Error : Annual budget exceeded (FMAVC005)

Dear guru,
I want to create PR (ME51N), the net total amount is 50.000. But the error message shows :
Annual budget exceeded by 11.812.000 IDR (FM PB Availability Control) for document item 00010
Message no. FMAVC005
Diagnosis
The annual budget is exceeded by 11.812.000 IDR (FM PB Availability Control) for the document item 00010. Budget control on outgoing amounts ( ceiling type Expenditures) raised this message for the following combination of availability control ledger, fiscal year (and if applicable, year of cash effectivity) and control object:
9H/2011/DUMMY/EXPENSE1
FYI,
Consumable Budget : 35.700.000
Consumed Amount : 650.000
Available Amount : 35.050.000
The error message says it's exceed 11.812.000, it seem Available Amount for budget is - 11.762.000 (50.000 - 11.812.000)
It's strange...
Please tell me how to solve this...
Thank you..

It's solved with logout from system and then log in again
It's a very stange thing...
Dear Alex,
Thanks anyway

Similar Messages

  • Error Payment budget exceed

    Hi Experts,
    I have an issue about payment budget. We had open item Rs. 37000 for previous year 2009 & same would carryforward to 2010 year through FMJ2. But in FMJ2 there is no document number & I tried to reverse the same document but there was no document in FMJ3 also. How do solve the same ?
    Rgds
    Suma

    Hello Mani,
    Please let me know if I am understanding correctly:
    you are running FMJ2 and trying to CF a certain PO.
    if the PO is not selected, you should first make sure it still has an open amount and review your settings for Carry forward:
    Public Sector Management->Funds Management Government->Closing Operations->Enter Default Settings
    And
    Commitment Closing Operations->
       Enter Settings for Commitment Carryforward Payment Budget
    and/or
       Enter Settings for Commitment Carryforward Commitment Budget
    And make sure that value type 51 is allowed for CF
    If you are getting Budget exceeded error in FMJ2, since you are running CF without budget, it means that the CF of your PO will release budget in the previous year and consume budget in the following year. If budget in the new year is not sufficient, you will get an Availability control error.
    There is a parameter in FMJ2 which allows you to decide how to run it:
    - No Availability control
    - Update without AVC check
    - AVC checked
    Hope this helps you
    Regards
    Mar

  • Error : Annual budget almost exhausted for document item 000001 (FMAVC006)

    Dear guru,
    I want to do release budget via FMMPRELE. It showed the error message :
    Annual budget almost exhausted for document item 000001
    Message no. FMAVC006
    Diagnosis
    The current budget consumption is 10.500.000 IDR (FM PB Availability Control) less than the annual budget for the document item 000001. Budget control on outgoing amounts ( ceiling type Expenditures) raised this message for the following combination of availability control ledger, fiscal year (and if applicable, year of cash effectivity) and control object:
    9H/2011/DUMMY/EXPENSE1
    FYI :
    The Budget Process is "Return" and the amount is 100.000 IDR
    These are the reports show :
    via FMRP_RW_BUDGET (Budget Overview) :
    > Current Budget : 10.700.000
    > Original Budget : 9.800.000
    > Return : -100.000
    > Supplements : 1.000.000
    via tcode FMAVCR01  (Annual Values) :
    > Consumable Budget : 10.800.000
    > COnsumed amount : 200.0000
    > Available Amount : 10.600.000
    How to solve this?
    Thanks before

    Hi,
    If you are on release ECC500 please check if notes 848408 and 849402 are valid to be implemented and if manual steps of note 924406 are applied in your system. This usually is the cause of this error message but only if ECC 500 is your release.
    Please check also if note 978580 is valid to your release and if manual steps are done already.
    Notes 1143244, 1092634 and 1145080 provide corrections to FMMPRELE also, check if it is valid to your release/package.
    This issue usually is related to a missing correction note or manual steps of the notes mentioned above for release ECC 500.
    Please let me know if the notes resolved the issue.
    Best Regards,
    Vanessa.

  • Error Message : Budget exceeded for WBS(BP604)

    Hi
    Im getting a message when im trying to post a commitment to a WBS through PO.
    Originally for the WBS element USD-110107117  I pushed down $15K   and yesterday I was told to push down another $40k. Bringing the total to $55K.
    Today I'm trying to cut a PO (73910) for an amount over $15k and it says that the budget exceeds. But if I cut it below or equal to $15k it works.
    But if you check the Budget it's right there are $55k.
    Can you please help me why still im getting this message.
    Your advice is appreciated.
    Thanks and Regards
    Megha

    Hi
    Thanks for this.
    Another question is that this 55000$ is allocated at level 2 WBS USD-110107117. In this assigned amount is 15000$.
    Project is USD-110100000
    The WBS element which im assigning in the PO is at level 4 USD-110107117-B-5656-03 which of now has 0 value.
    So how do i bring down this value of 55K to this level USD-110107117-B-5656-03 .
    Also if i give any amount less that 15000$ it is taking.
    This sounds strange.
    Any help would be highly appreciated.
    Thannks and Regards
    Megha

  • Error for Budget exceeded for Network does not show up while creating PR.

    Hi SAP Gurus,
    We have an issue while creating a purchase Requisition from Network. When we enter the Toatal Amount in the PR and if the total Amount is greater than the total Budget for the Network, the error "For item 001 Ntwk actvty XXX &  WBS element XXX budget amount XX USD exceeded " is not showing up in the foreground by the system and hence not able to create PR. It seems that while trying 30-40 times, the system will show this error in the foreground once or twice only and we want this to be appears in the foreground consistently. Can you please advice how to fix this? Thanks,
    Reagards,
    Imran.

    Hi,
    you need to maintain sufficient budget in respective WBS element by using transaction CJ30 and by releasing budget through CJ32.
    Check the budget availabilty in report s_alr_87013558.
    It will resolve your issue
    Regards,
    Sandesh Sawant

  • Budget Exceed Error during creating of Purchase order in reference to PR

    Hi,
    I am getting the subject error (Budget Exceed Error) every time when I want to create a purchase order related to purchase requisition of my project.
    Issue is that after release the project when the purchase requisition has created for non stock item under activity I found in transaction CJ31 the assign value has already updated.
    Let say my budget is 400 US$, and the purchase requisition has created for 380 US$. Now when I check with CJ31I found the assigned value is 380. Now If I create a purchase order it throws an error that budget exceed.
    The tolerance limits are following:
    SA     ZSA01     Budget Profile Overall AVAC     ++     1     90,00
    SA     ZSA01     Budget Profile Overall AVAC     ++     3     100,00
    SA     ZSA01     Budget Profile Overall AVAC     01     1     90,00
    SA     ZSA01     Budget Profile Overall AVAC     01     3     100,00
    Please advice what will be the proposed solution for the above issue.
    Thanks in advance.
    With Regards,

    Your budget is 400$ and PR value is 380$ but you have not mentiond what is the tax value ?
    when u r creating PO at that time system will check the budget against PO value considering taxes also.
    eg. 380$+tax value.
    after considering taxes your total PO value imay be getting updated more that 400$.
    Explre you error by clicking on error information you get the exact diffrence in budget and PO value.
    Hope this will sove your problem, reply after doing this.

  • Error in PO "IO Budget exceeded"

    Hi All,
    I am working with extended classic scenario , I am facing a problem while changing the PO.
    When I try to add or delete any line item in the PO it throws error of "Budget Exceeded for the IO XXXX" for 1st line item or any other line among the PO for which the PO is ordered and Budget is available.
    e.g.
    1) PO is created with one IO 1P , its in ordered status . after that I try to add 2nd line item in the same PO with IO 2P, that time it throws error " Line item 1 Budget exceeded for  IO 1P "
    2) Po created with 8 line items with different IOs.. When I try to delete 6 line item , it throws Budget exceeded error for other line item.
    Its working fine in Test system, I tried to replicate the same scenario in ET2 ( Test system ) but I didn't get any error there, so its really very difficult to analyse exactly whats happening in production system.
    Please help me out to resolve this issue
    Regards,
    Sheetal

    Hi CS,
    I have tried all sceanrios  before reporting this problem .I had created PO in R/3 and deleted , added line item in the same PO..  There is no any error in R/3 system.
    Its working fine. Only problem in the SRM side. That day I received one more same problem with another  PO.& IO..  User was trying to delete the PO line item , he wasn't able to delete it that day. But next day, he could able to delete the line item. & nothing was changed in that one day... This is really inconsistency of the system.. I don't know whats happening in the system and how to rectify this error. As  I said, I had tried to replicate the scenarion in SRM test system . In my first atttempt , i could able replicate the same error, but when I tried next day there was no any error in the PO...... After that I tried many POs but not able to replicate the same error.  I have raised OSS for this , but side by side I am trying to fix this problem from side, as many problems are reporting from the user side..
    Also I would like to share one more imp thing, that this problem is only one specific conutry.. We are supporting Globally, but not other than Thailand reported this problem and its nos are also increasing day by day.
    Is there FI-CO related check setting there in SRM & R/ 3?
    I have checked the R/3 Co setting for IO, so will the Tolerance limit setting affect in this case?
    Please let me know
    Sheetal

  • Budget exceeded error while deleting CAPEX Purchase order

    Hello All,
    We've created purchase order with WBS element for some materials & account assgn P. This however needs to now be deleted as there has been mistake in th PO.
    But while trying to delete the PO the system gives an error message " WBS element XXXX.XXX.. budget exceeded"
    I've tried deleting the PR first and then the PO which works fine, BUT we are not able to create another PO as the error of Budget exceeded is seen here as well.
    Please advice on how to delete the PO.
    Regards,
    ManojR

    Hi,
    Please read note 178837 which gives information on how to check the real assigned value.
    I would like you to run report ZKAOIDE0 from Note 100409 to remove
    the data which is not linked to a valid purchase order or requisition.
    After running the report then run transaction CJEN to reconstruct the
    project.  Then run report RKANBU01 after completing the reconstruction.
    The problem is probably that  a purchase order has the deletion indicator set but it still appears in table COOI.
    I hope this helps!.
    Best Regards,
    Arminda Jack

  • Budget Exceeded Error in CJ88

    Dear Friend's
    When i am doing a perodic settlement of project then system shows error message "Budget Exceeded."
    But actually sufficient budget is available against that wbs element.
    Why this error is showing at the time of settlement.
    Pls guide me on this issue.
    Thanks in Advance.
    Regards
    Sandeep N.Theurkar

    Hi,
    Can u please clarify some question
    1. to what account assignment you are settling the cost and fom where u r bringing the cost whether it is production order or maintenance order etc..
    2.In cji3 report are u getting any negative value
    Kindly confirm so that i can provide u the soln
    Abraham

  • Budget exceeded BP604 (when create Invoice)

    Hi All,
    User got an error message budget exceeded BP604 when create invoice. How can i know what the configuration to check why system check budget( Investment management). I tried to check the configuration in SPRO (Define tolerance limit for availability control) shows that budget profile use ++ which are : (no invoice checking) but in actual it checks budget.
    ++     All activity groups           
    00     Purchase requisition          
    01     Purchase order                
    02     Orders for project            
    03     Goods issue                   
    04     Financial accounting document 
    05     CO document                   
    06     Budgeting                     
    07     Funds reservation             
    08     Fixed prices in project       
    09     Payroll                       
    Many thanks in advance.
    Nies

    Business transaction group 04 (Financial accounting document) contains below transactions:
    G/L account posting
    FI invoice parking
    Invoice verification
    Goods receipt for the order
    Cash budget management
    Payment transfer
    Down payment posting
    Inventory difference
    Regards
    Sreenivas

  • Payment Budget Exceeded - Availibility Control

    We are trying to save a Purchase Order which is using a commitment Item, and get a error "Payment Budget Exceeded"and above this error it says Availability Control".
    but when we check the budget allocation against this commitment we find enough amount available.
    how do we get around this problem?
    Lalchand.R

    Hi suresh,
    I solved it myself.
    Ref: Note 573556 - If availability control works correctly?
    in this note he mentions :
    If you think the available budget amount is not correct, please run report RFFMAV01 (RFFMAV01X) or RFFMAV02 (RFFMAV02X) to check
    If the 'Assigned budget' is same as the 'Commitments/actuals', if not, you must run report BPINDX03 first to correct it.
    IN report RFFMAV02X the assigned budget and commitments/Actuals were not matching, I ran this BPINDX03 and all was done.
    Basically it recontructs the AVC.
    Lalchand.R

  • Budget Exceeding

    Guys,
    I need help with this scenario. Here is the scenario. When i create a purchase requisition which has an internal order assigned in it, it was counting as a commitment, we didnt want this to appear as a commitment. We applied notes 955106,1227760 and1307755 to fix the issue.
    My problem is fixed for new purchase requisitions but for existing ones the commitment is being double counted and i get an error internal order budget exceeded when i am trying to create a PO
    eg i had a commitment of $ 100 before i applied the notes. My available budget was $90( after the purchase req posted). When i create a PO,  it should just move the $100 commitment from purchase requisition to Purchase order but system is taking commitment of $100 ( purchase requisition + $100 purchase order). Giving me the error message budget exceeded by $110 which is incorrect.
    Note 1227760 talks about this exact issue which is already applied in our system but that doesnt help
    Please advice how i can fix this, business is unable to create purchase orders

    Hi Azam,
    I think in the customization settings for tolerence limit, you have maintained it for TrGr ++ as well as TrGr 01for PO.
    The system will take the priority of 01; so please change the setting to ++ only with warning, error etc.
    After changing the setting advisible to run CJEN and then CJBN if needed.
    Hope this will solve your problem.
    Regards,
    Ganesh

  • Error in budget

    Hi
    When We try to release the bugdet error shows budget exceed by amonut.
    I check IMG setting for budget and amount is also available.
    But in the cj32  in that table there is filed ASSIGNED what is indicates. see amount the ASSIGNED filed and amount is exceed is same .
    how we can stress that assinged amount.
    thanks
    sunil

    hi ,
    But how to trace this since PR and PO are created in last year 2007. they use the last year budgets that we release for 2007.  but still that fig comes in that assined filed.
    is there any table or report from that I can trace how many PR and PO are created , closed , partially completed.
    thanks
    sunil

  • Budget Exceeded but no Error message Assign more than allocated

    Hi Gurus,
    I am stuck in a situation where the Error Message BP603 while creating a PO for a wbs at level 2.
    IN cj30 , i found out that  Budget = 69500000 and assigned = 69950772
    if i create a PO OF even .30 (thirty paisa) the budget exceeded amount = 450772.35, which is actually the diffrecene betweenn assigned and Budgeted values.
    Now we are not able to raise any PO
    Below is tolerance limit
    please key in your valuable inputs.
    Regards
    Rohit

    Hi Rohit,
    In Budget report, Assigned value = Actual + Commitment
    If your assigned value is great than Budget, then you will get Budget exceeded error when you try to do any further posting against specific WBS element.
    So, you will need to supplement Budget to cover shortfall.
    You can also refer following SAP note which shows how assigned value is calculated.
    178837 - Availability control: Incorrect assigned value?
    There are lot of threads already discussed in this forum for error message you are mentioning.
    Please search them.
    Regards
    Tushar

  • Error: Order 300401 Budget Exceeded while doing PO w.r.t PR

    Hi Experts,
    We are getting error, Order 300401 budget exceeded  while doing service PO
    In budget shows exceeded in making the P.O of approx amount Rs 411,500. While in the below PO Value, it is clear that the indent still has the amount of RS 1,760,737.
    Indent No. 1000031924 Total Value = 3,230,000
    Sr No.     P.O     Value     
    1     3900006041                       456,774     
    2     3900006146    Line item 1       101,467     
                            Line item 2      266,414     
    3     3900006184                       326,158     
    4     3900006188                       318,450     
         Total P.O's Value               1,469,263     
    Total value of Indent                  3,230,000
    Total P.O value in the Indent     1,469,263
    Balance Amount in the Indent     1,760,737
    Regards,
    Manjunath

    Hi,
    Budget is exceeded w.r.t to maintained Internal Order in PR /PO ,Use below options.
    1 ) Re-construct Budget-KO31 or
    2 )Either de-activate budget-KO32 or
    3) Maintain budget for IO-KO22 .
    This will resolve your issue.
    Thanks & Regards,
    Sandesh Sawant

Maybe you are looking for

  • Can you set a pdf to default the page scaling to 'off'?

    We have a pdf that our customers will print to measure their arm, but most printers tend to page scale and therefore the measurements will be off, is there a way to turn this option off in the pdf settings?

  • Mac for Office and stolen macbook

    I had my macbook stolen. I have purchased a new one, but I now need to re-download the Mac for Office software. It won't let me do this. I don't want to purchase again. How can I get this authorised? Thanks

  • How to display more than 132 characters in a smartform

    Hi Experts, I am reading notes/text entries by calling read_text and then passing them in a variable. I want to display the notes. But even after declaring the variable as  LINE2048, it is displaying only 255characters as output length in smartform.

  • BAPI/FM to remove payment block on MIRO Invoice

    I need a BAPI/FM to remove a payment block on a MIRO invoice.  I realize that this has probably been answered before but, due to SDN's search feature, I haven't been able to find an answer. Regards, Davis

  • When I save an image after editing it goes into my Bridge folder instead of Lightroom.

    I have been using Photoshop CS5 and Bridge for photo editing.  I recently got Lightroom 4.  When I edit a picture and save it, it goes to my Bridge pictures folder not back into Lightroom.  How do I get it to save into Lightroom? Thanks fo ryour help