Error Project Server 2010, % Complete, Work and Actual Work

Hi Everyone
I have a Project Server 2010 SP2 Environment, The farm contains 3 Servers.
1 WFE, 1WebApp, 1 BD. All servers in the farm are Windows Server 2008 R2 and the Data Base Server is SQL Server 2008 R2
The Context:
The Project Managers create the Project in Project Professional 2010 SP2 for support Annual Maintenance about a software, then the team members go to my tasks in PWA to create the task inside the stage in the project, then they put the actual work, then they
send the progress to his project manager.
So, the project manager goes to the approval page to approve two times, one, the task creation and two, the progress.
So far all ok but when the project manager open the Gantt in Project Professional 2010 SP2 , the task that the team member has sent appear with a 100 percent complete, but the work with 0 hours and the actual work with 0 hours too, being that should appear
with the hours the team member has sent, that is my problem.
This occur only with this project manger and his team member, all of others project managers in the platform don't report this issue.
I already have  re open the project and re publish too
So , let me know if you have some idea about this issue.
Erick Gutiérrez PMI Membership #ID 2089740 MTCS - Microsoft Project Server Managing Projects

Only other ideas is to make sure the duration isn't 0, which would make it a milestone.
Have the resources, recall the timesheets and resubmit.  Run it thru cycle again and see if they actual show up.
Finally, you can run SQL query and see where the data may be. 
1) Check if status manager is who you think it is
2) Check if project shows actuals in sql.  Doesn't explain why not showing in schedule.
cheers!
Michael Wharton, MVP, MBA, PMP, MCT, MCTS, MCSD, MCSE+I, MCDBA
Website http://www.WhartonComputer.com
Blog http://MyProjectExpert.com contains my field notes and SQL queries

Similar Messages

  • Playbook Restore error project server 2010

    HI,
    I am getting error when trying to restore Server settings using play book, my backup and restore server versions are same project server 2010 sp2.
    below is the error i am getting 
    Creating lookup table Project Work Category...
    08:16:25 :       SoapException: ProjectServerError(s) LastError=LookupTableSortOrderMustComeBeforeParentNextSiblingSortOrder Instructions: Pass this into PSClientError constructor to access all error information
    08:16:25 :       ERROR: Project Server Error: LookupTableSortOrderMustComeAfterParentSortOrder Context: Updating lookup table 
    08:16:25 :       ERROR: Project Server Error: LookupTableSortOrderMustComeBeforeParentNextSiblingSortOrder Context: Updating lookup table 
    08:16:26 :    Updating Custom Fields...
    08:16:29 :       Updating custom field Sample Compliance Proposal...
    08:16:29 :       Updating custom field Sample Approved Start Date...
    08:16:29 :       Updating custom field Sample Proposal Cost...
    08:16:30 :       Updating custom field C_Project Name - English...
    08:16:30 :       Updating custom field B_Project Name – Arabic...
    08:16:30 :       Updating custom field F_Date Requested...
    08:16:31 :       Updating custom field Cost Type...
    08:16:31 :       Creating custom field P_Service Name...
    08:16:31 :       SoapException: ProjectServerError(s) LastError=CustomFieldInvalidLookupTableUID Instructions: Pass this into PSClientError constructor to access all error information
    08:16:31 :       ERROR: Project Server Error: CustomFieldInvalidLookupTableUID Context: Updating custom field P_Service Name.
    08:16:31 :       Creating custom field H_Project Work Category...
    08:16:31 :       SoapException: ProjectServerError(s) LastError=CustomFieldInvalidLookupTableUID Instructions: Pass this into PSClientError constructor to access all error information
    08:16:31 :       ERROR: Project Server Error: CustomFieldInvalidLookupTableUID Context: Updating custom field H_Project Work Category.
    08:16:31 :       Updating custom field Project Departments...
    vijay kommireddi

    Hello Vijay,
    From error it seems to be the issue with the Project Work Category lookup table sorting. Could you please share what sorting option is selected for this Lookup table?
    Please refer to
    http://social.msdn.microsoft.com/Forums/en-US/aee17d2b-5171-40f6-88aa-d4d15472c1d7/firm-with-complex-and-frequently-changing-org-chart-wants-to-have-its-ps2010s-rbs-lut-refreshed?forum=project2010custprog
    You may run into this issue if sort order for the lookup table is not set to sort By Ascending or Descending.
    If it set to "BY Row Number" then try to set to "By Ascending or Descending" and they try backup and restore again.
    Thank you,
    Kiran K.

  • Project Server 2010 - Modification date and name of the person who made the last change in the project

    Hello everybody
    I'm with a doubt.
    I got in the business
    environment Project Server 2010 and
    would like to get the publication date,modification
    date and name
    of the person who made
    the last change in
    the project. It is possible
    to doby the native
    resources or is
    there any query in
    SQL Server to perform a
    query of this information.
    Thank you.
    Obrigado por contactar o fórum Microsoft Technet!

    Hi Hezequias,
    You can get the ProjectModifiedDate column in MSP_EPMProject_userView in the Reporting DB where you can
    get the data based on the projectUID. 
    The "last saved" date in the draft DB (be aware that querying in the draft DB is not supported by MS).
    For the "last modified by", I think it is not stored in any place.
    But you can develop custom code upon publishing the project (Event BeforePublish), writing the current
    date and username automatically into a custom enterprise field.
    Hope this helps,
    Guillaume Rouyre, MBA, MCP, MCTS |

  • Project Versions: Plan Work and Actual Work

    Hi,
    Can you pls suggest me,
    where can i get Project actual work and planned work from R/3.
    which R/3 table will provide this information for different Project Versions.
    Thes values are required against each Project version.
    Your valuable inputs will be rewarded.
    Thanks,
    Lakshmi.

    Hi,
    We have the following scenario: The system does not default the Actual Duration when the Start Date, Time and Finish Date, Time are entered on the time confirmation, it should calculate the time and insert the value in the Actual Duration field.
    Is it possilbe.
    Regards
    JF
    Please open a thread for your specific query.
    -Paul
    Moderator
    Edited by: Paul Meehan on Sep 9, 2011 10:59 AM

  • Question on original work and actual work

    Hey folks,
    Sometimes the simplest things in Project befuddle me. I'm working in Project 2010 Standard. I have a whole bunch of "Fixed Work" tasks. This is a pretty simple project, and I haven't done baselines or anything like that.
    So let's say I have a task, "Build X" that is was originally estimated as 4 hours of work. That is entered into the Work column.
    During the project, Build X gets completed, and I learn that it only took 2 hours of work. I want to enter this into Project so that we know that:
    Task "Build X" is 100% complete
    The actual work was only 2 hrs
    The original estimate was for 4 hrs
    However, if I enter 100% into either % complete or % work complete, Project changes the Actual Work to 4 hrs, which is wrong. If I set the Actual Work to 2 hours, Project changes % complete or % work complete to 50%, which is also wrong.
    Is there anything I can do here that doesn't involve baselines?
    Thanks!

    sbattisti,
    What have you got against setting a baseline? A baseline captures your original plan. The schedule will be dynamic and as things happen Project updates that dynamic plan to reflect what really happened. So no, there is no way to do what you want without
    a baseline, except perhaps of capturing the original work value in an extra field (e.g. Text1), but there's no point in doing that.
    Set a baseline. That will capture "Build X" as being originally planned at 4 hours work. When you later find out that it only took 2 hours, you enter that into the Actual Work field and set the Remaining Work field to zero. That tells Project that
    the task is in fact complete and it only took 2 hours. If you then display the Baseline Work field you will see that the original plan was 4 hours. You can also display Work Variance.
    Hope this helps.
    John
    OK, thanks very much. I'll do that. 
    I have a follow-up question, but it's not really directly related, so I will post separately, thanks!

  • Project Server 2010 compatibility with IE11 and Windows 8.1

    Hi All!
    Maybe a silly question since compatibility is always asked about older versions, but here is my question:
    Is Project Server 2010 compatible with IE11 and Windows 8.1?
    I personnaly tested with IE11 and it seems to be ok. All views and pages can be opened with IE11.
    But what about windows 8.1? 
    Has Microsoft done any communication about this?
    Thanks in advance for your helps.
    Guillaume.
    Guillaume Rouyre - MBA, MCP, MCTS

    I am seeing a minor issue with the timesheet grid after users are upgraded from IE8 to IE11.
    We are using Project Server 2010 with SP1 and Oct 2013 CU.
    When some users (using IE11) switches between filters or views in the Timesheet page, the grid shrinks making to content un readable.  The only way to get it back is to refresh the page. After a refresh, the grid returns to normal size, but the pane
    divider is too far to the left and always must be dragged to the right in order to see the task names in the left grid. 

  • Project Server 2010 Jobs All 'Waiting To Be Processed'

    Hello,
    We have installed Project Server 2010 for evaluation and are running into an issue when creating new projects in the Project Center.  The installation included SharePoint 2010 and is a single-machine install (i.e. DB and WFE on same machine). 
    We can access the site without any problem and when accessing the Project Center and electing to create a new project from Basic Project Plan template, the interface processes the request and then informs us that the request was taking a long time to process
    and to check the Manage Queue Jobs interface for status.
    Reviewing the queued jobs reveals four queued tasks for Project Create, Project Publish Notifications, Project Publish and Start Workflow, all with a Job State of 'Waiting To Be Processed'.  When we originally ran into this issue, we realized that the
    User Profile Synchronization Service was configured to run with the Network Service account and that the two relevant ForeFront Identity Manager services were not running.  We had read that this may cause the queue to not process requests, so we reconfigured
    the system to use a domain account and started the User Profile Synchronization Service Application (which in turn started the ForeFront Identify Manager services).
    However, this did not help and the jobs (as well as new jobs) are still waiting to be processed.  We don't see any errors listed in the queue and can't really find relevant errors in the SharePoint logs or event viewer.
    Has anyone else run into this problem who can provide some insight?  Thanks.
    John

    Another thing to check John, and you may well find evidence in the ULS logs, is that the queue service is really running.  Just looking in Services isn't enough.  When the queue service starts it will check for the presence of PWA sites within
    each and every (probably just one) Project Service Application you have running.  It will then spawn an extra process for each Service Application it finds that has one or more PWA instances.  So you should always see at least two Microsoft.Office.Project.Server.Queuing.exe
    processes running within Task Manager -and if you just see one the looking in the ULS logs should give an indication why it didn't start up (re-starting will give you a fresh entry in the log - which will be easier than searching through lots of logs.
    Best regards,
    Brian.
    Blog |
    Facebook | Twitter | Posting is provided "AS IS" with no warranties, and confers no rights.
    Project Server TechCenter |
    Project Developer Center |
    Project Server Help | Project Product Page

  • Is it possible to create a formula that converts a resource hours into full time units in project server 2010

    Hi
    Is it possible to create a formula that converts a resource available hours into full time equivalent units in project server 2010? Say a resource has 160 available hours for any given month this will translate into 1 FTE for this month. If it is 80 hours
    for that month then it will be 0.5 FTE and so on and so forth.
    Thanks,
    -Maurizio

    Maurizio,
    It's a bit late, but there are two OLAP cubes that can provide you with this information in a pivot table in Project Server 2010.
    "MSP_Portfolio_Analyzer" and "Resource Timephased" contains capacity measures that be used to provide calculated measures when the cube database is generated. You change OLAP cube configuration in "Server Settings -> Database Administration -> OLAP
    Database Management". In either of the aforementioned cubes, use "Calculated Measures" to create two measures:
    Member Name
    MDX Expression
    Available (FTE)
    ([capacity]-[work])/[capacity]
    Work (FTE)
    [Work]/[Capacity]
    These two fields will appear in the pivot table field list as "Values", and when combined with a "Time" column, can give you a picture of FTE usage and availability.
    I prefer the portfolio version since it contains project/assignment data and resource data, letting you see just  how resources are being utilized.
    One thing I have not been able to get around is getting ""Maximum Units" for a resource factored into the measure. A common practice is to allocate more that "100%" to generic resources to represent teams for planning purposes. The OLAP measures will show
    only 0.0 to 1.0 FTE for any resource, even if a resource represents more than one body.
    If you have an SSRS query you could share, I would appreciated it!
    Hope this helps!
    JTC
    JAckson T. Cole, PMP, MCITP

  • Project Server 2010: PWA Removing Default Project Site Security Groups When Creating a New Project

    I looked for this specific issue with Project Server 2010/PWA/SharePoint and could not find an exact answer... hopefully someone can help.
    We are currently using Project Server 2010 and have a number of project site templates that are used dependent upon the enterprise project type selected. Each of these project site templates have unique permissions which should create the default security
    groups on the project site upon publishing/syncing:
    <Project Name> Members
    <Project Name> Owners
    <Project Name> Visitors
    <Project Name> Project Managers (Project Web App Synchronized)
    <Project Name> Team Members (Project Web App Synchronized)
    Web Administrators (Project Web App Synchronized)
    Whether a user creates a project through PWA or Project Pro 2010 and imports the project into PWA, we get a weird result in the Site Permissions of the newly created project site. PWA will remove all default security groups from the project site template
    and add a whole list of users in the Site Permissions list without groups. 
    Once the project is published and the project site is created, we can then go back and add those default security groups back in the project Site Permissions and even add a couple of custom groups without them being removed on all subsequent project syncs
    or publishing. 
    How do we get PWA to not overwrite the project site templates' security groups and place each user in the proper default security groups? At the same time, how is PWA adding a number of users into the Project Site Permissions?
    Thanks in advance.

    Paul,
    Thanks for that information. Right now we are using the Test environment to turn the Auto-sync feature back on. I suspect that the reason this is happening is due to PWA groups/categories/security templates. There may be more than one PWA group that is "overwriting"
    the default project site groups upon initial creation of the project. We will look further into the security settings to tighten up the policies. 

  • Project Server 2010 - Error 20010 with a master project and 3 sub-projects during publication

    Hi,
    Here is the situation :
    One master project with three sub projects.
    Sub projects are really similar (Same ressources and nearly same tasks but only the first contain real work for now).
    Sub projects got no sub projects nor links between projects.
    The owner of the master project got read rights through projects permissions on sub projects.
    Sub projects are link in "read only".
    We applied Project Server 2010 SP2 last week end and the issue appeared monday.
    Here are the symptoms :
    When we link only one sub project (Doesn't matter which one), the owner can publish, no problems.
    With 2 sub projects, the error may occur.
    With 3 sub projects, the error always occurs.
    With admin rights, the error doesn't occur.
    Here is the error :
    ID : 20010 (0x4E2A)
    Description : You don't have required permissions to perform the action (Average traduction)
    Detail : <detail><errinfo><general><class name="Project"><error id="20010" name="GeneralSecurityAccessDenied" uid="19515c1d-2624-466f-953a-b7fc67337b81"/></class></general></errinfo></detail>
    I'm unable to determine which sub project is the culprit, if there is one, as it's working when I link only one of them.
    Thanks for your time !

    Fylim --
    If the project manager in question does not need to edit any of the three projects, the PM does not need to have Read/Write access to any of the three projects.  Because you said that the PM needs to set links in all three projects, this means that
    the PM will be editing all three projects.  In order to edit the three projects, the PM must have Read/Write access to all three.  Setting cross-project links constitutes editing of the projects, which is why the PM must have Read/Write permission. 
    Make sense?
    Regarding SP2, I am not aware that this would change anything, but I could be wrong.  The reality is that regardless of which SP you have applied to Microsoft Project and Project Server 2010, the PM in this situation MUST have Read/Write access to the
    projects that he/she needs to edit with cross-project links.  Hope this helps.
    Dale A. Howard [MVP]

  • How to add total of actual in My work- Task in project server 2010.

    Hello all, 
    I need to add total of actual in My work->Task in project server 2010.
    How can I achieve it?
    Your help is appreciated. 

    Hi Rohit,
    Unfortunately, there is no configuration which allows having the actual total work in "my tasks" page. Note that you have the total for the period for each assignment in the column next to the "work" column. In case it doesn't suit
    your need, I'd suggest to propose for example a simple report, otherwise a development could be quite complex and time consuming.
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |

  • Project Server 2010 , Project Center, Resource Center, My Work not loading

    Hi,
    We have Project Server 2010 SP-2 env
    Yesterday one of my Project Manager told me that he is not able to access any of the following page Project Center, Resource Center, My Work in our Quality env. Issue is it shows page is loading infinitely long and on botton it shows some script error mentioned
    below
    Webpage error details
    User Agent: Mozilla/4.0 (compatible; MSIE 8.0; Windows NT 6.1; WOW64; Trident/4.0; SLCC2; .NET CLR 2.0.50727; .NET CLR 3.5.30729; .NET CLR 3.0.30729; .NET4.0C; .NET4.0E)
    Timestamp: Tue, 21 Oct 2014 13:55:19 UTC
    Message: 'null' is null or not an object
    Line: 217
    Char: 4
    Code: 0
    URI: http://XXXXXXXXXXX/_layouts/inc/pwa/library/webmethodmanager.debug.js?rev=BtnvMSOtt14tg%2FnfhDTJpA%3D%3D
    Also I have checked event logs in shows WebHost failed error with Event ID 3 , complete detail mentioned below.
    Event Log Error
    WebHost failed to process a request.
     Sender Information: System.ServiceModel.ServiceHostingEnvironment+HostingManager/45523402
     Exception: System.ServiceModel.ServiceActivationException: The service '/_vti_bin/PSI/ProjectServer.svc' cannot be activated due to an exception during compilation.  The exception message is: Could not load file or assembly 'FirePoint.SharePoint.RssViewerWebPart,
    Version=1.4.7.12, Culture=neutral, PublicKeyToken=e891f27e2edd24d0' or one of its dependencies. The system cannot find the file specified.. ---> System.IO.FileNotFoundException: Could not load file or assembly 'FirePoint.SharePoint.RssViewerWebPart, Version=1.4.7.12,
    Culture=neutral, PublicKeyToken=e891f27e2edd24d0' or one of its dependencies. The system cannot find the file specified.
    File name: 'FirePoint.SharePoint.RssViewerWebPart, Version=1.4.7.12, Culture=neutral, PublicKeyToken=e891f27e2edd24d0'
       at System.Reflection.Assembly._nLoad(AssemblyName fileName, String codeBase, Evidence assemblySecurity, Assembly locationHint, StackCrawlMark& stackMark, Boolean throwOnFileNotFound, Boolean forIntrospection)
       at System.Reflection.Assembly.InternalLoad(AssemblyName assemblyRef, Evidence assemblySecurity, StackCrawlMark& stackMark, Boolean forIntrospection)
       at System.Reflection.Assembly.InternalLoad(String assemblyString, Evidence assemblySecurity, StackCrawlMark& stackMark, Boolean forIntrospection)
       at System.Reflection.Assembly.Load(String assemblyString)
       at System.ServiceModel.Activation.ServiceHostFactory.CreateServiceHost(String constructorString, Uri[] baseAddresses)
       at System.ServiceModel.ServiceHostingEnvironment.HostingManager.CreateService(String normalizedVirtualPath)
       at System.ServiceModel.ServiceHostingEnvironment.HostingManager.ActivateService(String normalizedVirtualPath)
       at System.ServiceModel.ServiceHostingEnvironment.HostingManager.EnsureServiceAvailable(String normalizedVirtualPath)
    WRN: Assembly binding logging is turned OFF.
    To enable assembly bind failure logging, set the registry value [HKLM\Software\Microsoft\Fusion!EnableLog] (DWORD) to 1.
    Note: There is some performance penalty associated with assembly bind failure logging.
    To turn this feature off, remove the registry value [HKLM\Software\Microsoft\Fusion!EnableLog].
       --- End of inner exception stack trace ---
       at System.ServiceModel.ServiceHostingEnvironment.HostingManager.EnsureServiceAvailable(String normalizedVirtualPath)
       at System.ServiceModel.ServiceHostingEnvironment.EnsureServiceAvailableFast(String relativeVirtualPath)
     Process Name: w3wp
     Process ID: 5052
    Also I have checked Brian Smith blog to resolve WebHost error with Event ID 3, but that didn't help.
    So kindly help me to get this issue resolve and do let me know in case need further details.
    Thanks

    Hi,
    From error log it seems you have some custom or thrid party web part activated in your application and that web part is not able to load which might causing those pages to get corrupt.
    As a fix can suggest you below to two thing to check
    1) Remove that "FirePoint.SharePoint.RssViewerWebPart" from your environment and try to access those PWA pages again.
    2) Even after removing above web-part solution does not fix this issue, as it is quality env can you try to disconnect and reconnect the share-point farm . Then try to access those pages again.
    Share us the latest update and your finding on this issue.
    Regards
    Sachin Vashishth MCTS

  • Problem: Task completion sync back from Exchange 2010 to Project Server 2010

    I have new installation of PS 2010 and Exchange 2010 (one server holds all roles including CAS).
    For sync between PS and EX 2010, I following the technet article Configure Project Server 2010 to work with Exchange Server 2010 at http://technet.microsoft.com/en-us/library/ff468700%28office.14%29.aspx (yes I read the second part on Impersonation, too).
    Basically I followed the video and opted for "Impersonation for all users".
    I got tasks appear in resources outlook "Tasks" folder no problem. They appeared instantly after project is published. But when the resource update the completion in outlook, it failed to update the Project server.
    The applog on Exchange server has the following events:
    A notification for subscription [IABmaWxiZXJ0Lm1zYy5hbHR1cmFzYW5hbHl0aWNzLmNvbRAAAABpsVspLo+TSpth0iMukr+TjiFq73wS0Qg=] against endpoint [http://MyPSserver/PWA/_vti_bin/PSI/ExchangeSync.asmx] couldn't be sent. (Send attempts: 2) Details: WebException:
    The remote server returned an error: (500) Internal Server Error. StatusCode: InternalServerError Internal Server Error    at System.Net.HttpWebRequest.EndGetResponse(IAsyncResult asyncResult)
       at Microsoft.Exchange.Services.Core.NotificationServiceClient.HandleResponse(IAsyncResult responseAsyncResult)
    After 8 unsuccessful attempts to send a notification for subscription [IABmaWxiZXJ0Lm1zYy5hbHR1cmFzYW5hbHl0aWNzLmNvbRAAAABaEEJ+4ahFSY6IVGcSZ7/m4kLgKCES0Qg=] against endpoint [http://MyPSserver/PWA/_vti_bin/PSI/ExchangeSync.asmx], the subscription has
    been removed. Details: WebException: The remote server returned an error: (500) Internal Server Error. StatusCode: InternalServerError Internal Server Error    at System.Net.HttpWebRequest.EndGetResponse(IAsyncResult asyncResult)
       at Microsoft.Exchange.Services.Core.NotificationServiceClient.HandleResponse(IAsyncResult responseAsyncResult
    The W3C log on PS app server has the following related entries (401 and 500 errors. 10.0.0.76 is Exch server. 10.0.0.77 is the PS app server):
    2014-03-20 18:12:39 10.0.0.77 POST /PWA/_vti_bin/PSI/ExchangeSync.asmx - 80 - 10.0.0.76 - 401 2 5 0
    2014-03-20 18:12:39 10.0.0.77 POST /PWA/_vti_bin/PSI/ExchangeSync.asmx - 80 - 10.0.0.76 - 401 1 2148074254 15
    2014-03-20 18:12:39 10.0.0.77 POST /_vti_bin/PSI/ExchangeSync.asmx - 80 MyDomain\MyExchServer$ 10.0.0.76 - 500 0 0 31
    2014-03-20 18:12:39 10.0.0.77 POST /PWA/_vti_bin/PSI/ExchangeSync.asmx - 80 - 10.0.0.76 - 401 2 5 0
    2014-03-20 18:12:39 10.0.0.77 POST /PWA/_vti_bin/PSI/ExchangeSync.asmx - 80 - 10.0.0.76 - 401 1 2148074254 0
    2014-03-20 18:12:39 10.0.0.77 POST /_vti_bin/PSI/ExchangeSync.asmx - 80 MyDomain\MyExchServer$ 10.0.0.76 - 500 0 0 31
    2014-03-20 18:12:39 10.0.0.77 POST /PWA/_vti_bin/PSI/ExchangeSync.asmx - 80 - 10.0.0.76 - 401 2 5 0
    2014-03-20 18:12:39 10.0.0.77 POST /PWA/_vti_bin/PSI/ExchangeSync.asmx - 80 - 10.0.0.76 - 401 1 2148074254 0
    2014-03-20 18:12:39 10.0.0.77 POST /_vti_bin/PSI/ExchangeSync.asmx - 80 MyDomain\MyExchServer$ 10.0.0.76 - 500 0 0 31
    2014-03-20 18:12:41 10.0.0.77 POST /PWA/_vti_bin/PSI/ExchangeSync.asmx - 80 - 10.0.0.76 - 401 2 5 0
    2014-03-20 18:12:41 10.0.0.77 POST /PWA/_vti_bin/PSI/ExchangeSync.asmx - 80 - 10.0.0.76 - 401 1 2148074254 0
    2014-03-20 18:12:41 10.0.0.77 POST /_vti_bin/PSI/ExchangeSync.asmx - 80 MyDomain\MyExchServer$ 10.0.0.76 - 500 0 0 62
    2014-03-20 18:28:39 10.0.0.77 POST /PWA/_vti_bin/PSI/ExchangeSync.asmx - 80 - 10.0.0.76 - 401 2 5 15
    2014-03-20 18:28:39 10.0.0.77 POST /PWA/_vti_bin/PSI/ExchangeSync.asmx - 80 - 10.0.0.76 - 401 1 2148074254 0
    2014-03-20 18:28:39 10.0.0.77 POST /_vti_bin/PSI/ExchangeSync.asmx - 80 MyDomain\MyExchServer$ 10.0.0.76 - 500 0 0 46
    2014-03-20 18:28:39 10.0.0.77 POST /PWA/_vti_bin/PSI/ExchangeSync.asmx - 80 - 10.0.0.76 - 401 2 5 15
    2014-03-20 18:28:39 10.0.0.77 POST /PWA/_vti_bin/PSI/ExchangeSync.asmx - 80 - 10.0.0.76 - 401 1 2148074254 0
    2014-03-20 18:28:39 10.0.0.77 POST /_vti_bin/PSI/ExchangeSync.asmx - 80 MyDomain\MyExchServer$ 10.0.0.76 - 500 0 0 31
    2014-03-20 18:28:39 10.0.0.77 POST /PWA/_vti_bin/PSI/ExchangeSync.asmx - 80 - 10.0.0.76 - 401 2 5 0
    2014-03-20 18:28:39 10.0.0.77 POST /PWA/_vti_bin/PSI/ExchangeSync.asmx - 80 - 10.0.0.76 - 401 1 2148074254 0
    2014-03-20 18:28:39 10.0.0.77 POST /_vti_bin/PSI/ExchangeSync.asmx - 80 MyDomain\MyExchServer$ 10.0.0.76 - 500 0 0 15
    2014-03-20 18:28:41 10.0.0.77 POST /PWA/_vti_bin/PSI/ExchangeSync.asmx - 80 - 10.0.0.76 - 401 2 5 15
    2014-03-20 18:28:41 10.0.0.77 POST /PWA/_vti_bin/PSI/ExchangeSync.asmx - 80 - 10.0.0.76 - 401 1 2148074254 0
    2014-03-20 18:28:41 10.0.0.77 POST /_vti_bin/PSI/ExchangeSync.asmx - 80 MyDomain\MyExchServer$ 10.0.0.76 - 500 0 0 15
    I am new to PS 2010. Help is appreciated. Thanks.

    Here are the errors found in Project Queues:
    ExchangeSyncExchangeSubscriptionUpdateForUserFailed (40511). Details: id='40511' name='ExchangeSyncExchangeSubscriptionUpdateForUserFailed' uid='ef501cc2-9305-47b5-92b3-021e3b41d1b5' teamMemberUid='b8f2e0cd-9882-4677-be61-b2780b32bae5' exception='System.NullReferenceException:
    Object reference not set to an instance of an object. at Microsoft.Office.Project.Server.ExchangeSync.ExchangeSyncUtil.UpdateExchangeSubscription(Guid resourceUid, SubscriptionContext context) at Microsoft.Office.Project.Server.ExchangeSync.ExchangeSyncUtil.UpdateExchangeSubscription(Guid
    resourceUid) at Microsoft.Office.Project.Server.ExchangeSync.ExchangeSubscriptionRefreshProcessor.Refresh(PlatformContext ctx)'.
    ReportingProjectChangeMessageFailed (24006) - The INSERT statement conflicted with the FOREIGN KEY constraint "FK_MSP_EpmAssignment_ResourceOwnerUID". The conflict occurred in database "ProjectServer_Reporting", table "dbo.MSP_EpmResource", column 'ResourceUID'.
    The statement has been terminated.. Details: id='24006' name='ReportingProjectChangeMessageFailed' uid='ef4e51a1-8cb2-4ec2-bfc4-530f1f34cd8c' QueueMessageBody='Project UID='2668bb26-5c23-42ce-843a-fa49feadba05'. PublishType='ProjectPublish'' Error='The INSERT
    statement conflicted with the FOREIGN KEY constraint "FK_MSP_EpmAssignment_ResourceOwnerUID". The conflict occurred in database "ProjectServer_Reporting", table "dbo.MSP_EpmResource", column 'ResourceUID'. The statement has been terminated.'.
    ReportingProjectChangeMessageFailed (24006) - The INSERT statement conflicted with the FOREIGN KEY constraint "FK_MSP_EpmAssignment_ResourceOwnerUID". The conflict occurred in database "ProjectServer_Reporting", table "dbo.MSP_EpmResource", column 'ResourceUID'.
    The statement has been terminated.. Details: id='24006' name='ReportingProjectChangeMessageFailed' uid='0b88178b-2e45-41af-a85f-8c5590e9c3e7' QueueMessageBody='Project UID='2668bb26-5c23-42ce-843a-fa49feadba05'. PublishType='ProjectPublish'' Error='The INSERT
    statement conflicted with the FOREIGN KEY constraint "FK_MSP_EpmAssignment_ResourceOwnerUID". The conflict occurred in database "ProjectServer_Reporting", table "dbo.MSP_EpmResource", column 'ResourceUID'. The statement has been terminated.'.
    ReportingProjectChangeMessageFailed (24006) - The INSERT statement conflicted with the FOREIGN KEY constraint "FK_MSP_EpmAssignment_ResourceOwnerUID". The conflict occurred in database "ProjectServer_Reporting", table "dbo.MSP_EpmResource", column 'ResourceUID'.
    The statement has been terminated.. Details: id='24006' name='ReportingProjectChangeMessageFailed' uid='0d7421f6-2579-4656-b956-d50ecc7f5f1c' QueueMessageBody='Project UID='2668bb26-5c23-42ce-843a-fa49feadba05'. PublishType='ProjectPublish'' Error='The INSERT
    statement conflicted with the FOREIGN KEY constraint "FK_MSP_EpmAssignment_ResourceOwnerUID". The conflict occurred in database "ProjectServer_Reporting", table "dbo.MSP_EpmResource", column 'ResourceUID'. The statement has been terminated.'.
    ReportingProjectChangeMessageFailed (24006) - The INSERT statement conflicted with the FOREIGN KEY constraint "FK_MSP_EpmAssignment_ResourceOwnerUID". The conflict occurred in database "ProjectServer_Reporting", table "dbo.MSP_EpmResource", column 'ResourceUID'.
    The statement has been terminated.. Details: id='24006' name='ReportingProjectChangeMessageFailed' uid='3456b70e-fe16-4b3a-ab66-f2a5237fbaeb' QueueMessageBody='Project UID='2668bb26-5c23-42ce-843a-fa49feadba05'. PublishType='ProjectPublish'' Error='The INSERT
    statement conflicted with the FOREIGN KEY constraint "FK_MSP_EpmAssignment_ResourceOwnerUID". The conflict occurred in database "ProjectServer_Reporting", table "dbo.MSP_EpmResource", column 'ResourceUID'. The statement has been terminated.'.
    ReportingProjectChangeMessageFailed (24006) - The INSERT statement conflicted with the FOREIGN KEY constraint "FK_MSP_EpmAssignment_ResourceOwnerUID". The conflict occurred in database "ProjectServer_Reporting", table "dbo.MSP_EpmResource", column 'ResourceUID'.
    The statement has been terminated.. Details: id='24006' name='ReportingProjectChangeMessageFailed' uid='fc78474a-bf5c-422c-a209-cb79e3201e38' QueueMessageBody='Project UID='2668bb26-5c23-42ce-843a-fa49feadba05'. PublishType='ProjectPublish'' Error='The INSERT
    statement conflicted with the FOREIGN KEY constraint "FK_MSP_EpmAssignment_ResourceOwnerUID". The conflict occurred in database "ProjectServer_Reporting", table "dbo.MSP_EpmResource", column 'ResourceUID'. The statement has been terminated.'.
    ReportingProjectChangeMessageFailed (24006) - The INSERT statement conflicted with the FOREIGN KEY constraint "FK_MSP_EpmAssignment_ResourceOwnerUID". The conflict occurred in database "ProjectServer_Reporting", table "dbo.MSP_EpmResource", column 'ResourceUID'.
    The statement has been terminated.. Details: id='24006' name='ReportingProjectChangeMessageFailed' uid='d2f4b313-0c21-4a2c-b8a7-f6bd7aef13fe' QueueMessageBody='Project UID='2668bb26-5c23-42ce-843a-fa49feadba05'. PublishType='ProjectPublish'' Error='The INSERT
    statement conflicted with the FOREIGN KEY constraint "FK_MSP_EpmAssignment_ResourceOwnerUID". The conflict occurred in database "ProjectServer_Reporting", table "dbo.MSP_EpmResource", column 'ResourceUID'. The statement has been terminated.

  • Do I *really* need a Service Connection Point in AD to complete a Project Server 2010 SP2 installation?

    Hi all,
    I have installed Project Server 2010 SP2 and run psconfig.exe
    PSCONFIG is failing because it cannot set up a Service Connection Point in AD. I've checked in AD and the contains 'Microsoft SharePoint Products' does not exist. All the resolutions I can find suggest adding the container into AD.
    The issue I have is that I have no control of the AD, and adding containers will take lengthily negotiation.
    Is there any way of completing the installation and getting my site back without adding the container into AD?
    Thanks in advance.

    other solutions
    1) check timer service see if it is running
    http://www.jonthenerd.com/2011/06/30/sharepoint-2010-sp1-upgrade-error-unable-to-create-a-service-connection-point-in-the-current-active-directory-domain/
    2) check UAC (and the rest of the technet answers - some are listed below)
    http://social.technet.microsoft.com/Forums/en-US/94a8bb64-e0ea-493f-8e29-01347b1fc6c7/psconfig-fails-failed-to-upgrade-sharepoint-products
    3) My workaround:I
    run once again the command „PSConfig.exe -cmd upgrade -inplace b2b -force -cmd applicationcontent -install -cmd installfeatures“  in
    the “Bin” Folder as an administrator console session.In the moment I saw the staus “Configurationtask 5 of 6 is executed”
    I start to run the command “net start SPTraceV4 & net start SPWriterV4 & net start SPAdminV4 & net start SPSearch4 & net start SPTimerV4” in a parallel administrator console session and after that the configuration task finished successfully.
    http://social.technet.microsoft.com/Forums/en-US/94a8bb64-e0ea-493f-8e29-01347b1fc6c7/psconfig-fails-failed-to-upgrade-sharepoint-products
    4) Try running the psconfig.exe command a second time
    5) had the same issue and called Microsoft support.  Here is the fix:
    Stop the "SharePoint 2010 Timer" service
    Delete ONLY the xml files from C:\ProgramData\Microsoft\SharePoint\Config\216f8013-b78b-4e5b-8631-3a5f4c7277e8
    Note: Do NOT delete the cache.ini file in this folder
    Edit cache.ini and change to "1"
    Start "SharePoint
    2010 Timer" service
    Run psconfig again:  PSConfig.exe -cmd upgrade -inplace b2b -wait -force
    6) Initially I tried http://support.microsoft.com/kb/2009272 but
    it did not help (I re-implemented later).
    I re-registered the DLL’s as perhttp://social.technet.microsoft.com/Forums/da/winservergen/thread/b4bd0deb-45d0-4661-8c50-a2b45db41103 from
    NareshD.  I do not believe this is necessary unless there is a corruption in the system but I am noting here just
    in case.
    I tried to run The PSConfig but it was failing:  I
    had to do the following in order to make it finish successfully:
    (from same page at http://social.technet.microsoft.com/Forums/en-US/smallbusinessserver/thread/94a8bb64-e0ea-493f-8e29-01347b1fc6c7/)
    On the migrated SBS2011 PSCDiagnostic Log I found no entry to detect or start the services SPWriterServiceInstance and SPTimerServiceInstance.
    I run once again the command „PSConfig.exe -cmd upgrade -inplace b2b -force -cmd applicationcontent
    -install -cmd installfeatures“ in the “Bin” Folder as an administrator console session.
    In
    the moment I saw the status “Configuration task 5 of 6 is executed” I
    start to run the command “net start SPTraceV4 & net start SPWriterV4 & net start SPAdminV4 & net start SPSearch4 & net start SPTimerV4” in a
    parallel administrator console session and after that, the configuration task finished successfully.  (I
    just opened another cmd window and copy/paste the sequence below when I saw the status “Configuration Task x of y” on the screen:
    net start SPTraceV4 
    net start SPWriterV4 
    net start SPAdminV4 
    net start SPSearch4 
    net start SPTimerV4
    -Note SPSearch4 is disabled in our system…
    Very awkward but it worked…
    I implemented http://support.microsoft.com/kb/2009272 again.
    Backup started working with no errors.

  • Project Server 2010 PWA Provisioning Error - System.UnauthorizedAccessException: Access is denied.

    Hi,
    When migrating from a Prod Environment to a Test Environment using the Project Server 2010 5 Database backup and restore process (actually 6 DB's with the Project Sites DB), upon encountering a failure during provisioning the PWA Instance, we get the errors listed
    at the base of this posting in our Event Logs.
    To clarify what we have done already, we have:
    1. Backed up the 6 databases from the Source Environment.
    2. Removed the existing PWA_Content and PWS_Content (Project Sites) databases from the Target Environment Farm.
    3. Restored the 6 databases in the Target Environment.
    4. Given the SP Farm Service Account 'db_owner' rights to each of the 6 restored databases.
    5. Added the PWA_Content and PWS_Content databases  (exact same names) to the Target Environment.
    6. Locked down (offline/stopped), all of the SharePoint Content databases in the Farm except for the PWA_Content database.
    7. Run the PWA Provisioning process from the 'Project Server' SharePoint Service in Central Admin.
    It is during the PWA provisioning that we encounter these errors.
    As the Target Environment is for Test/Dev purposes, the SP Farm Service Account is setup to support all of the SharePoint Farm Services, is in the Local Admin Group of each of the Servers (App, WFE and DB), and is actually in the sysadmin
    role on the DB Server.
    Any suggestions on what is causing this denied access situation would be most appreciated.
    Cheers,
    Wayne
    Event Log Entries:
    ============================================
    Log Name:      Application
    Source:        Microsoft-SharePoint Products-Project Server
    Date:          1/22/2014 2:47:34 PM
    Event ID:      6971
    Task Category: Provisioning
    Level:         Error
    Keywords:     
    User:          ACCOUNTS\svc_psfarm
    Computer:      SERVER.accounts.domain.com
    Description:
    Failed to provision site PWA with error: Microsoft.Office.Project.Server.Administration.ProvisionException: Membership synchronization failed. ---> System.UnauthorizedAccessException: Access is denied. (Exception from HRESULT: 0x80070005 (E_ACCESSDENIED))
       at Microsoft.SharePoint.Library.SPRequest.AddRoleDef(String bstrUrl, String bstrName, String bstrDescription, Boolean bHidden, Int32 lRoleOrder, UInt64 iPermMask, Byte iType, Int32 lRoleDefID)
       at Microsoft.SharePoint.SPRoleDefinitionCollection.AddCore(SPRoleDefinition role)
    etc....
    Failed to create the Report Center web (Exception: PSI Entry Point:
    Project User: DOMAIN\svc_psfarm Correlation Id: c0a30b18-46e4-4447-b469-f8fd3bb1490a
    PWA Site URL: http://pstest2010/PWA
    SSP Name: Project Server
    PSError: NoError (0))
    Failed to grant 'DOMAIN\svc_psfarm' access to web application 'SPWebApplication Name=Portal'.
    Error: System.Security.SecurityException: Access denied.  Only machine administrators are allowed to create administration service job definitions of type: Microsoft.SharePoint.Administration.SPUpdateWorkerProcessGroup, Microsoft.SharePoint, Version=14.0.0.0,
    Culture=neutral, PublicKeyToken=71e9bce111e9429c.
       at Microsoft.SharePoint.Administration.SPAdministrationServiceJobDefinition..ctor(String name, SPService service, SPServer server, SPJobLockType lockType)
       at Microsoft.SharePoint.Administration.SPUpdateWorkerProcessGroup..ctor(SPTimerService timerService, String[] loginsToAdd, String[] loginsToRemove)
       at Microsoft.SharePoint.Administration.SPWebApplication.GrantAccessToProcessIdentity(String username, SPPolicyRoleType policyRole)
       at Microsoft.Office.Project.Server.Administration.PsiServiceApplication.GrantAccessToWebApp(List`1 webApps, String userName) The Zone of the assembly that failed was: MyComputer

    Is the Test and Production in the same domain. If they are not, then the SIDs associated with the SQL accounts may look the same but they are not.  At times, I have had to recreated accounts when in different domains.
    I would also use PowerShell cmdlets and see if it finds any issues, such as Test-SPContentDatase.. Validate the SharePoint content databases, because if not setup properly the Provisioning will fail.
    Also check these properties.
    $web=get-spweb http://prodproj01/pwa
    $Web.AllProperties[“PWAURL”] ### see what the value is.. you may have to blank it out, specially if it is pointing to a different URL
    Here is how to fix.
    $Web.AllProperties[“PWAURL”]=””
    $web.Update()
    Michael Wharton, MVP, MBA, PMP, MCT, MCTS, MCSD, MCSE+I, MCDBA
    Website http://www.WhartonComputer.com
    Blog http://MyProjectExpert.com contains my field notes and SQL queries