Error in good receipts for sch.agreement

hi frnds,
   while i make gr w.r.t sch.agreement. it is telling that " Document xxxxxxxxx does not contain any items ". i have maintained delivery schedules in day format. and iam trying to do gr in tht date too. but still it is not showing.
how could i resolve..kindly help me..
regards,
prasath

Hi Prasanth,
There have been several reasons which can be attributable to this problem -
1) This PO is subject to release strategy and since the final release was not made, this PO is considered as 'blocked'.
2) You have been using the confirmation control category where in respect of the last confirmation category key, the GR assignment check box is flagged. In this particular case, GR is only be posted if the confirmation is not maintained.
3) Early delivery date i.e. the GR date is coming earlier than the PO delivery date.
Check also the movement type used:should be 101.
Regards,
Nani.

Similar Messages

  • Goods receipt for schedule agreement  / schedule line

    HI Dears,
    could u pls help me, how to carry out goods receipt - MIGO- for sch agreement po or sch ag sch lines.
    thanks in advance
    rgds
    Jay

    It's a normal process as we do for Normal Po in MIGO...
    But the GR allowed on the scheduled Delivery date...
    Go to MIGO Select Goods recept & Purcahse Order
    and  Enter the SA number in the Purcahse Order  filed..
    Edited by: Manohar Raju on May 15, 2008 7:04 PM

  • Goods Receipt for scheduling agreements

    Dear Experts,
      I have created schedule lines through MRP in MD03. But when i tried to do  goods receipt for that scheduling agreement , it is telling
    "Document xxxxxxxxxxx does not contain any items ". I am doing GRN w.r.to that scheduling agreement. How do i do GR w..r .to that scheduling agreement ? I dont have release for sch.agreement. Kindly help me..
    Regards,
    BBR

    Hi,
    Go to MIGO enter the Sch.Agreement number  and do the MIGO
    Please check the following
    1. Whether Delivery date is today date (MIGO date)
    2. Whether Delivery completed indicator is set.
    Regards
    Ganesh

  • Goods Receipt For Scheduling Agreement

    Dear Experts,
    Can anybody please explain, the step by step procedure for the Goods Receipt of Scheduling Agreement.
    I have created scheduling agreement (ME31L) and delivery schedule (ME38) with 15 schedule lines (e.g. from date 01.04.2008 to 15.04.2008).
    But in goods receipt it is showing the single line with total ordered quantity. so how to take the reference of actually scheduled quantity for posting goods receipt ?
    Thanks in advance

    Hello Kiran,
    Let us assume your total quantity is 15 that mean 1 qty each day (from 01.04.2008 to 15.04.2008).
    On 01.04.08 system will allow GR of 1 Qty only.... in this way, you will get 15 Qty after 15 days.
    But in case you donu2019t do any GR up to 14.14.08 and on 15.04.08 system will allow doing GR for all 15 Qty. And same will come in single line.
    If you do GR on daily basis, you will get the reference with schedule qty.
    Rewards are helpful.

  • Error: GR "Goods receipt for purch. order" is not allowed (ORD 4000048)

    Hi gurus, can anyone please help me
    while doing service entry for the PO with account assignment F and Item Category D
    our client is facing the error
    "Goods receipt for purch. order" is not allowed (ORD 4000048) MSG no: BS007
    Diagnosis
    The current status of object 'ORD 4000048' prohibits business transaction 'Goods receipt for purch. order'.
    Procedure
    To process business transaction 'Goods receipt for purch. order', you first have to change the status of object 'ORD 4000048' to allow the transaction 'Goods receipt for purch. order'.
    This gives you an overview of the system and user statuses that affect the transaction. A transaction can only be executed if there is at least one status that allows it and there is no status that forbids it.
    Anyone can give the solution please
    Guruk

    hi dear all
    Really thanks for your prompt reply.
    i solved this issue, as what u said, it is not released in IW31, at the time of PR creation. So i asked the User to go to IW32 anc choose the apprpriate order and change mode and click on Flag Icon to release.
    Any way i awarded points for your support
    Thanks
    regards
    Guru

  • Error during Goods Receipt for Production Order

    Hi All,
    When using MIGO to post Goods Receipt for a Production Order, I got a customize message saying that the posting is only available between 2010.08.25 to 2010.08.27.  I have checked in Business Add-in using SE19 but there are no implementation present.  I know that in Logistic Verification MIRO there is a transaction OMRM to set messages.  I would like to ask is there anything similar for MIGO.  
    Or is there any other place in Configuration which allows me to add these Customize message.
    Thanks.
    Edited by: jamison2004 jordan2004 on Jul 9, 2010 9:09 AM

    Hello Jiaul,
    Sorry I may have mislead you.  The actual error message is "Goods Receipt for Production Order XXXX can only be made on 2010.08.25 to 2010.08.27".  These two dates are the Start Date and FInish Date for the Production Order in CO03, 
    The Basic Start Date for the current Production Order is  2010.08.25
    The Basic Finish Date for the current Production Order is 2010.08.27
    I think what it means is that you can only Post Goods Receipt for the Production Order only after the Basic Start Date of the Production Order.  Do you know where I can find the configuration for this message?
    Thanks

  • Goods receipt for Schedule Agreement

    Hi
    I cannot make a goods receipt today, for a future schedule line date, in a schedule agreement, in MIGO transaction. I know it is standard functionality, but please inform is  there any settings available to make it happen.
    Also i would like to know whether the goods receipt for a future schedule line is possible in MB01 transaction.
    Regards
    Arvind

    Hi,
    1. In JIT it will allow only exact date what it is showing in that SA schedule lines...
    But we can manually cahge the date we can do the MIGO. But in this case i hope there is no setting ....
    2.I hope there is a link B/w Calendar if we make as working day it will allow i hope
    Regards
    Murugan J

  • Unable to create Goods Receipt for Scheduling agreement

    Hi,
    I am have setup Scheduling agreement. When i try to create the Goods receipt on MIGO by entering the agreement #, I get an error : Purchase Order not yet released.
    Please help, I couldn't find similar issue reported on this forum.
    Thanks
    Ramya

    Release SA by T-code ME35L , If it's PO Release by ME29N

  • Error while Goods receipt for rework order.

    Dear all,
    I have created one Rework order through TC CO07.
    While doing Goods Receipt it gives Error Msg as following.
    "No valid order items exist for order 200000203"
    Message no. C6008
    Regards
    Atul

    Dear,
    There is only confirmation CO11N for the rework order. And good reciept MB31 for main order.
    There is no GR for rework order. Once you confirm rework order,you need to do the GR for the balance qty of  main order or parent order.
    And you need to priliminary settlement of rework order first in CO8B, hence the cost will be moved to parent order, then you settle parent order in KO88.
    Hope clear to you.
    Regards,
    R.brahmankar

  • Goods receipt for Shedule agreement

    hi all
    we are using SA to go for subcontracting .
    Process is like creating agreements by  ME31L and then Delivery schedules are created by ME38.
    then goods are issued to subcontractors by MVT type 541 with SA as ref.
    then challan is created by J1ifo1.
    GR is divided into 103 first at gate and then 105 entries at shop floor.
    we made 3 103 entries for a specific SA .now when we try to do 105 we are getting the error message
    Of the required quantity of material &, & & remain(s) open----this message has status Error in customizing in standard. version is 00 and application area is LB which is for batches.
    does anybody has any idea  regarding the above message? what could be the possible reason for this?
    thanks in advance for ur considerations
    raja

    HI ALPESH PATEL
    THNX FOR UR HELP. BUT I CHECKED THE 103 MVT AND IT WAS ACTUALLY TO BLKD STOCK SINCE THE MOVEMENT ITSELF IS GR TO BLKD STOCK.(103).AND ALSO IN MB5B THERE IS NO REVERSE FOR 541 AND ALSO STOCK IS AVAILABLE AT VENDOR SIDE.
    MOREOVER THERE IS NO CHANGES IN BOM OR INFORECORD SINCE THE DELIVERY LINES WERE CREATED.
    MESSAGE WAS ACTUALLY THE SYTEM COULD NOT FIND THE COMPONENTS SAYING THE MAIN ITEM COULD BE ZERO OR NO BOM COULD BE THERE. BUT BOM WAS CREATED WELL BEOFRE AND 103 QTY WAS ALSO CORRECT. I CHECKED THE 103 QTY AND ALSO CHANGES MADE IN BOM.
    THEN I TRIED CANCELLING THE 103 AND AGAIN DOING 103 AND 105 WITHOUT REEXPLODING OR MAKING ANY CHANGES AND IT WENT OK. I JUST WONDER FOR THE CAUSE.
    HOWEVER THX FOR UE HELP AGAIN
    RAJA.

  • Goods receipt for purchase order is not allowed

    Hi,
    When I am doing the PO receipt i am facing the error message "Goods receipt for purchase order is not allowed WBS element xxxxxx"
    What could be the problem
    Thanks
    Lucky

    Hi,
    Please check the WBS element in CJ03, in Basic Data, System status,
    Is the WBS is not released or blocked.
    Hope it helps you.
    Thanks

  • Goods receipt  for purchase order not allowed for a particular wbs

    hello everybody..
    Am creating a good receipt for a purchase order using the T-CODE-: MIGO...
    While doing so am getting an error as " goods receipt  for purchase order not allowed(wbs element)".
    What can be done to rectify this error?
    Plz do help me....
    Regards,
    Deepika
    Moderator message: not directly related to ABAP development, please have a look in the appropriate functional forum, study the long text of this error message.
    Edited by: Thomas Zloch on Dec 1, 2010 5:52 PM

    Hi Br. Ajay M,
    Released the order and Status line as follow
    REL  AVAC BUDG GMPS
    but the error changed while reverse the document
    item 0001 Order is invalid.
    Many thanks for your kindly reply.
    regards,
    Steven

  • Goods receipt for purch. order" is not allowed

    Hi Experts,
    I am using BAPI_GOODSMVT_CANCEL..and getting the below Error messege
    "Goods receipt for purch. order" is not allowed (NWA 9000275335 0020) 
    What is this (NWA 9000275335 0020)*
    i would like to ask how do i go about resolving the error message. Please help me.
    Thanks ,
    Silviya

    Hi,
    Thanks for your reply. I have checked Network & Activity in CJ20N. I dont know how to identify whterher it's defined correctly or not.
    Is any other way to solve this?  please help me.
    Advance thanks,
    Silviya

  • Error during goods receipt of Finished goods for production order

    hi friends
    pls help me iam struggle this issue and mentioned the issue .
    when i do goods receipt for production order system getting error like
    No price could be determined for material/batch FG/ plant ZTP
         Message no. CK 465
    Diagnosis
         The system could not calculate a price for material/batch FG/ in plant
         ZTP for valuation view 0, because none of the valuation strategies in
         valuation variant 007 was successful.
    System Response
         User-defined error management enables you to specify whether the message
         is an error message, a warning message or an information message.
         o   If you have defined the message as a warning message or an
             information message, the costing item will be entered in the cost
             estimate with a value of zero.
    If you have defined the message as an error message, the cost
    estimate contains an error or errors.
    -   In the case of a material cost estimate, the system sets the
        status KF.
    -   If it is a cost estimate without quantity structure, or base
        object cost estimate (that is, a unit cost estimate),  the
        system cannot proceed with costing until you have corrected the
        errors.
    If the system issues a termination message, the cost estimate cannot
    be processed, and processing is terminated.
    procedure
        o   Check the master data for material/batch FG/ in plant ZTP.
        o   If you have authorization for Customizing, check the valuation
            strategy for materials in valuation variant 007.
        Note
        If the message is a warning message or an information message, there is
        a danger that materials with errors will be ignored by the system.
        If, because of this, you issue a warning message and at the same time
        include materials with a zero value in cost estimates, you can make the
        following settings for these materials in the costing view of the
        material master:
      1.  Enter a very low price in the planned price 1, 2 or 3 fields
          manually, for instance 0.01 USD. These prices are used for costing
          purposes only; they are not read by other applications.
      2.  Enter the highest price unit possible, for example 10000.
          Note: If you enter a new price unit that is higher than the costing
          lot size, the system increases the costing lot size accordingly.
      3.  Change the valuation strategy, such as strategy 4, where you could
          enter the planned price field in which you entered the low price.
          The system now costs as follows:
          Using the valuation strategy, the system finds planned price 1, 2 or
          3. Due to the low price and high price unit, the system rounds the
          value to zero. However, the cost estimate still obtains status KA
          (free of errors), and no error message is issued.
          This procedure can be used for all materials that have caused error
          message CK465 to be issued.
    with regards
    dinesh
    Edited by: code acess on Nov 8, 2010 4:06 AM

    hi ragavendra,
    this is dinesh .i maintained the costing view and planned price. but again i have same error.so please reply me where i missed the data
    with regards
    dinesh
    Edited by: code acess on Nov 9, 2010 4:01 AM

  • Error while doing Goods receipt for process order. Error code: "BS027"

    I am getting error while doing GR for a day whereas previous day(s) GR is already done and also 2 days post that day are also done successfully.
    Error :  ""Goods receipt for prodn. order" is not allowed (ORD XX-CEMTSAL) " (XX = First two characters of plant code)
    Error code: BS027.
    Thanks to all in advance.

    Hello,
    This issue would occur when you want to post a confirmation for a production order. The error message is generated if you wanted to post a backflush for a component and if this component was assigned to a sales order stock. The sales order itself was assigned to a work breakdown structure element which should be debited with the actual costs. However, the business transaction 'Confirm' is not permitted for a work breakdown structure.
    Please look into SAP Note 62367 and 64370
    Hope the information is helpful
    regards

Maybe you are looking for

  • Error in Simple PID

    The LabVIEW supplied "Simple PID" vi contains an error which disables the Integral function. The "First Call?" node is located outside of the main loop and is therefore only evaluated once. Consequently, each time around the loop the value selected f

  • I can't download  Adobe Reader 9.3

    I can't download reader 9.3 i received error message run dll.32.exe i used microsoft internet explorer. I turned off pop up blockers and deleted cookies then the error message changed to "operating system error" what should i do???

  • Jtree's ValueChange method problem

    my code are as follow: i'm now doing a JTree which will list all the directory in the computers(every node is a directory) .. When i click on each node, i wanna it to display all files names in this directory ... but i just fail that statement: Defau

  • What is RMAN configure file ?

    Hi, When you create recovery catalog, and start RMAN, where does RMAN get information to decide to get configure from catalog database instead of control file? what is the file name? Thanks.

  • How do I place two independent voices in one staff?

    The header says it all: I have two voices in one staff, how do I get Logic to tell them apart?