Error during Production Order creation

Hi All,
Our's is MTO scenario. We have maintiain Account Assigment Category as 'M' in Requirement Type. During creation on production order with ref to sales order system gives error "Account assignment cannot be carried out because of different origin no."
If I create the production order with ref to quotation system does not gives any error. But my requirement is to create the prod order with ref to sales order.
Please guide
Regardsd

Hi Bala,
In SPRO goto>Sales and Distribution> Basic Functions-->
Availability Check and Transfer of Requirements
-->
         Transfer of Requirements
-->
             Define Requirements Classes
             Define Requirements Types
  -->      Determination Of Requirement Types Using Transaction
Determination Of Requirement Types Using Transaction
In the standard system, requirements types are determined according to a specific search strategy beginning with the material strategy group.
Strategy for Determining the Requirements Type
1. First, an attempt is made to find a requirements type using the strategy group in the material master.
2. If the strategy group has not been maintained, the system will determine it using the MRP group.
3. If the MRP group has not been defined, the system uses the material type instead of the MRP group when accessing the corresponding control tables.
4. If no requirements type is found here, the system assumes a special rule and attempts to find a requirements type with the aid of the item category and the MRP type.
5. If this is not possible, a last attempt is made to find a requirements type with the item category only.
6. If the last attempt fails, the system declares the transaction as not relevant for the availability check or transfer of requirements.
Note
You can select an alternative search strategy in the 'Source' field, for example a transaction-related procedure for determining requirements type (source = 1 or 2). 
Example
There are business transactions, such as consignment stock processing, in which the material with its planning characteristics is not important, rather the transaction itself. An issue from the customer's consignment stock should not trigger an availability check against planning at the plant as layed down by the planning strategy but rather against special stock.
Actions
1. Assign the item categories and MRP type to the requirements types.
2. Select an alternative search strategy in the 'Source' field if necessary.
By assigning the 1 or 2 to the Source you can have the requirements in MD04 refered to order instead of the initial source document which is usually quotation. If we don't assign this then the system by default refers to the initail document created i.e. Inquiry or Quotation whichever is the first document.
Regards,
Karthik.

Similar Messages

  • Error during Production Order Confirmation

    I get a real wierd error during production Order confirmation.  The error message is
    "Additional items are not allowed
    Message no. ZOAL010"
    Can anyone throw some light on this?
    Regards
    Raj

    it is not std SAP message.
    you can check the user exit for confirmation.
    check in transaction code CMOD/SMOD for CONF*

  • Batch no assigning during production order creation

    Sir,
    We are manitaining the batch management for inut raw materials. During production order creation it is mandatory to assign the batch no for raw materials then only production order releasing is possible.In our case due to batch assignement to production order while order creation,we are facing the lot of problems like batch no not assign for full req qty and also if unavailabilty of stock for particular batch no it will come to COGI.hereby i need experts help for,
    1.I want to determine the batch no during confirmation instead of order creation and also allow to release the production order even batch should be in blank.
    Kindly help
    Regards,
    PS

    Hi
    For Rawmaterials why cant'n you assign Batch nos buring GR of purchase order.
    Then you can do automatic batch determination during confirmation of order for mvrmt type ;261...
    This is  easy  to handle.
    Please check and come back
    Regards,
    srihari

  • How to ignore Assembly Scrap of MRP during Production order Creation

    Hi All,
    We want to ignore the Assembly Scrap maintained in MRP View during production order creation.
    We are maintaining assembly Scrap for planning so we do not want to remove that.
    Please let us know if any User exit is there during Production Order Creation.
    Thanks,
    Amit

    Dear Amit,
    Assume in CO01,once after entering the total order quantity the system proposes the scrap quantity field separately,now
    remove this quantity for scrap field and press enter and once again adjust the total quantity and check for what quantity the
    system is proposing the BOM components.
    check whether this works for your requirement.
    Regards
    Mangalraj.S

  • Error during prdn order creation co01

    Dear All,
    During creation of production order by co01 a error message is generating i.e."13.05.2035 comes after end of factory calender" for some of my Fert materials only in one of my plants.Bom & Routings,Workcenters are valid for this FG & also for Sfg's which exists in as components in  this fert material.At the time of availability check the system generates this error.Factory calender is valid for 2010 but if the error is due to validity of factory calender the system should generate error for all the Fert materials which we are producing in same plant which is not happening actually.The problem is for only a few of Fert materilas.Pls help suitable answer will be awarded with points.
    Regards
    R Sehgal

    Hi Rakesh,
    The problem i think should be in ur lead time for those materials for which the error is occuring.
    See ur factory calender is valid up to 2010 but for some materials because of the order quantity and the lead time from routing its going beyond the 2010 ( means that order is getting scheduled beyond the2010) so it is giving the error.
    Pls check the same and revert.
    Regards,
    Vinayak.

  • Reg:error during transfer order creation

    hi,
    after quality inspection i move the stock into warehouse integrated storage location. if i clear inspection lot in qa32 for a material after saving it will pop up express message"error during creation of transfer order for a material".i configured that after qc inspection automatic TR is created.i just proceed with manual.
    its a issue related with workflow or configuration....i checked with automatic TO all the things are deactivated.....where i am missing
    Thanks
    Muthuraman.D

    hi,
    goto VOV8
    choose your sales order type
    transaction flow - variant (remove the transaction variant if any)
    but this will remove the transaction variant(custom) which you created , it will take the standard variant for your transaction VA01
    regards
    senya

  • Error during Production Order release

    Hi Experts,
    When I am releasing one production order follwoing messege appearing.
    Error during availability check for order xxxxx (see log)
    co02>goto> logs--> release
    Date 22000504 lies after the end of the valid factory calendar (please correct).
    I have checked routing, pv, bom etc. availability check indicator 02 is alreadly maintained in mm03. Earlier we have confirmed several order of this material in the past, now suddenly this error is appearing.
    Kindly help me to solve this problem.
    Regards
    GR

    Hi,
    Chk for following :
    01. Timings in Routings/Factory calender
    02. Chk for all components in order . It may be possible that one of component is having some MRP elelment dated beyond factory calender
    03. Also chk all receipt /issue elements with dates .
    Regards,
    Milind.

  • Component Availabity Check during production order creation

    Hi All,
    During production creation, I donu2019t want to include/ check the reserved stock of component (stock which has been assigned for other prod order)
    Where I required to make the changes in config.
    Regards,
    Shailendra

    Hi,
    Deactivate Include Reservation in T.Code OPJJ. But make it sure you are doing it for correct Checking Rule which you have maintain in your checking Control OPJK for Order Type and Plant Combination.
    Regards,
    Dhaval

  • Availability check during production order creation - Missing parts details

    Hai Gurus,
    I have one problem during Availability check when converting Planned order to production order.
    1) A- is the finished material, which has A1 to A7 components.
    2) A2 is the procured item with safety stock and it has safety stock also.
    3) When sale order is created , the material A2 is reserved against the planned order for finished material - A.
    4) so when availability is checked during planned order stage , system says no missing parts, when planned order
         is converted to production order system says missing parts for component A2, which is stock and reserved against
         planned order
    5) Checking rule for Production order is maintained as follows,
         a) Include safety stock.
         b) Include reservation.
         c) Include sales requirement
         d) Include deliveries.
         e) Include dependent reservations.(x)
         f) Include production orders.(X)
         g) Check release for stock transport orders only.( A)
    So now i don't know where I went wrong , so that the system could consider the safety stock of Component A2 which is in stock and already reserved against planned order and it does not show missing parts when planned order is checked.
    Waiting for your positive feed back.
    Regards,
    Sekar chand

    Dear,
    What checking rule you have maintained for planned order.???
    As what i can understand by your question that you have maintained to check reservation only in production order not in planned order. Or one important thing mostly people configure to reserve material only after release or creation of production order. Are you reserving material at planned order stage.?
    Check these things. you will automatically find the answer. Hope it will help you. Revert back for more clarification.
    Regards,
    Alok Tiwari

  • Error during production order confirmation - costing related

    Dear All,
    When i am confirming a production order through CO15 following error is coming and system is not allowing to proceed further
    Enter rate EUR / SAR rate type M for 01.01.1998 in the system settings
    Kindly guide me how to avoid this error

    Dear,
    Please go to OB08
    Then enter the details Currency Type M
    Then put the valid date from date
    Then put the currency from
    Then put the currency to
    in last columan put the rate
    as
    Exc rate   Valid From              Ratio(From)            From                                Dir.Quot                   Ratio               To
    M              01.01.2011    X        1                           AED (Currency)      =                         x             1                    EUR (Currency)
    Thanks,
    MS

  • Error during Production order settelment

    I am getting error while settlement of production order " GL Account required valid Tax code",
    waiting for your advice.
    Thanks

    1. This should be solved by the FI consultant.
    2, Check the setting of the Tax in teh  Control data tab of the respectiev Gl account in FS00.
    let me knw the feedback
    reg
    satheesh

  • Error during Production Order Confirmation mfbf ( backflush)

    in my company in sap when i using mfbf for production Order confirmation of tractor then during backflush using mfbf tcode order confirm but in my store dept no metiral cunsume  so please regards this problem
    with warm regards
    pritpal singh

    Dear Pritpal,
    sorry dear,today i cant check  my inbox immediately. Anyway my mail id is [email protected]
    have checked as per my previous post.
    regards
    pradeep

  • Error in Production Order creation : No Production Storage Bin could be fou

    Hi Experts,
    I am creating Production Order for a Warehouse Managed Material. On saving the Material, it is resulting in an error saying " No production storage bin could be found (8005 RX1 000000000001802347)u201D
    Message No : LP 093.
    I guess some master data is missing. Please give some inputs on closing this.
    Thank you,
    Regards,
    Ramakrishna

    Hi Jurgen,
    As such no Control cycle is exsing for this combination. We are in an Upgrade Project from ECC 5.0 to 6.0 . I am wondering, how this is working in ECC 5.0 with out control cycle as well. Will there be any other possibility
    Thank you,
    Regards,
    Ramakrishna

  • BOM and routing selection during production order creation

    I am having a material which is having only one BOM and one routing. Now for this material in the material master in the selection method indicator i have put as 3 as selection only by production version. But i have not maintained any production versions in the work scheduling view for checking purpose. now when I am creating a production order for this material manually through CO01 system is allowing to create production order. when is the selection is only by production version how system is allowing to create production order when there is no version is maintained.

    Hi Kumar,
    Looking into scenario as u have maintained,if you have define the selection id and not maintained the production version then it should ask for the production version and show the following
    Since the production version is missing, you cannot execute the desired processing step.
    As well as pls look into OPL8 ,what Production Version is maintained.
    Thanks,
    Mohit
    Edited by: Mohit Sharma on Feb 4, 2011 5:35 PM

  • Error during production order released

    The profile selected for the  capacity availability is not suitable error comes during po released.
    Pls tell me how to resolve it

    Dear
    Maintain the Capacity Overall profile SAPSFCG011 in Production Scheduling profile in OPKP and the same prod. schduling profile to be assigned in Material master work scheduling view. Please check and revert.
    Regards
    Ganesh.M