Error in entry sheet creation - SE134 (enter a price)

Hi,
I run CATM tcode and have encountered error which is to enter a price. I have debugged the calling program of the transaction and it uses MS_CREATE_SERVICE_ENTRY_MULTI function module to create the entry sheet. This FM returns error SE134. Can someone knows what caused this error?
ESSL structure which is being passed to the FM has a dummy in the first line and not sure if this has something to do with the error.
We have checked this also to the functional resource and they were able to create entry sheet manually.
Please help.
Thanks so much in advance!

Hi
Could you please check if Message SE 363 is set as an E (Error) in the IMG transaction OME0?. If it is set to an error you will not be  able to accept service overdeliveries even if you have the unlimited indicator set.                                                                               
Regards,
Mauro

Similar Messages

  • Error ' Quantity exceeds quantity in PO' in service entry sheet creation.

    Hi,
    I am getting error "Quantity entered 7,000 exceeds quantity 5,000 in purchase order' ,  Message no. SE363" while creating service entry sheet
    PO Quantity - 1 AU
    Service  quantity - 5 HR
    in service entry sheet creation i am giving 6HR instead of what is planned in PO
    Not sure what driving this error, please help
    Thanks

    Hi
    Could you please check if Message SE 363 is set as an E (Error) in the IMG transaction OME0?. If it is set to an error you will not be  able to accept service overdeliveries even if you have the unlimited indicator set.                                                                               
    Regards,
    Mauro

  • Service Entry sheet creation - Using a diffent contract diff from line item

    Hi,
    Here is the scenario...
    I have a services purchase order referring to contract  and its service item with services ( service masters) attached to it.
    And the PO  item is a limit item with some limits maintained on the limits tab, but contract reference is specified at the limits level it is only at the line item level.
    System version : ECC 6.0
    Lets say PO number : 123456789
    Lets say contract number and item is : 2323232323  item 10 ( Account assignment U )
    My supplier is : 111111111
    Now I am creating the Service Entry sheet  and I am trying to add the services  ( services selection button)  I get a pop up to  search for services  by certain selection criteria  and one of them is purch document ( remember it doesn't pre-populate and grey out the purch doc field with that the contract number from the item level) and now I can select any service contract that belongs to any supplier and select the services from it and complete my  SES.
    So lets say the contract from which I chose the service is : 3232323232
    And the supplier on the contract is 2222222222
    Is this a valid scenario or not?
    Has any body ran into this situation  before?
    Hope I was clear in explaining my scenario....  
    Thx,
    Krishna.

    Hi Krishna,
    the External Services Management distinguishes between planned and unplanned services.
    In case you have ONLY limits, no planned services in the PO item, it does not matter if you have entered a contract number into the PO item - in this case this contract will be not a real reference for your services.
    If you have entered limit values only as overalllimit and expected value and you did not enter a contract limit on the contract limit tab, then you will not have a special contract reference on unplanned level neither.
    In this case it is NOT an error when you start the entry sheet creation and you can select services from other contracts or purchase orders against your limit values in the PO into the entry sheet.  The system does NOT check for a different vendor when you select services from other documents than the contract which you have specified in your PO item, because it is NOT a real reference - nor on services level as you have only limits in your PO item, nor on limit level since you have NOT entered a contract limit into your PO item.
    In order to understand this process please study the unplanned scenario and contract reference scenarios.
    Regards,
    Edit

  • Supress Mandatory field for Service Entry Sheet Creation

    Hi,
    I am using BDC for Service Entry Sheet creation as BAPI cannot fulfill the Business needs.
    During Recording when I click on Service Overview and click on Service Selection we provide the Model Service Specification Number there I can see the Services and select it, but when I select the service and adopt, an error message ocuured to enter the quantity.
    Is there any way to supress the standard error message without using acess Key.
    BR
    Aviram

    Hi Aviram,
    Messages type 'E' , 'I' or 'W' are controlled through configurations. Please check with your functional consultant with the message number you want to supress. It can be made as 'I' or 'W' through configuration.
    Similarly if you do not want that particular field as mandatory field ask functional consultant to make it optional.
    Regards
    Sachin
    Edited by: sachin G patil on Mar 9, 2011 3:13 PM
    Edited by: sachin G patil on Mar 9, 2011 3:20 PM

  • Entry Sheet Creation

    I am using u201CBAPI_ENTRYSHEET_CREATEu201D bapi for creation of entry sheet number. If I am giving field ACCEPTANCE  in ENTRYSHEETHEADER  details tab.  I am getting error like u201C error in updatingu201D. Any one is worked on this before?.
    Any pointers will greatly appreciated.
    Thanks in advance.
    Edited by: Lokeswari Bandaru on Jan 25, 2010 6:50 AM
    Edited by: Lokeswari Bandaru on Jan 25, 2010 6:52 AM

    Hi,
        while creating through BAPI for entry sheet creation, how many material document items are created in the case of GR-Based, Non-Service Based PO item.Whether through T.Code and BAPI will give the same number of material documents.If so what fields will influence the in which table of BAPI_ENTRYSHEET_CREATE  will influence the number of material document items.I am getting DIfferent number when comapred to BAPI with T.Code.But I know that through T.Code it is giving correct number.Suggest me in this regard.
    Thank you
    Santhi Kumar

  • Entry sheet creation for services in MM module

    I would like to know the what are the fields to be filled in creation of entry sheet through BAPI_ENTRYSHEET_CREATE function module tables to create an entry sheet.And its functionality of each field what exactly it denotes.How package number is external can be given, why that externally given package number is not stored in any of SAP database tables and,in that case how we know that Externally entered package number can be referred in what way in the point of iew of exteranl user?

    Hi,
        while creating through BAPI for entry sheet creation, how many material document items are created in the case of GR-Based, Non-Service Based PO item.Whether through T.Code and BAPI will give the same number of material documents.If so what fields will influence the in which table of BAPI_ENTRYSHEET_CREATE  will influence the number of material document items.I am getting DIfferent number when comapred to BAPI with T.Code.But I know that through T.Code it is giving correct number.Suggest me in this regard.
    Thank you
    Santhi Kumar

  • Error - Service Entry Sheet

    Hi all,
    While Doing service entry sheet system is showing the following Error Log.
    "147 Account determination for entry 1000 KBS 1000 not possible"
    Please explain how to resolve this.

    Hi,
    No need of any sap note check here.
    Go to OBYC transaction.
    Double click on KBS transaction key, Enter the chart of account.
    There maintain the G/L account for 1000 valuation class/valuation modifier.
    Regards,
    Bharat.

  • Entry sheet creation using BAPI_ENTRYSHEET_CREATE

    I wanted to create Service entry sheet for Purchase order Service items.I am using the BAPI -BAPI_ENTRYSHEET_CREATE.BAPI returns the error 'Unplanned service may not be entered'.I am passing PLN_PCKG & PLN_LINE from ESLL to the structure/ENTRYSHEETSERVICES, still the service lines are considered as unplanned service.

    Hi,
    I came across this issue and have blogged a solution that gets round it for our purposes. This may help:
    http://community.altiusconsulting.com/blogs/adamadshead/archive/2009/09/24/bex-analyzer-s-file-upload-bug-when-integrated-with-sap-portal.aspx
    Regards,
    Adam

  • Service entry sheet creation thru bapi for multiple line items

    HI All,
    WE are using BAPI_ENTRYSHEET_CREATE bapi for the creation of service entry sheet against service PO.
    We are able to create the service entry sheet successfully with single sevice line item using this bapi,but when we are going for multiple service line items in item services tab in aPO, we are able to create the service entry sheet with only one service line item although there are 4 service line items in the item service tab in the po.
    We know that this bapi cannot support more than one po line item as it has provision for only one line item at the header leavel in the bapi
    will be rewarded for the best solution.
    Regards,
    velu

    Hi,
    Do you know the note 420334?. There you have very useful information.
    Best Regards,
    Arminda Jack

  • Service entry sheet creation from PO without selecting line item of PO?

    Dear SAPIENTS,
    While creating service entry sheet for one frame work order (PO) i do not want to select line item of PO. I want all the service of PO line item should come automatically in single service entry sheet number.
    At present whenm i enter the PO number its taking line item 10 as default because of this service of that line item is coming and for every line item i have to create different service entry sheet.
    Regards,
    Kaushal Rai

    Hi,
    in ML81N please enter the entry sheet header data, then go to full screen services, push the button for
    "service selection" and after that  a popup appeares for the service selection (SAPLMLSP
    0500). On the bottom of this popup you have the button "complete" = adopt all = F9. If you hit this
    button all of your services within the service specification will be copied into the entry sheet
    at the same time.
    Regards,
    Edit

  • Service Entry sheet Creation for Shipment cost Document

    Dear All,
    While creating a shipment cost document .A service PO is getting generated in the back ground based on which a service entry sheet is created and LIV is made.But in the configuration we are mapping the Transportation planning point to Purchase organisation alone.
    Can some one let me know whether the generation of PO in the back ground for a shipment cost document in the back ground is a standard SAP feature if so can you tell me the configuration steps.
    Regards,
    K.Vivek

    Hi,
    Creation of Service PO in shipment cost document is based on the following SPRO setting or T-code.
    T code : T_56.
    SPRO > LE > Transportation > shipment cost Document > Shipment cost types and item categoires.
    Get into the details of item categoires, you can see the indicator Generate PO.
    hope this helps.
    Harish

  • Service entry sheet creation for planned services

    Hi,
    I have created a service purchase order with planned services. After this I am trying to create a service entry. During ML81N, I give the P.O number and then click on create service entry.
    However, to adopt the services from the purchases, there is a service selection tab which takes the user to the services tab of the purchase order and then the user must select the relevant service and click on the adopt button to bring the  service into service entry sheet screen.
    However, in my  case, the service selection tab is not appearing on the service entry screen. Hence I am not able to call the services from the purchase order. I am on ECC 6.0 version.
    Am I missing some step in config or in procedure ?
    Kindly advice.
    Regards,
    Rajeev

    Hi,
    This doesn't sound like a config problem.
    If the services are on the PO then you should be able to select the option to choose them from the PO services.
    A remote (very remote) possibility is that you may have an authorisation problem, stopping you from being able to use the PO details? Is this possible? do you have authorisation to change this PO via ME22N etc:?
    Steve B

  • Service Entry Sheet creation!!!!

    Hi all,
    I am working on service procurement with ECS scenario.The Service Entry Sheet in the backend R/3 system is subject to release strategy(for a material group).
    Whenever I create a Service Entry Sheet(SES) based on a EBP PO, then the SES is subjected to a release strategy.
    Whenever I create a confirmation in the EBP system(which doesn't have a workflow for confirmation), the follow-on document i.e. Service Entry Sheet is getting created in the backend with absolutely no release strategy whatsoever.
    Why is the SES getting created automatically,even though there is a release strategy attached to it at the backend?? This release strategy is functioning fine when I create a SES manually in the backend.
    I found a thread { Service Entry sheet auto released when created through EBP } wherein someone had faced the same issue that I faced, but no one gave him a clear picture as well.
    Help me!!
    Regards
    Hari

    Hi,
    This is standard SRM design.
    The Service Entry Sheet created from SRM in ECC is directly released to create a material document (good receipt).
    This is because, there is no release functionnality available from SRM.
    Thus, if there were a release strategy, there is no way in standard to pilot it from SRM.
    If you need a release straegy, you need to use the confirmation WF in SRM that will occur before the Service Entry sheet is created in ECC.
    Kind regards,
    Yann

  • CATS - Service Entry Sheet creation

    Hi Experts,
    I'm trying to create a Service Entry Sheet via CAT2 but have been unsuccessful up to this point. I have been unable to solve this issue thus far and I've spent quite some time. I was hoping that someone out there might have some information that could aid me. At this point, I've done the following:
    I've created Info Types 0315, 0000, 0001, 0002, 0006, 0007, 0003, 0105, 0024, 0016, and 0019. In addition, the Personnel Number has been set up as with an Employee Group of 9 - External Employee. At this point I'm unable to actually create the Service Entry Sheet via CAT2 and I unable to figure out why.
    Kind Regards,
    Jason

    Hi Jason,
    if u merely create an employee with necessary infotypes thats not sufficient tobe able to access the timesheets thru CAT2. a data entry profile needs to be assigned to the userid along with appropriate authorisations.

  • ME21N - error during service PO creation - "Please enter a service"

    Hi,
    PR was created with reference to agreement.  When we try to create PO, below error appears.  Apparently service code, text are available so this error does not make sense.  Have you come across such a situation ?
    Thanks,
    Sankar

    Root cause was a mess up from the user.  The user has linked multiple line item services from contract (OA) to single line in PR.  System does not stop at PR level.  But throws this error at PO creation level.  User has recreated the PR and all OK.
    Wrong process:
    OA item 10 - PR item 10
    OA item 30 - PR item 10
    OA item 60 - PR item 10
    Correct process:
    OA item 10 - PR item 10
    OA item 30 - PR item 20
    OA item 60 - PR item 30
    Moreover error does not happen in ME59 (automatic PO creation) even through the wrong process.

Maybe you are looking for

  • How can I install CS6 on a second computer?

    I need to install CS6 Basic, not extended, on a new computer. I found several different suggestions. So here's what I've done: 1  I downloaded a trial so I could register it with my CS6 basic version S/N. The trial version it downloaded was Extended,

  • Error while deploying the project to ESB

    Hi, When I try to deploy any services to ESB I am getting the following error. error code: 1000 : 5 summary: /rh37/u01/app/soa/10.1.3.1/SOA/integration/esb/oraesb/deploy/DEV_Ramana_Order_Variable_Test.zip (Read-only file system) Fix: Contact Oracle S

  • How to set focus on the title of JTabbedPane

    I have created a JTabbedPane and added three JPanels to it. They are titled, say "Panel 1", "Panel 2" and "Panel 3". And each of them contains buttons and text areas. Since this app is for physically disabled users, it must provide navigation through

  • How to unlock ipohone 4

    hi. I bought an iphone 4 from someone on Facebay and it was working but after one week I can't make or receive calls. I showed it to someone in the Town and he thinks it needs to be unlocked. can you help me to unlock my phone?

  • Creating Customer from employee who is hired in HR

    Hi Please tell me if there is some way to create customer records from employee record created in HR Is there any report or transaction available that will create a customer record by using/copying  the HR employee record without entering data again.