Error at creation of Production Order

Hello all,
When I am trying to create a Production Order with Material &  order type PP01, I am getting an error. I am providing Qty & finish date & type is "Backward", then I am getting an error as " Price is Zero for order or BOM Item". The error message is 00208 with no more diagnosis.
Please suggest how to proceed as I am unable to create.

Hi Satya,
Please have a look at the below thread. You may find some useful information.
Zero quantity in BOM
Sales item pricing from BOM - updated
BOM business requirement for sales order and PGI
BOM- Actual Additional Cost
Warm regards,
Murukan Arunachalam
Edited by: Murukan_A on Jan 14, 2012 3:48 PM

Similar Messages

  • WM error  while creation of production order.

    Hi ,
    I am trying to create a production order . I am getting below error in log as"Movement type for production supply missing in whse 112, storage type SHP" .
    Can anybody tell me which movement type i am missing here ?
    Regards
    Rohit Chavan

    In OMK0, click on Assign & check if you have assigned mvt. type 319 for the w/h - storage type combination.

  • Co- Product Error while creating a production order

    Hi,
    While performing the Co-Products Approtionment at the time of creation of Production order..
    we are facing a problem regarding cost apportionment I have crated a Source Structure and the cost element is assigned to that Source Structure but still iam facing this issue
    kindly help me out.
    the error msg is
    Debit with cost element 9460404 cannot be settled.
    Message no. KD549
    Diagnosis
    Costs/revenues exist for cost/revenue element 9460404.  This cost/revenue element was given source assignment 40 in the source structure (-> settlement rule for sender -> parameters).  However, there is no distribution rule with settlement type FUL for this source assignment or the total of the percentages for the rules is less than 100.
    Note:
    Full settlement settles all the costs and revenues which have occurred up to the settlement period and have not already been settled. In the case of periodic settlement, you can configure the settlement profile so that all the costs occurring in the settlement period are settled, or if an amount less than 100% can be settled.
    Procedure
    Maintain the distribution rules for source assignment 40 and settlement type FUL or use periodic settlement to settle less than 100%.  Change the settlement profile for the sender as necessary.
    Change settlement profile
    Note:
    Cost and revenue elements receive source assignment " " if you have not entered a source structure in the settlement rule parameters.

    Hi Krishna Murthy I went through the note but i couldnt recive a big help from that note.
    I will explain the step by step process that i have done.
    I am attaching the Screen shots of the issue.
    1. For co-products I have created a source structure and Sec. Cost Elements were assigned in the source structure.
    2. The source structure was assigned in the Material Master for co-products equally distrubuting the amount between 2 materials.
    3. When we are trying to create a production order the error was displayed but the costs was getting calculated properly.
    4. When I was settling the production order the same error was getting displayed.
    I have tried various methods to resolve it.
    1. I have created a periodic settlement rule and tried to settle but it didnt work
    2. I have assigned the source structure in the settlement profile this also didnt work.

  • Error message while creating production order with KMAT material strategy25

    Hi PP Gurus I am running variant configuration cycle...Strategy 25, Custermer Req KEK (KMAT Matrl)
    Sales order & MRP Picked the components correctly as per the dependencies
    written. So Planned order generated against sale order.
    When I tried to convert planned order to Production order...I am getting the
    below error message..
    Error Message:
    You cannot make an assignment to make-to-order stock Message no. CO684
    Diagnosis The component cannot be allocated to an individual stock because
    make-to-order production and engineer-to-order production cannot be executed
    with this order.
    A possible cause is that you are trying to create an order with reference to a
    sales-order/project, where an account assignment to a sales order/project is not
    allowed in the settlement profile that is assigned to the chosen order type.
    This is inconsistant.
    System response The following responses are possible:
    Order processing is cancelled.
    The system resets the special stock indicator back to the original value.
    Procedure Choose another order type.
    I used order type with SD1 as settelement profile.
    OVZG: default 046, settlement profile = SD1
    OPJH: Settlement profile = SD1
    Plz through some light on this if u have worked on Variant Configuration/MTO
    settlements.
    Question:
    1) Is creation of production order with KMAT material supported by SAP?
    2) If yes, why the above error occurs?
    Waiting for Ur reply
    With Best Regards

    Dear R.Brahmankar,
    I have check on the note, but it is not relevant to ecc6. The current system default setting is :
    Standrad setting for reqt class 046
    Special Stock E
    Acct Assgt Cat. M
    Valuation M
    Settlmt Profile SD1
    However if I change the Acct Assgt Cat. from M to E. It resolve the problem. I would like to know is this the right solution?
    Config in Acct Assgt M
    Consumption Posting = E
    Config in Acct Assgt E
    Consumption Posting = '  '
    In F1 key of Consumption Posting field it shown following:
    To flag the sales order item as cost- and revenue-carrying, enter an "E" (settlement via sales order).
    If you do not wish to flag the sales order item as cost- and revenue-carrying, do not enter anything.
    Dependencies
    If you are working with nonvaluated sales order stock, always flag the sales order item as cost- and revenue-carrying.
    If you are working with valuated sales order stock:
      In the case of complex make-to-order production, flag the sales order item as cost- and revenue-carrying
      In the case of sales-order-related mass production, do not flag the sales order item as cost- and revenue-carrying
    Should we change to E?
    Regards,
    Ong

  • Serial number error while creating the production order

    Hello frds,
    I am getting the following error while creating the production order.
    "Item 000000 requires exactly 100 serial numbers for the asset".
    If i give 100 serial numbers in the order, the error is solved. But i do not want to assign 100 serial numbers, i want to assign only 2 numbers.
    I have tried using the new serial number profile also, but it is giving same error.
    Kindly guide.
    Regards,
    Narendra Bora

    Dear Narendra
    Select the serial number profile and go to serialization procedure and set the ser. usage status 02 - Optional as below.
    Procd Procedure description Ser.Usage
    PPRL PP order release 02
    since the serail number creation is optional for order relase this will allow you to relase with out error and with serail number assigned in partial.
    Regards
    Soundar

  • Reg: Error in scheduling of production order

    Hi experts,
    I have an issue during creation of production order. During production order creation, if i am giving todays date as start data and scheduling type as forwards (1) and executing it, it is showing the following error message and it is automatically taking the start date as 2 days forward date (if i am creating order on 06.02.2012 it is taking 08.02.2012).
    Start date is in the past: today scheduling
    Message no. C7030
    Diagnosis
    The start date determined in scheduling is in the past.
    In customizing, you have defined the number of days that the start date is allowed to be in the past.  This number is exceeded.
    System Response
    "Today" scheduling is carried out.Hallo
    Please suggest me a possible solution.
    Regards,
    Krishna Chandra

    Dear Krishnachandra,
    If my understanding is correct then I guess you are mentioning the start date as a date which is more than 2 days older(more
    than 2 days in the past) and so the system is automatically switching over to today's scheduling as you might have mentioned
    in OPU3 the number of days allowed in past as 2.
    Check if this setting is defined as I have mentioned,if so means tiher you can only mention a date within the allowed range or
    else use today's date and carryout a forward scheduling.
    Check and revert back.
    Regards
    Mangalraj.S

  • BOM Selection Mandatory while creation of Production Order

    Hello Friends,
    I would like to know that is there any option other than production version which makes it mandatory to have valid BOM must for creation of Production order / coversion of planned order to Production order.
    I have tried with Production version option but it doesnt throw any error in case BOM with inactive status has been selected in it & also Production order gets created & released.
    Before going for user exit / enhancement option, I just wanted to ensure that it is not possible with standard SAP.
    Kindly share your views on the same.
    Your urgent replies will be highly appreciated.
    Regards,
    Tejas

    Hello Tejas,
    I think this is standard SAP Behaviour.
    Try with following exits:
    PPCO0018
    PPCO0012
    Also check out the following link:
    [How To Make BOM Mandatory while creating Production Order;
    Regards,
    Vinod

  • Problem During Creation of Production Order

    Dear Sirs
    Hope you all are well. I am facing a problem in PPDM during creation of Production Order which is that when I try to release the order System shows me material availability error for BOM items but when I check those material in MMBE(stock overview )all materials are available in UN-restricted use stock. I am facing this problem and not able to resolve it please help me out in it.
    Thanks
    Regards ,
    Haseeb Khan
    Senior Consultant

    Dear
    Did you maintain Work Schedulimng View of the Material ??
    Did you maintain any Production Storage Loaction in MRP2 view and same is appearing in Goods Movement Tab in CO11N screen with Movement Type 101 ??
    Did you maintain the Operation Control Key -pp03  which should have Auto GR check box marked in OP00 ?? Goto Operation Control key -Detail information -Check whther Auto GR is marked or not ??
    If you are using Serrial Number Profile and Serial Number , then Auto GR is not possible .Make sure that you are not haveing functionality because it does not support Auto GR fro serialised material and need to do it through MIGO/MB31/MB1C.
    Make sure that you have used PP03-Control key only at last operation not all the operations.You need to maintain PP03 at Routing level and call the function by Read PP Master data  at production order level   (co02-function read pp master data )
    Regards
    JH
    Edited by: Jiaul Haque on Feb 14, 2011 12:55 PM

  • Blocking creation of production order if standard cost estimate is not done

    Hi PP gurus,
    Can anyone help me in blocking the creation of production order if the standard cost estimate is not done for the particular posting period.

    Hi,
    I do not think there exist a standart check. You can use exit EXIT_SAPLCOZF_003 to block creation of production order by sending error messages based on any condition.
    Regards.

  • Error While saving the Production Order

    Dear Experts
    Pls let me know why am getting the below error while saving the production order after release..
    PSFC_STD_LAYOUT does not exist
    Message no. SSFCOMPOSER004

    Dear,
    Please check have you assigned the scheduling profile in work scheduling view of materail master?
    Then go to OPKP check the same scheduling profile where you have activited the On realese execute printing remove this tick mark and then try with new order.
    Or you can do the configuration in Tocde :OPK8 here assign the PSFC_STD_LAYOUT in forum.
    Regards,
    R.Brahmankar

  • Creation of production order with reference to sales order

    dear all guru's,
                       i m having a requirement of creating production order with ref to sales order but without changing my old strategy of make to stock.
    regards
    ujwal

    Hi,
    For the purpose of creation of production order with reference to sales order while maintaing MTS strategy you need to maintain Make to stock strategy 40 in strategy group in MRP-3 View of Material Master.
    This is the only Make-to-Stock Strategy which enables you create Production Order against both Sales order as well as Demand / PIR.
    So if your strategy group is already 40 then you need not change it.
    However if you are using any other Make-to - Stock strategy like 10, 11 etc. then it is not possible to create Production Order against Sales Order since they dont consider Sales Order in planning.So you need to change them and set strategy group as 40.
    Hope this helps.
    Revert if you have any doubt.
    Regards,
    Tejas
    Edited by: Tejas  Pujara on Sep 27, 2008 8:50 AM

  • Error during creation of transfer orders for material

    Hi,
            We are doing a transfer of stock from one storage with WM to a storage without WM.
    But system does not finish the process automatically displaing the following error message:
    "Error during creation of transfer orders for material document 49000XXXX"
    System cannot find source storage bin
    Thanks in advance for the help
    Regard
    Enzo

    your picking strategy does not find the bin where the material is.
    So you need to check what value you have entered for picking in WM view of material master.
    then you have to check where your material is (storage type and bin)
    then you need to check customizing to where what storage types are included in the picking strategy that is tight to the material master entry.

  • Reg:Bapi for mass creation of production order/confirmation

    Dear Experts,
    I wanted to know with the following BAPI is it possible to create Multiple production orders for different semifinshed Materials along with material availability check and other functions similar to CO01 transaction.
    I knew there are standard transactions for mass confirmation for production orders. But i need a confirmation on this BAPI . As i am planning to go-ahed with ,mass creation of production order creation / Order confirmation in single custom transaction.Need back flush activity even supported.
    BAPI_PRODORD_CREATE to create the orders.
    BAPI_PRODORD_RELEASE to release the orders.
    BAPI_PRODORDCONF_GET_TT_PROP to get the default data for the confirmation.
    BAPI_PRODORDCONF_CREATE_TT to ost the confirmation of production order.
    Along with this BAPI do i need to commit any other BAPI to carry out back flush for components.
    Need your suggestions to take it further.
    Regards,
    Daya.

    Dear SAP Daya
    If the issue has been solved, please close this thread.
    You have already mentioned that the issue has been resolved, thefore, you should not ask for help on another thread before closing this one, as it looks like you are trying to force people to answer your threads.
    Users are always trying to answer as many threads as possible on good will we don't need this kind of "incentive".
    Please read carefully the The SCN Rules of Engagement, especially point 8:
    Be responsive. If an SCN member has answered your question, please mark the answer as "helpful” or “correct”. Mark the discussion as “answered,” so that other members can find the answers more easily
    Also, I checked your old threads and I could observe that there is only one closed. Please review your old threads and close those already solved.
    BR
    Caetano

  • Header Material Repeated during creation of production order

    Sir,
    I have defined bom as one component and 3 co product.
    During creation of production order in operation overview i found header material is repeated in components.
    Pl. suggest me where i have made mistake.
    Regards,
    Vivek

    Hi
    Check whether BOM is recursive or not? also check the movement type against the header material.
    Also check in CO03>Goto> Material list
    Regards
    Anupam Sharma
    Edited by: anupam sharma on Jan 30, 2012 12:17 PM

  • Purchase Requisition on creation of Production Order

    Dear Experts,
    Please clarify the following points
    1 In our Business Scenario on creation of Production Order for a Material, Purchase Requisition is being created on creation of Production Order itself for all Dependent Materials where the items are declared as Non Stock items in BOM  and for the stock items only on MRP run the Purchase Requisitions are created. Is this the standard procedure, or can we customize to create the PRs for all the items on creation of Production Orders??
    2 What exactly the processing indicator in MRP list indicate?
    Thank you,
    Regards,
    Ramakrishna

    For Non Stock items it is understandable, that a PR has to be created with production order creation , as they are not in the stock.
    For Stock items, the creation of PR cannot be linked with Production order creation but can be done with MRP run.
    We can make the system create planned orders or Purchase requisitions or PR in opening period during MRP.
    Processing indicator gives you the scope of PLanning.
    PLanning all the materials within the Planning horizon  --NETPL
    Plaqnning all the materials beyond also--NETCH
    Deleting the current plan and recreating the plan.-regenarative PLannng
    regards
    Ratan

Maybe you are looking for

  • How to store text in AD attributes of type String(Unicode)

    In our company, we store the name of the building in which an employee works in one of the ActiveDirectory attributes named extensionAttribute# where # represents a number form 1-15.  I want to be able to store the names of buildings in the AD attrib

  • PDF/X-3 Quartz Filter

    Hi Thinking that my issue was Pages related, I have posted similar questions in the Pages area but hope that this will have a wider readership amongst people here familiar with pdf production in OS X. I'm using Pages to design a document that needs t

  • Relevant for picking or putaway

    Hi, I have problem with deliveries that are WM HU managed( picking is done through TO-s) and in same system I have also normal deliveries. Problem is when I set indicator "Relevant for picking or putaway" in table TVLP-KOMRL as checked, system reques

  • Replacing SAP Object Selector with Radio Button in ALV table in WD ABAP

    Hi All, I have a view in Webdynpro ABAP which displays data in an ALV table view (using SALV_WD_TABLE component). By default we have the SAP Object Selector for selecting a particular row of the table. This has to be replaced with radio buttons. I me

  • Any way within XI to explore the file system

    Hi all please let me know whether thereu2019s a way from within XI to explore the file system? For the abap part we can use transaction u201CAL11u201D to browse the directories mounted to the Application server, but I do not expect our directory to b