Error Activation of all work flow templates

Dear Folks,
Accidentally there is a big hurdle before me, I have found that all my event linkage's are active in swe2 for almost all the work flow templates. please help me how could such a situation araise with out even activating any thing from SWDD.It happened in Quality & PRD only.
Please help ASAP unwanted work flows are generating.
Thanks and Regards,
Krishna Mukthineni

HI ALL,
The cause of issue is not yet identified however, there is a solution for deactivation / activation from DEV .
Go to SWE2 and in the menu option we find the Transport option, copy all the line items/Records into the Request and place for importing into the desired server. Since it is a maintenance view please be care ful of changing the entries of the table manually rather please follow the method mentioned above.
Thanks and Regards,
Krishna Mukthineni

Similar Messages

  • Work flow template download error

    Hi Folks,
    I am trying to down load work flow template but its giving me this error please help me out
    " No Import Filter Was Found To Import the XML
    Document Chosen. Do You Want to Display the XML
    Document?  "
    what need to be done.
    Thanks in advance for the help
    Krishna Mukthineni

    HI folks ,
    Any help please ..
    Thanks
    Krishna Mukthineni

  • How To Activate Work flow Templates for Campaign Automation

    Hi friends,
    i created all settings for campaign Automation.when i click start process the system showing message like campaign has not started.i am not sure about weather work flows should activate for starting campaign automation.
    can u please let me know how to activate work flows and what is the path to activate work flow templates for campaign automation
    Thanks&regards
    kishor kumar

    Pls forward to me as well, facing the same problem unable to start Campaign Automation.

  • How to create a work flow template

    HI
    how to create work flow template using EP.
    I am new to this division of  EP .
    Could some please give me a head start to go with this
    some how to docs or weblogs
    thanks
    pk

    Universal Worklist Configuration
    http://help.sap.com/saphelp_nw04s/helpdata/en/0c/19dfc6febc4f888701697ef23b16cd/frameset.htm
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/com.sap.km.cm.docs/library/xi/xi-how-to-guides/how to configure the universal worklist.pdf.
    Patricio.

  • Work  Flow Template and Work flow tasks

    Hi,
    Work  Flow Template and Work flow tasks are the two objects which are found surprisingly in our client system(when we go to PP01/ HRP1000 IN SE16 ).My employer wants to know what these are:
    Can any one please tell me about "Work  Flow Template and Work flow tasks".
    are the SAP Generated?
    Can we delete them if we don't need?
                                                                                    Thanks in Advance
                                                                                    Gopi Palleti

    Hi Gopi,
    Workflow Template and workflow tasks are part of SAP Business workflow.
    A business workflow is an executable process embedded in SAP applications that you use to automate business processes. 
    You can find more info here.
    http://help.sap.com/saphelp_nw70/helpdata/en/c5/e4b62c453d11d189430000e829fbbd/content.htm
    Regards,
    Sharadha

  • Work flow Template

    Hi Experts,
              My scenario is I need to create an Process code based on Function module and when the process code triggers it will automatically fetch the work flow template.
    So what are the import, export parameters are need to call the WF template using Process code[Function Module].
    Thanks.

    for exampe, u can use this function:
    CALL FUNCTION 'SWW_WI_START'
                  EXPORTING
          CREATOR                            = sy-uname
          PRIORITY                           = '5'
          TASK                               = 'WS74508518'
        IMPORTING
          WI_ID                              = wi_id
        TABLES
          AGENTS                             = agents
          WI_CONTAINER                       = wi_container
       EXCEPTIONS
          ID_NOT_CREATED                     = 1
          READ_FAILED                        = 2
          IMMEDIATE_START_NOT_POSSIBLE       = 3
          EXECUTION_FAILED                   = 4
          INVALID_STATUS                     = 5
          OTHERS                             = 6
    where agents is internal table with agents like SWHACTOR (otype, objid)
    and wi_container is workflow container with pairs (element, value).
    U can fill it with macroses from include <CNTN01> (swc_set_element, SWC_SET_TABLE).
    U can use function's SAP_WAPI_START_WORKFLOW , SWW_WI_START_SIMPLE too, or start the event wich start WF (function SWE_EVENT_CREATE)

  • Toad Error after installed Oracle Work Flow Builder

    Hi,
    I have using Toad 9.6.1 version. I installed newliy Oracle Work Flow Bulider 10g. After installed when i trying to open Toad it is giving Access Vioalation Error.
    Please advice what may be the reason and how to correct it.
    Thanks

    Hi,
    Did you use exsisiting oracle_home while installing workflow builder? if yes then may be reinstallation of toad is the soluiton.
    Is toad throwing error at startup or when you fire any query? and what is complete error message...
    Thanks,
    JD

  • How to set active version for work flow

    hi ppl,
              I have 3 versions of my work flow i want to set the second version to be the active version how do i do this ? . plz help me out.

    WF builder choose your second verion & choose <i>Workflow -> Activation -> Generate and Activate runtime version.</i>
    This will make it second version as active verion.
    <b>*Reward each useful answer</b>
    Raja T

  • Work flow template creation

    hi
       Whn i try to create a new worlflow template (pftc) and while saving i m getting error message saying: Prefix number: entry missing for system RRD client 100.
    pls giv me the solution.
    is it necessary to configure.
    thanks in advance

    Hi Prabhakar
    You need to do the config in SWU3 first. Prefix number is like a number range for customised workflows, this needs to be set up along with other essential things. Go to SWU3 and click Auto Customising....
    Good Luck
    Ravi

  • Old Version of Business Object & work flow templates

    Hi,
    I deleted few methods and commented some code in an existing business object for some issue.Now I want to call back the older version. How can I do this? 
    Similarly I did some changes to an workflow template and now want to re-call the older version .
    How can I do them both.
    Thanks
    Kiran

    Hi,
    First retrive the corresponding request of those objects from SE03 or SE09 transactions
    and reimport them from your PRD or QAS  system.

  • While Processing one ASN in EBIZ we are getting below work flow error.

    Hi Gurus,
          while processing WF details , i am receiving following erorr in one of node process. Can you please give any sugessions from your end why this error will come and resolution ways.
    thanks in advance
    issue details are below :
    Error Stack Wf_Engine.CompleteActivity(NVISPASN, 36562, STOP)
    NVISP_EDI_856_PREPROCESS_PKG.CompleteParentStop(36562-100101309584-1)
    Wf_Engine_Util.Function_Call(nvisp_edi_856_preprocess_pkg.CompleteParentStop,
    NVISPASN, 36562-100101309584-1, 230620, RUN)
    for ref please find below screen shot.
    and we retry same work flow by clicking retry button on the screen.
    so the work flow was completed successfully.
    and processed one more ASN for this ASN also got same work flow error.
    could you please suggest the solution to avoid this error.
    it is customized work flow but we are getting WF standard error.
    thanks
    raghava

    According to error, it appears that child flow activity trying to push the parent flow notified activity. Could be that parent flow is not ready/notified when child tries to push it.. Check for timings of 1)  begin and end times of child activity 2) begin & end times of parent activity . If this is timing issue, add defer activity for child flow to wait till parent flow comes to required status.

  • Regarding Production order changes work flows

    Hi to all,
    I activated WS20000387 work flow template. its regarding the production order changes .
    briefly: i created one production order, immediately assigned person will get a message in his SAP inbox.
    he has to double click/execute on that mail, then system will take u directly to the production order screen. there is no need to enter that Order no.
    but here, after double clicking, system is asking The Order no.
    we have clients 300,500 and 700.
    i executed same work flow in 300 successfully,
    700 is not modifiable. thats y i did all the settings in 500 and copied the request to 700.
    i am getting  the problem in 700,, i compared all the settings in 300 and 700, but no use,,,all are same,,,but not executing in 700.
    anybody can help me in this regard.

    You Can use below FM to confirm Production order and it is very simple BAPI.
    BAPI_PRODORDCONF_CREATE_HDR -> just check in where used list.
    Thanks
    Seshu

  • Std Work flow for Invoice Parking & posting

    I am working om std SAP workflow for invoice document parking :
    I have done the following activities :
    1. Activate Work flow Template for Document Completion
    Here i activated the event "Complete the Parked Log. IV Document"--> Incoming Invoice Document Parked. It is showing a green traffic light .
    In agent assignment
    Complete the Parked Log. IV Document>Complete the Parked Log. IV Document>Complete the Parked Invoice--> i have assigned the user MMCONFIG
    2. In Define Release Criteria i have the following settings :
    1000 H Credit 0.01 INR US MMCONFIG
    1000 S Debit 0.01 INR US MMCONFIG
    3. In Activate Workflow Template for Release for Posting
    Here i activated the event Incoming Invoice Complete: ReleaseRel & i m getting a green traffic light .
    In assign agents i did the following
    Release the Completed Log. IV Document>Release the Completed Log. IV Document>Release the Completed Log. IV Document i assigned the user MMCONFIG
    In Invoice Parking: Approve Release i assigned the user MMCONFIG .
    For Invoice Parking: Release Invoice
    Invoice Parking: Posting an Invoice " I AM NOT ABLE TO ASSIGN ANY USER AS THESE ARE BACKGROUND TASKS ".
    Now when do a MIR7 - Park invoice & save the invoice as complete i am getting a mail in the mail box of MMCONFIG saying :
    "Invoice Release 5105xxxxxxx 2009, Completed by MMCONFIG "
    I go & release the same invoice .
    Then i executed MIRO & tried posting the released invoice . The sysem doesnt allow me 2 post the invoice .
    It automatically goes to MIR4 transaction & forces me to save as complete
    if i try to post it the system says "Parked document is release-relevant and cannot be posted"
    Pls tell me how can I post the invoice & IF MY SETTINGS FOR THE WORKFLOW IS OK ???
    Regards
    Anis

    Firstly,  check with the Binding of the event and workflow, if they are fine
    then check if the workflow gets triggered when you are posting... to check this,
    First go to transaction SWU8 - turn on the workflow trace and then
    Proceed with posting the invoice
    go to transaction SWU8 again and then turn off the workflow trace
    go to SWU9 - to check which all workflows got triggered....
    If there is any workitem in your workflow, then go to SWI1 and select the workitem of that workflow and press shift+F8 to check the status of it and also check to which all agents it had sent...
    If possible just give a hardcoded value in the workitem for testing purpose and check if that goes properly, later on implement the rule.....
    If the workflow does not triggere - go to transaction SWETYPV and deactivate and activate the event linkage with that workflow....
    Regards,

  • Event linakge in qm work flow

    Dears
    I try to activated QM work flow for notification ..I activated all under event linkage area
    and try to create a notification but User inbox is not updated
    We need to do any setting in assign agent area
    pls verify in detail
    Any abaper input is required to fulfill this task
    thanks in advance
    Faisal

    Hi
    we are able send the mail by using action box..no issue for that
    Issur is if we assign a task to a user (in qm notification) he need to be i nformed autmatically by the system if we activate QM work flow
    to achive this i done following
    QCC0>QUALITY NOTIFICATION>NOTIFICATION PROCESSING>ACTIVATE WORK FLOW TEMPLATE
    and i activate event linkage in the screen
    i dont know what do further
    Hope i make clear on my question
    Faisal

  • ACTIVATE WORK FLOW FOR QM NOTIFICATION

    Dears
    Please tell me the step for activating work flow template for Quality notification
    If we activate it effect any other module?
    A QM consultant can be activate it or it required technical person
    Any in put will be highly appricaited
    Thanks in advance
    Faisal
    Edited by: Muhamed Faisal on Jul 21, 2011 8:00 PM

    Hi,
    For all three tasks, it is very conveniant to assign ROLE or USER itself to the task.
    But for that Purchse activity would be your new and separate task it self, for which you should new task, where you can assign the RULE for the Agent. That may make it optional as per your requriement.
    Hope it'll work for you.
    Update us to help you more, reward points to help you better!
    Regards,
    Shyamal

Maybe you are looking for

  • Javascript to check for duplicate entries in 2 pull-down lists

    I have created an application form in Acrobat 8 Professional, using LiveCycle and would like to compare selections in 2 drop-down lists so that the same option is not selected twice. I think this is something that could be done with javascript, but m

  • 10g express Exec Imm. Create table problem

    Account is setup as a DBA account in Database (everything granted). I get Insuffiction privelages when running the following stored procedure: CREATE OR REPLACE PROCEDURE R02_BLD_RMS_JRNL( in_rdate IN DATE) AS v_sql VARCHAR2(1000); BEGIN -- Note I to

  • Organizational Structure Configuration

    Dear Gurus,                   I am into configuration for the organizational plan for our client, so can anyone of you send me some material that will help in setting up the configuration for our client as i am facing some problem in it.           Wh

  • Oracle Application Library

    I am beginer to oracle applications. I want to learn oracle applicatiion object library. Is there any book or study material available for oracle applicatiion object library? It is coming under which oracle edition. Is there any tool to explore oracl

  • Help with MOD and DIV

    I have to calculate minutes to debit from an account based on the call length (rounded to the next full minute). But I'm having issues since I don't know the CF syntax for what I need to do. Here is my test code (the call "Length" is dynamic in the r