Error CK11N
Hi,
I'm calculating the QAS a client planned cost.
But the materials of the center is 212,215 giving the error message:
Cost Center 212215, type MOBRA activity: rate differs from estratif.custos
No message CK687
diagnosis
For the cost center 212215/tipo MOBRA activity, the rate determined for the second pricing strategy differs from the corresponding primary stratification costs.
Possible causes are:
The user works in the accounting cost centers with rates set manually, included in the iterative determination of tariff.
Rounding error (in this case, contact the system administrator).
System activities
The cost estimate ignores the stratification of the primary cost accounting cost centers and assigns costs by cost element of stratification allocation of costs to the costing of the product.
I applied the notes: 1404483, 1322105, 1068702 and 999985 but still does not work.
Does anyone know what can be?
Regards,
Cristiane.
Dear Christiane,
Error CK687 may be processed if
prices are set manually which do not reflect the full iterative price when price calculation is run (manually set prices are never iterative)
cost elements are missing in the cost component split
one of the receiving element in cost component split cannot carry fix and variable costs
average prices are used (see version customizing in transaction OKEV)
If you therefore still receive the error please define a "BLANK" cost element interval as cost component in the cost component scheme which is able to carry variable and fixed costs. Then the error will be resolved as these costs can then subsequently be used in the cost component split. Re-running KSII always posts delta amounts. Therefore You may re-run it again after above prerequisites are fulfilled.
Best regards,
Antje
Similar Messages
-
Error CK 694 No structure could be determined for internal activity
Hi everybody
When I do confirmation, I have an error like this: CK 694 No structure could be determined for internal activity
In KP26, I defined plan price for Exactly Cost center and activity, Price indication is 3.
In costing variance
In OPL1, Actual Cost for Activity I choose 1. Plan Price...
In OKTZ, I define Cost Element in Cost Component Structure
I don't use Activity Group.
I don't know how to fix this error. Does anybody help me ? Please
Thanks.
QuangDDDear,
CK11N check the cost component structure for this material
Check whether secondary cost element is assined to that activity.If it is assigned then check cost component structure in IMG where that secondary cost element is assigned or not.
Please refer this thread also,
PRODUCT COSTING ERROR -CK11N
Regards,
R.Brahmankar -
While product costing CK11N error
While using CK11N I am getting following error:
Sr.No. Error Description Msg No
1> No price could be determined for Material /Batch XXXXXXX/Plant XXXX 465
2> Cost Component split costed with value zero 240
3> No valid source of supply could be found. 380
4> Object was not costed 60
5> Cost estimate for material XXXXXXX /Plant XXXX is incorrect 168
Please help me how to fix above problem.
Thank you.Check following points,
Probably material might be split valuated,Check price is maintained for all valuation types including header in MM60.
Check price is maintained in info record.
Check type of procurement in MRP2,it will be external procurement - F.
Do product cost estimate using KKF6N.
Check production version is maintained in MRP4 ?
Check throughly all masters vendor,info record & material master.
It will solve the issue. -
Error showing - No price could be determined for subcontracting in CK11N
Hi,
We are facing a problem in CK11N that while we are creating Material Cost Estimate with Quantity Structure, getting an error message..
No price could be determined for subcontracting
Message no. CK468
Diagnosis
The system could not calculate a price for the subcontracting because none of the valuation strategies in valuation variant 001 was successful.
System Response
If the system issues a warning message or an information message, the costing item is used in the cost estimate with a zero value.
If the system issues an error message, it sets the status "KF" (costed with errors).
If the system issues a termination message, the cost estimate cannot be processed.
Procedure
If you have authorization for Customizing, check the valuation strategy for subcontracting in valuation variant 001.
I read many thread already, but no solution is suit my requirement..
please help..We run the transaction OPN2 and select 001- Planned valuation - mat. Valuation Variant. Db Click on it and select Subcontracting tab.
There Strategy Sequence is defined as under:
Priority......Strategy Sequence
1...............Effective price from Purchase Order
2...............Net Purchase Order price
3...............Effective price from Quotation
and in Quotation in Purchasing option, there is selected - Auto quota arrangement.
please guide. -
Material Cost estimate error in CK11N
Hallo friend,
While I cost estimate in particular material through CK11N then this error occur as No price could be determined for material/batch 1002769-750/ plant XYZ. Even the material is maintained in BOM and Routing also. What would be the procedure for costing calculation ?
With Regards,
Samrat
Edited by: Samrat Roy on Feb 25, 2008 3:07 PMHi,,
kindly tell me urgent solution which is still pending.
With Regards,
Samrat -
Error during Material Cost Estimate (CK11N)
hi friends,
I am getting am error during the material cost estimate run.(ck11n)
"No control record for the activity type"
please let me know what is the problem.
regards
RameshRamesh,
System is not able to determine activity type price.
You need to input activity price in transaction KP26 for Version 0/Period/Cost Center/Activity Type combination.
Regards,
Prasobh -
Error in CK11n - The system could not determine a cost component split for
Hi All,
When i run CK11n i have following error:
The system could not determine a cost component split for the internal activity with activity type 502000 of cost center 10100.
Procedure
Check the master data for activity type 502000 of cost center 10100. It is possible that no activity price calculation has been carried out for the cost center.
could any one give me solution
Thanking you.Well, did you run activity price calculation for the relevant cost center(s)?
The CCS you're using for product costing (either your COGM split, or the auxillary) has been marked as a "primary" cost component split. It wants to break secondary costs down into their cost components, and assign those components to components in its own structure.
Wihout a planned CCS for the activity, this isn't possible. (This is normally calculated by KSPI during planning.)
Either calculate an activity CCS is KSPI, assuming that all the prerequisites are in place for that, or uncheck the "primary cost component split" indicator in your costing variant configuration. -
A new error message when ck11n
dear all:
when i make standard cost calculate using ck11n,
a new error message happened , that is 'costing item 00005 is not assigned to
a cost component'.
anyone can tell what should i do to reslove the problem.
thank you a lot.
bset regards!Hi,
Please check T.code OKTZ.
Regards,
Murali -
Error in CK11N ( Object was not costed )
Dear All,
In CK11N run with Costing variant NTAX. Error message CK 060 Object was not costed.
I updated moveing average price in material master - accounting 2 - Tax price 1 field i give the value.
Please help me on this.
Best Regards,
Venkat.
Edited by: venkateswarlu reddy on Sep 18, 2009 6:58 AM
Edited by: venkateswarlu reddy on Sep 18, 2009 7:18 AMHi,
there could be variety of issue that would result in a cost object not being costed.
You need to check the error log and find out what exactly the issue and then resolve it.
Best regards
Surya -
Hi experts,
When I'm trying to execute CK11N I'm facing the error messages as follows.
1. Cost estimate Material RM1/plant is incorrent. Message No. 168
2. Cost estimate Material RM2/plant is incorrent. Message No. 168
I configured Raw material, and consumption accounts in OBYC correctly,[ GBB-VBR; ZOF;AUF;VAY;VAX ]
I configured OKTZ also correctly.
Thanks & Regards,
Reddy.P.SHi Reddy,
On a lighter note..
Are you suffering from 'Dual Personality Disorder'?.
You raised the question and you answer to it.
~Andrew -
I roll-up cost 3 products after I excute at CK11N I found error messages as bellow :
Product AA message error "No valid source of supply could be found"
Product BB message error "No cost field for fixes costs has been defined"
Product CC message waining "No price could be determined for
material CC / Plant S1"
Please advise and explain solution for solve the problem because I take more time for solve it.it is all driven by costing variant
please check in IMG
In CK11, double clieck on costing variant...system will take you to costing variant screen
click on valuation variant pudh button
in Mat valuation tab page
check which priority will suit to your situation? if not set you need to select the priority
Same case in inter activity tab page and other pages...
check and come back if you need help -
CK11N: Wrong Error Msg CK 229 (No routing could be found)
Hi
When I am running cost estimate for a material which is sub-contracted outside, system is giving error msg CK 229 that "NO Routing Could be found"... Since, this material is sub-contracted, it won't have any
routing
In OPR4_CK, CK 229 is defined as a error msg...
But earlier, we have released std cost estimates for many such sub- contracted materials and system never used to give us this msg
If I change CK 229 to warning, it will be problem because for Internally manufactured materials routing is MUST and system will just give a warning msg if no routing is found....
What we are expecting is the behaviour as before.. i.e. for sub- contracted materials, message CK 229 should not be issued as error msg.. But for non-sub contracted materials, it should be error msg
Regards
AjayDear Ajay,
1.First ensure that sub-contracted material has got a valid sub-contracting info record maintained
through ME11 against a vendor.The sub-contracting charges will be maintyaine here.
2.Ensure the source list is maintained for material and vendor combination through ME01.
3.Ensure the costing variant used in CK11N has the proper priorities maintained for it,say for Eg PPC1
is used,check in OKKN for this costing variant it has proper priority say first may be for planned
price,second may be based on value in purchase info record.
4.Generally for a sub-contracted material the system sometimes shows error message as no souce list
exists,but routing will be created only for an In-house manufactured products with the procurement type
E.For a sub-conracted material check the procurement type is E and special procurement value is 30 in
MRP2 view of the material master.
Check and revert back.
Regards
Mangalraj.S -
Dear all,
Currently i having some issues when running CK11N (create cost estimate), the system is throwing errors for all parts having $0.01. Can anyone pls advise on what can be done or where in the configuration can i set it to accept 0.01.
Thanks
Regards
MingHi Piet,
i getting the error msg of "Cost component split costed with value of zero" for all components having $0.01. In another system which i using, i not facing any issue with components that is valuated at $0.01.It seems like there some configuration discrepancies.
Thanks for the reply.
Regards
Yiming -
dear all:
when i make standard cost calculate using ck11n,
a error message happened , that is 'consume account can't be determined'.
anyone can tell what should i do to reslove the problem.
thank you a lot.
bset regards!Hi Ansuman :
i think i have aready created the cost component structure using t-code oktz.
i created a complete new material ( we can call i b000001) using mm01.
then i created new bom&routing for b000001.
when i maked the standard cost calculate,the error happened,
so i think i should assign the account to the new material ??
but i don't know how to do it.
thank you
best regards! -
Hi Controlling Expert,
Good Moring!!
while Cost Estimate RUN CK11n getting Error , see the Below screen shot
Kind regards
PranavDear Pranav
Please check the log. There will be more messages for other materials which are used in BOM of this material. First you need to remove those errors,this will automatically be removed.
Some lower level materials (which is in the BOM of this materia;) do not have the prices according to your valuation variant. Hence check the valuation variant used for your costing variant and according to priorities maintained there for material prices, maintain the price of BOM components which have errors.
Regards
Rajneesh Saxena
Maybe you are looking for
-
Help needed with creating HTML email in Dreamweaver
Hi everyone, would really appreciate some help with a dilemma or two that I have. I have created the following newsletter in Dreamweaver and uploaded it to our website: http://www.nova-design.co.uk/sales/000030.html Now, when I go into my email mass
-
Please help as soon as possible. Thank you!
-
Problems install SCCM 2012 with remote sql 2008 r2 sp2
I am having issues installing sccm 2012 on a remote sql 2008 r2 sp2 server on a seperate instance. I get the error "The network path was not found" if i point it at the primary instance it will let me continue but i cannot install sccm into that in
-
How to use aggregate function with Toplink
Hi My question is how can I get the following select when using Toplink-EJB.3: SELECT MAX(fieldname) FROM tablename; Thanasi
-
IDOC's sending to XI from NON-SAP system
I need to send one IDOC from a NON-SAP sytem to XI. In my scenario I've configured a receiver IDOC adapter with the suitables RFC destination and Port for the SAP R/3 receiver system. We achieve this sending by using the following URL: "http://:/sap/