Error Msg while BOM creation - Maximum low-level code 999 reached

Dear Expert,
After uploading the BOM (T-code: CS01) of material XXXXXXX in XXXX plant, error message through express message is coming regarding maximum low-level code 999 and the BOM is automatically getting deleted.
Error Info...   Maximum low-level code 999 reached
Thanks & Rgds,
Dipen

Is by any chance this BOM recursive?
If so, you need to allow recursiveness specifically.

Similar Messages

  • Low-level code MRP

    Dear gurus,
    i find in the material master (MM02 and in the table MARA) the parameter "Low-level code" = 000 , how  use this parameter ?
    When this value is write?  At saving of Bom? Is a setup of customizing for value possible?
    Thanks a lot
    Daniele Pistilli
    PP TEAM

    Hi
          Pl go thru the following may be useful
    The lowest level that a material appears in any product structure of the
    company. The low-level code controls the sequence in which the material
    is planned in an MRP run: First the materials with low-level code 0 are
    planned, then the materials with low-level code 1, and so on. The lower
    the low-level code, the higher the number that is assigned to the
    material.
    The level that is set in the material master record represents the level
    at which the material will be planned. This means that the material will
    only be planned once all assemblies in which it occurs have been planned
    and exploded.
    The low-level code is set internally in the material master record when
    the BOM is maintained.
    When you create a bom item for a assemblyparts ,the item's low-level code will equal (assemblyparts's low-level code + 1),but if (assemblyparts's low-level code + 1) < bom item then the bom item's low-level code not changed
    Ram

  • I need to allocate low-level code to a material while creating in mm01..

    hi experts,
    In the material master record, each material is allocated one low-level code (field L.Lvl Code) which is determined by the bill of material (BOM) management program.I couldnt find this field in any of the tabs while creating the master record.So can u plz help me out to find this.
    Thanks in advance..

    Ramesh,
    You cannot create an LL code entry in MM01.  The purpose of MM01 is to create Material masters.  LL code is managed by the system, automatically, during BOM maintenance.  SAP does not give the users the ability to edit LL codes.
    It is unwise to attempt to change LL codes.  Improper entries in this field could lead to MRP results that will not meet your business requirements.  You should generally let SAP automatically manage this data for you.
    In the case where you believe you have an incorrect LL code, SAP does have some OSS notes that apply.  Start with [544489|https://service.sap.com/sap/support/notes/544489].
    Regards,
    DB49

  • Getting error msg while inserting a record

    HI
    Am getting error msg while am inserting a new record. Am unable to view the data that i inserted in to database. If any one can help in sorting of the problem plz help. I used the following code in Application Module(AM) and Controller(CO)
    processRequest()
    -- am.invokeMethod("insertmethod");
    processFormRequest()
    -- if(pageContext.getParameter("Create")!=null)
    -- am.invokeMethod("savemethod");
    In AM Code
    public void insertmethod()
    EOVOImpl vo=getEOVO1();
    if(!vo.isPreparedForExecution())
    {    vo.executeQuery(); }
    Row ro=vo.createRow();
    vo.insertRow(ro);
    ro.setNewRowState(Row.STATUS_INITIALIZED);
    public void savemethod()
    {   OADBTransaction oa=getOADBTransaction();
    oa.commit(); }
    Error
    Attribute SummaryFlag in kiInsertAM.kiInsertEOVO1 is required

    Hi,
    Either on the form you don't have SummaryFlag field or you forgot to map VO attribute i.e. SummaryFlag to that field.
    If you don't have SummaryFlag field on form then you need to set it programatically before committing record.
    Please check and let us know.
    Regards,
    Mukesh Uchaniya

  • Error msg while using i pod touch on bose sounddock

    i got an error msg while using my ipod touch on a bose sound dock... it is still working fine it just said error not comatible with i pod touch, was this just a little second glitch, everything is still working fine dock is brand new, is there anything i should be aware of?

    Have you contacted Bose/went to their support site?
    You can try:
    - Reset the iOS device. Nothing will be lost
    Reset iOS device: Hold down the On/Off button and the Home button at the same time for at
    least ten seconds, until the Apple logo appears.
    - Reset all settings
    Go to Settings > General > Reset and tap Reset All Settings.
    All your preferences and settings are reset. Information (such as contacts and calendars) and media (such as songs and videos) aren’t affected.
    - Restore from backup. See:       
    iOS: How to back up           
    - Restore to factory settings/new iOS device.

  • Error msg while downloading or visiting iTune store: "network connection was lost". Any idea about the problem?

    I am getting for the last days a constant error msg while downloading or visiting iTune store: "network connection was lost" (sometimes also ways it was "reset" instead). But, the network is working (I can make othe rdownloads and visit to other internet sites). Any idea about the problem?

    Mac server or Windows server? Have you checked her permissions/access vs another user not having the issue?

  • Low level code

    hi
    while configuring SNP planning run -SAPAPO/SNP01     screen under object selection >manual selection i could see planning version, product, location and low-level code....
    1. what is the significance of this parameter low level code ?
      2. how it reacts to the planning run ?
    my guess is that it takes into account all the tail end level of the BOM that belongs to the product ..but am not sure ..since it is 000/production server i dont want to experiment
    Please help me understand the science behind low level code,can you please suggest an easy to understand link or material
    thanks

    Hi Rahul,
    The low level code the position of a particular location product in a supply chain. SNP heuristics use it to determine the correct planning sequence. This is particular important if you are running "Location Heuristics" and putting the location products in the selection and want system to plan for only those location products.
    The system will use the low level code to determine which location product to plan first and then move to the next one and so on.
    You can refer the following links for further explanation.
    The Level of BOM Planning in the SNP Heuristic and Low Level Codes - SAP Planning
    Low-Level Code Determination - Supply Network Planning Run - SAP Library
    Regards,
    Mitesh

  • ERROR Message while creating Rebate condition record T code VBO1

    Dear Experts,
    I am getting error message while creating rebate condition record T code-VBO1-Error Msg-862 system cannot read the structure for table,because of this i could not create condition record.
    Please give the solution to create condition record.
    Regards
    siva

    Hi,
    You said you are trying to do this stuff in IDES right.
    If you are using IDES provided by a company and where many people play on IDES, then you can get many such issues...
    This is by our experience.  Today you do something in IDES and tommorow that thing or config is screwed up by others.
    If you have your own IDES, then check the suggestion given by the forum Guru's.
    Regards,
    SB

  • Issue in determining Low level codes

    Hi Gurus,
    We are having an issue running heuristics when running  along with Temporary low level codes. We are in SCM 7.0 environment.
    The SNP Heuristics jobs are failing with this message "Low-level code
    not available for product XXXXXXX at location XXXX
    Job cancelled after system exception ERROR_MESSAGE"
    Also, the message in the job log  for the product in was flagged for deletion and I am not too sure why is this being picked up for processing and then failing?
    I tried using SDP relevance as '1' for the product flagged for deletion for testing purposes and then the program is not considering this SKU, but stopping at another SKU and also that SKU is flagged for deletion. But the flip side of using SDP relevance is that that setting is at global level andmay have issues where the SKU is active.
    I have couple questions:
    1) Is there a way for the program to skip the code which has an error and move forward instead of failing the job? and provide a spool with error codes.Also, to provide the LLC number for all the correct SKU's instead of failing at that point and not generating the LLC's?
    2) Why is the program also considering the codes which are flagged for deletion which should not be the case?
    Also, I tried another way of maintaining the codes in thevariant which are not flagged for deletion and tried running heuristics in the background but failed at a point and it gave a message stating Low-level code not available for product XXXXXXX at location XXXX,     Job cancelled after system exception ERROR_MESSAGE
    But the product which was displayed in the job log is an active SKU. I am not too sure why the job failed with this error?
    I tried running that individual SKU in the background including the temporary determination of LLC, it was successful. I am not too sure why it failed when it was a part of selection?
    Any suggestions, would really help us a lot.
    Thanks and regards,
    Murali

    Hi Datta - Thanks for the replies. I was able to have a workaround by using selection profiles excluding the Procurement type 'P' and it worked.
    At our client, whenever a product is made 'non-X0'  in ECC, procurement type is set to 'P' and by excluding that piece in the variant I was able to continue with my processing.
    But still, don't you think the products which are flagged for deletion shouldn't be picked up heuristics?
    Thanks and regards,
    Murali

  • Low level codes

    How are low level codes define in bom,we know that systems plans 000 first then 001 & so on.
    for example fert will have 000 , halb 001 , & roh 002 it is like this or vice versa.
    but what i think system plans first for  roh , than halb then fert , what u say ?
    or how can u define low level code how it works ?
    are you posting these things or not
    plz explain in detail ....experts
    Regards
    SF

    Hi Safraz,
    Your intially statement is right
    i think system plans first for roh , than halb then fert , what u say ?
    Here the system doesn plan from below,because the requirement comes for the top level  not for the dependendent levels
    For ex -sale order or PIR (any reqmnt for tht matter) is created at the finished level product
    There by system xplodes the BOM & plns for the dependent requirement
    Regaring the low level code calculation check the below link for better understanding
    [Low-Level Codes |http://help.sap.com/saphelp_46c/helpdata/en/f4/7d276944af11d182b40000e829fbfe/frameset.htm]
    Hope this helps
    Regards,
    SVP

  • SNP - Issue with PDS as source of supply in low-level code run

    Hi All:
    I have a bunch of PDS that is giving me the following message when the SNP Low-level code is run:
    ''Invalid source 00000010382991380SLT1 S is not considered for low-level code calculation.  The source of suppy 00000010382991380SLT1   S is available actively in the Supply Chain Model. The location product for which the source of supply is intended, does not exist, however, or is no longer assigned to the model. The source of supply is therefore invalid. ''
    I tried all of the following but still did not get to work
    1. Made sure that FG and all the active component of one FG and the location and the PDS were in an active model.
    2.  Made sure that there was one production version and hence one PDS
    3.  Intialiazed the Planning area with the version
    But still would not generate the low level code for the product location.  Can some one throw share some insight and help pl?
    Thanks
    Ryan

    Could you please check whether in the Product Master, Procurement tab, the Procurement Type is set as "P - external procurement planning"? If yes, then that's the reason as the Low-Level Code is only calculated for Products that are to be planned in APO. In this case, change procurement type to X or E and it should work.
    Regards,
    Tiago

  • Error msg while processing a PO

    Guys, while processing a PO i enounter an error msg "NO SHORT TEXT MAINTAINED IN LANGUAGE DE"...is this an error with the master ???

    Guys, while processing a PO i enounter an error msg "NO SHORT TEXT MAINTAINED IN LANGUAGE DE"...is this an error with the master ???
    Do you think it's a right place to ask this question? I don't.
    Have a Coffee Break and then think friend
    Regards,
    Nick Loy

  • Getting an error msg while trying to run the java class from CMC

    Hi All,
    I am getting an error, while trying to run the java .class file, that which is imoported into CMC.
    Error msg:
    Exception in thread "main" java.lang.UnsupportedClassVersionError: Bad version number in .class file
         at java.lang.ClassLoader.defineClass1(Native Method)
         at java.lang.ClassLoader.defineClass(ClassLoader.java:620)
         at java.security.SecureClassLoader.defineClass(SecureClassLoader.java:124)
         at java.net.URLClassLoader.defineClass(URLClassLoader.java:260)
         at java.net.URLClassLoader.access$100(URLClassLoader.java:56)
         at java.net.URLClassLoader$1.run(URLClassLoader.java:195)
         at java.security.AccessController.doPrivileged(Native Method)
         at java.net.URLClassLoader.findClass(URLClassLoader.java:188)
         at java.lang.ClassLoader.loadClass(ClassLoader.java:306)
         at sun.misc.Launcher$AppClassLoader.loadClass(Launcher.java:268)
         at java.lang.ClassLoader.loadClass(ClassLoader.java:251)
         at com.crystaldecisions.sdk.plugin.desktop.program.internal.ProgramWrapper.main(ProgramWrapper.java:49)
    I have imported .class file into CMC and trying to invoke the .class file by another java program from eclipse..When i tried to invoke the .class in cmc, i am getting an error msg, mentioned above. I thought there might be version conflict. So i changed the java complier version to 1.5 in my Eclipse. After that is done again i am facing the same problem.
    Can anyone help me to resolve this issue?
    Thanks in Advance.

    i have installed BO SDK 3.1 , Service pack 3. It comes woth JDK 1.5 version. i have not done any chnages to it. I impoprted all the jar files related to BO into eclipse.
    1)  Actually, i am writing java code on eclipse. When i run code from the eclipse, it creates a session to cmc and creates folder structure what i need.
    2)  But the thing is, that code needs to run, when i import the .class file into cmc. The process how i imported the .class file to cmc.
    Manage> Add> Program File-->Java (Check Box). In this way i added java class file from the eclipse workspace (class file from the bin directory).
    3) So when i run the .class file externally by another java program or also when i log in to CMC and run that .class file, the instance shows sucess, but when i see the logfile i am getting an exception that which i mentioned above.
    If my method is worng can you please let me know the stepts how to run java program in cmc.
    Thanks in Advance

  • 2 error msgs while synching to I-pod touch.  "An error occurred while writing to the device.  Also, I-pod cann be synced, required disk cannot be found.

    Two error messages appear while trying to synch to I-pod touch.  "I-pod cannot be synced.  An error occurred while writing to the device."  Second msg:  I-pod cannot be synced, required disk cannot be found." 

    The latter error can usually be resolved by deleting the iPod Photo Cache folder.  See the following for its location.
    iTunes: Photo sync creates iPod Photo Cache folder
    For the former error, I would try again.  Then I would reset the iPod and try again.
    Press and hold the On/Off Sleep/Wake button and the Home
    button at the same time for at least ten seconds, until the Apple logo appears.
    - Next I would restore the iPod.

  • Error Msg During PO creation

    Hi,
    How to bring the error msg if  the purchase order value exceed than the valuation price of Purchase requistion
    Thanks in Advance
    Regards,
    Renuga.A

    hii
    We can do that by using USER EXIT option.
    So check with ur ABAPer and give ur functional requirements with which kind of error should come there .
    Technical consultant can do that .
    Thanks
    SAP-MM

Maybe you are looking for

  • I have transfered my itunes library from 1 pc to a new 1....

    But now my memory is saying there is double the amount. It says at the bottom of the ipod library when you plug it in that there is double the memory in use. I only have about 6 gb used on my ipod and its saying iv got 12 gb in use! It seems to me th

  • Whats the best way to get a smashed screen sorted on my 4S?

    Thee screen crakcked when I had only had the phone for a couple of weeks but I left i because the crack did not obscure vewing. However now, months later, the screen is cracked all over and is difficult to read, so needs to be replaced or the phone c

  • Loading a Back Up iPhoto Library, without imorting all of the photos

    I backed up my entire iPhot library on to an external Hard Drive. I then went and dumped all of these photos off of my local Hard Drive, freeing up a ton of space. Now I want to use iPhoto to look at my backed up library on my external drive. However

  • Cannot open folders by double-clicking

    I have an iMac (running Tiger) at work which I have recently joined to the network. With my iMac at home I am able to do anything I like without restrictions. Not so at work. I have a separate user on my machine at work with administrator privileges.

  • My new version

    my new version is 5.92 Is my device ok?