tasks for Update in Server Settings.
9) Verified Timesheet shows Actual Work on the Tasks via Pivot Table; compared Timesheet_User_View with MSP_Portfolio_View pivot table for project which shows 0 hours. Timesheet_User_View shows 33 hours.
All tasks have Remaining Work, are within the date range of the timesheet and are open for submitting time. Timesheets are still out of sync with project plans for many users and there is no apparent reason. I'm out of ideas!Hi,
In status manager's approval center, history, status updates, can you check the status of the approval? Do you have any errors in the ULs log for the approval or publish jobs?
Hope this helps,
Guillaume Rouyre, MBA, MVP, MCP | -
Issue while saving the project plans into XML
Hi,
Could anyone of you please help me here.
We are having one custom field(Type: Text) in the project level(Custom field name: ProjectComments) and end users are entering the data against this custom field more than 200 characters.
The problem here is when we are saving the project plans into XML and opening the same file again thorugh MPP, the data for this custom field(ProjectComments) is showing till 129 Characters only. Seems to be the data is truncating till 129 charachers.
Could anyone suggest me how to resolve this issue without trucnating the characters in the custom fields.
Thanks in advance!
Regards,
VenkatHi,
I cannot reproduce this issue with Project Pro 2010 SP2. Which SP do you have? How is configured your custom field?
Hope this helps,
Guillaume Rouyre, MBA, MVP, MCP | -
Can a Column in a Project Plan be set to Read Only for everyone except Admins
At my company the Project Server Admins create the initial project plans. We want to add a new column that will designate each task in the plan as Capital or Operational. We do not want anyone to have the ability to change these.
When the Project Managers need additional tasks on their plans they will need to copy an existing one in order to have this piece of information pre-populated on their new tasks, since we do not want them deciding what the task should be themselves and populating
the field as they create tasks.In addition to Dale's excellent answer, I'd mention that it is possible to make a column "read-only" for certain security groups in MS Project Pro with VBA code.
That being said, I'd suggest to follow Dale's advice using a "soft" solution.
Hope this helps,
Guillaume Rouyre, MBA, MCP, MCTS | -
MS Project 2010 Server
How to move a single MS Project plan and it's SharePoint project site from a PWA server to another PWA server (one at a time)
I have 2 Project PWA servers, i know how to copy all the databases (Publishing, Draft, Reporting, archive, content) from one SQL server and copy it to the other PWA server so both server can be identical.
I need to only move a single project from a PWA server to another,
Moving the Project plan, actual time data, SharePoint site with all it's content
Is there a 3rd party tool that can be added on to the server to help me move single project plans? to different PWA servers?
-IsaackVisit my friends at FluentPro and try FluentBooks
http://www.fluentpro.com/productsfluentbooks2013.html
they have a 2010 version also.
Hope that helps,
Thanks, Eric S. Pcubed -
Error in saving project plan in project server 2007
I am getting following error when I try to make a change and saved the project plan. It has happened several times since yesterday. Not sure if the file is corrupted.
Is it possible to make a copy of the file and mark the current file as inactive?
The File cannot be opened.
Check that the File name and path are correct.
Check that the File format is recognized by Project.
Project Files saved in a version earlier than Microsoft Project 98
can't be opened.
If your File is From an earlier version, open it in that version, click
Save as (File menu), and save in MPX Format Open the MPX File. When
you use this method, project data is imported, but Formatting is lost.
Has any one has same issue? any suggestions please reply.
Thanks-Hi Micahel,
Thanks for the posting!
what would be solution inorder to make it working.i was looking at some posts which i listed below for some it had worked....i did not try it but just guessing it would work
1. Launch Project Professional 2007 and connect to Project Server.
2. In the new blank project (Project1), click Insert - Project.
3. Select the troublesome project.
4. DESELECT the "Link to project" checkbox and then click the Insert
button.
5. When prompted to save the changes to the troublesome project, click the
No button
Or in another case it may be
Saving as a template with re-open is a smart work around, typically when a network connection gets dropped. In these cases
we have copy/pasted to a new file, or, saved as XML and then reopened.
I appreciate any kind of help on it.
Thanks
Tummala -
Best Practice for Using Static Data in PDPs or Project Plan
Hi There,
I want to make custom reports using PDPs & Project Plan data.
What is the Best Practice for using "Static/Random Data" (which is not available in MS Project 2013 columns) in PDPs & MS Project 2013?
Should I add that data in Custom Field (in MS Project 2013) or make PDPs?
Thanks,
EPM Consultant
Noman SohailHi Dale,
I have a Project Level custom field "Supervisor Name" that is used for Project Information.
For the purpose of viewing that "Project Level custom field Data" in
Project views , I have made Task Level custom field
"SupName" and used Formula:
[SupName] = [Supervisor Name]
That shows Supervisor Name in Schedule.aspx
============
Question: I want that Project Level custom field "Supervisor Name" in
My Work views (Tasks.aspx).
The field is enabled in Task.aspx BUT Data is not present / blank column.
How can I get the data in "My Work views" ?
Noman Sohail -
Read only Sub Project Plans checking out in EPM
Hi all,
Has anyone working on Project Server come accross an issue where sub project plans inserted as 'Read Only' in a master Plan, check out and therefore prevent other access? Working on Project Server 2010 with Project 2010 SP2
clients.
The strange thing is that its not every single plan in a master that performs in this manner.
Has anyone seen this behaviour and does anyone know any fixes?
Thanks,
-CL.We've always had security on, the only thing that changed was my understanding of how we were doing security.
Before, I had written a custom UserCC that always returned the same name, after I used the standard UserCC. I had the same results both time.
The cause of my error message is "MDS repository may be configured incorrectly", which I kind of figured, but there's nothing to point me to diagnose how it is incorrectly configured or how to fix it. -
Hi,
We have enable "Protect User Updates" option from PWA->Task Setting and Display->Only allow task updates via Task and Timesheets, to protect actual efforts in project plan that PM changes manually, however in some cases we need to allow actual
effort changes in open projects so it there any way or workaround so that Administrator or PM can make changes in actual even though "Protect User Updates" option is enable. Please Help!!
Thanks,
RahulHi Rahul,
Indeed when this option is activated, there is no way to directly update actual work in the project plan.
The workaround is to temporary deactivate this option, more preferly not during office working hours to avoid unexpected project updates.
A better workaround would be to ask the resource to recall, correct and submit again the timesheet, so the PM can approve an updated actual work. Finally the PM can use delegation to rscall and correct the timesheet for the resource.
Hope this helps.
Guillaume Rouyre - MBA, MCP, MCTS
Maybe you are looking for
-
Camera lock screen iPhone 5S not working properly after upgrade to iOS 8.1.3
Actually, i upgrade my iPhone to 8.1.3. What i am trying achieve is, when my iPhone is locked i just need to access my camera without login. When i open camera when my iPhone is locked, camera displays for 2 seconds and then my screen will be black.
-
In Day view, how to jump to next month
I've just updated to 10.7 and while there are so many things that annoy me about this iCal update, I'm going to try and focus on some very straightforward user interface options that were both solid and useful in 10.6 (and practically every other cal
-
When I try to start the windows tech. prev. installation on a virtual machine (running dynamically expanding hard disk and using 1500MB ram) the windows logo appears, but shortly after says the following message: Your PC needs to restart Please hold
-
when I type a document and try to save it, there are black lines over my sentences, as if it had been highlighted, and that's how it prints out, just black lines
-
ICal to Outlook Calendar moves event by one day. Why?
Hi If I create an event in Outlook Calandar (2011 for Mac, Sp1) it arrives via Syn Services on the correct day in iCal ......... Great! But If I create an event in iCal it arrives in Outlook calandar one day out .............. Why? HELP Please.......