Error reading material cost estimate for sales order (KE292)

Dear All,
I have an issue with billing. we are posting july month transactions, the material cost is maintained through MR21. When releasing billing document for accounting we are getting error message like"Error reading the material cost estimate for sales order "11"
Message no. KE292
Diagnosis
In Profitability Analysis (CO-PA), the system tried to valuate item 000010 of sales order 11 by reading the corresponding product cost estimate.
However, no product cost estimate could be found for this sales order item.
The system accessed product costing for product AMLFP011011XX00P using costing key YB3 as defined in the
CO-PA Customizing settings.
System Response
The system cannot process the document any further.
Procedure
Check your Customizing settings."
We cross checked with other client as a current date and we ran cost estimate through CK40N with same material. and we posted entries. Here it is working fine. but in above process it is not working. Can you pls guide me where i missed.
Regards,
Nagaraju,

Hi,
When the Costing Key is assigned to the material types in the COPA customizing, then system expects Cost estimation when billing is released to Accounts.
If you dont run cost estimation but update the material master through MR21, system will not accept as in the Costing key configuration you must have selected the Current Standard price field for the valuation.
Hence, try to run cost estimation and then do releasing.
Thanks & Regards
Ravi Kumar

Similar Messages

  • Cost estimate for sales order

    Dear Friends,
    In a make to stock scenario a finished good is sold from the depot and thereafter it is returned. After creating the credit memo for return, when the same is being released to accounting in VF02, the system throws an error message which reads 'Error reading the material cost estimate for sales order "12000373". and the document cannot be passed on to accounting. Although, we are able to release the sales invoice to accounting without any error. In the item condition tab for sales order the standard cost VPRS is updated as we enter the plant.
    Strategy group for the material is 40-planning with final assembly. The concern over here is that why the system is asking for cost estimate at the level of sales return.
    Please suggest why this error is coming and how the same can be released to accounting.
    Regards

    Hello Friend,
    The problem is that Material you are using for that Cost Estimate is not done. So go to T.Code CK11 give the Costing Variant, Material & Plant and go on entar and entar. If everything is green in end then save it.
    Then Go to T.code CK24 give the Company Code, material & Plant and then execute.
    Click Back and click on Release Button and then execute.
    Then try the Transaction you have got the error again.
    Hope this helps.

  • BOM Cost Estimate for sales order items

    Hi experts,
        Which data source could extract data created by CK51N (Order BOM Cost Estimate )? We need to get BOM Cost estimate (including input material and activity) for sales order items.
        The closest one is 0CO_PC_01, but it extracts itemizations for production order.
        It's urgent.Helpful answers would be awarded.Thanks.
    Regards,
    Aaron

    Hi Henry,
       They even do not have Sales Order segment. How could I get cost estimate data based on sales order?
    Regards,
    Aaron

  • Product cost collector for sales order related production

    Hi Friends,
    This is Azam and here i am new to this discussion forum.
    we are in situation that use diffrent variant for configurable material in sales order related production,
    I would like to have some information about use product cost collector for this kind of sales order related production,
    also I want to know difference between prelimanary cost estimate or cost estimate for sales order?
    Please co-operate me.
    I would be highly appriciated if you can respond at the earliest.
    Thanks
    Azam

    Hi,
    Here, for each sales order item, you will have sales order cost estimate. This enables the system to compute the variances once the actual costs are booked against the production.
    In the case of preliminery cost, we get the preliminery cost for production order as a plan cost and is not being used for the computation of variance but only for comparision purpose which is very marginally used.
    Trust this helps much and do encourage our efforts!
    Cheers!

  • Error when Create Cost Estimate for Material using CK11

    Dear Experts,
    I have a material ABCD which is FOC parts:-
    1) Procurement type: F
    2) Special procurement type: Z (at first, it was wrongly entered as B. I changed special procurement to Z & the message 'The procurement type of the special procurement type is E' displayed but I still can save & system allowed it).
    3) Standard price is 0.00 as this is FOC.
    Firstly, I run CK11 for material EFGH which is the parent of material ABCD.
    This time, the material ABCD has special procurement type B. I received error messages:
    1) No price could be determined for material ABCD in plant xyz,
    2) Cost component split costed with value of zero,
    3) Cost estimate for material ABCD in plant xyz is incorrect.
    Then, I changed special procurement type for material ABCD from B to Z and run CK11 again. Still the same error occurred.
    Could someone advise me how to run CK11 without errors.
    Thanks in advance!

    I don't know if B and Z are really the name of your special procurement keys or you are just using them as examples.  Either way, the special procurement key is critical for determining how your material is valued.  It is used for such things as stock transfer from other plant, subcontracting, and consignment processes.  Can you tell me how these special proccurement keys are set or what you want to use these keys for.  You can find the configuration for these key under menu path Controlling - Porduct cost controlling - Product cost planning - Material cost estimate with quantity structure - Settings for quantity structure control - Master data - Check special procurement types.
    thanks,

  • Error during Material Cost Estimate (CK11N)

    hi friends,
    I am getting am error during the material cost estimate run.(ck11n)
    "No control record for the activity type"
    please let me know what is the problem.
    regards
    Ramesh

    Ramesh,
    System is not able to determine activity type price.
    You need to input activity price in transaction KP26 for Version 0/Period/Cost Center/Activity Type combination.
    Regards,
    Prasobh

  • Cost Calculation for Sales Order Collectively

    Hi,
    We need to recalculate sales Order cost. We can recalculate Sales order cost in SAP T Code VA02 for individual sales order. I am having approx 1000 sales order of which cost needs to be recalculated. Can any one help me How to recalculate Cost of these sales order Collectively.
    Thanks in Advance,
    Pawan Kumar

    Hi,
    I guess you should select B (carry new pricing). Although the system would try to reprice, in fact I guess that no pricing value would be change. If this doesn't fit your requirements then SD expert should answer your question (there are some ways you can control the pricing calculation, the ultimate way is some coding under REQUIREMENTS, but I would use it as last option).
    Benni

  • How to split cost allocations for sales order lines?

    Has anyone here solved a requirement to split the cost of goods sold from a service request debrief.
    The scenario is -
    1.  A debrief of a service request is completed.
    2.  Material is issued and technical labor used and expenses incurred.
    3.  I am hearing that in Oracle Service, the material is only costed but not the technical labor and expenses.
    4.  No splitting can occur in any of the cases through standard Oracle?
    5.  We have gone down the path of creating sales order line types for each department (unique code combination) and then splitting the COGS in SLA.
    6.  This way, we have to create items for labor and expenses.
    Is this the only semi-standard way.
    Thanks for your thoughts in advance.

    Hi
    I have reverse the sales order settlement, PP order settlement to sales order and I have also done KB11N for transfering the cost to the new production order.
    The only problem is I was unable to transfer labour hour confirmation as cost element used for this are not for transfering cost. If I will reverse the confirmation in PP order system will reverse material movement also which I don't want any more. Can you please tell me how to I reverse the Labour hours with out affecting goods movement?
    Many thanks

  • Update Material Availability Date for Sales Order having a Delivery

    Dear Gurus,
    We have a bit out of the way scenario. There is a o/b delivery already added to a shipment. And then we receive a IDOC from external MES System (i.e. Production) with new material availability date. This new material availability date is updated on Sales Order. In short the order is delayed.
    Current Solution:
    In this case the user has to remove the delivery from the shipment manually. then the IDOC deletes the  delivery and the updates the sales order with new date followed by creation of new delivery.
    The business expects to updated the Sales Order material availability date without changing Shipment / delivery. Any solution?
    Current solution has to be changed as for Shipment purpose changes are made to delivery which are lost when the delivery is deleted.
    Edited by: abhishek singh on Feb 3, 2012 10:21 AM

    hi
    in this case you have to adopt the business process change.
    you have to update the EDI first and then you create delivery.

  • Material cost / Price on sales order ?

    Do we get the material Cost / Price (Vendor Material price ) on sales Order ?
    I means can we see the material Cost and Material Sales price in Sales order ?
    Hope my question clear .

    Hi -
          Please follow above answer and ignore my reply. 
    Thanks!
    Anesh B
    Edited by: Anesh B on Oct 7, 2009 4:28 PM

  • Update Unit Cost Estimate in sales order

    Hi,
    I want to update the Unit cost estimate in the sales order while saving. The unit cost estimate is coming from the Z-table and it is supposed to update in the sales order in the sales order user exit.
    Can you guys please suggest any function module or anything to update it ?
    Thanks in advance
    Hemant

    Are you asking in VA01/VA02 "while saving ... in the sales order user exit"
    - Check [User Exits In Sales Document Processing|http://help.sap.com/saphelp_46c/helpdata/en/1c/f62c7dd435d1118b3f0060b03ca329/content.htm], Use USEREXIT_SAVE_DOCUMENT_PREPARE or USEREXIT_SAVE_DOCUMENT.
    Or are you mass-changing order from a report "any function module"
    - Check [BAPI_SALESORDER_CHANGE|http://forums.sdn.sap.com/search.jspa?objID=c42&q=BAPI_SALESORDER_CHANGE]
    Regards,
    Raymond

  • Material Availability Report for Sales Order

    Hi,
    Is there any report which gives me for a sale order line item which is either pending or not yet picked in delivery, but for which stock is not available. If such report is not available then what to we do for getting the same?
    Regards,
    Ajit

    Hi ajit
    In VA05 itself you can see Ordered  qty, Open order qty and confirmed quantity , Delivered qty , Delivered  date  .Even  Laxmipathi also said same thing and  i also agree with his words.
    Regards
    Srinath

  • Material substitution program for sales order

    Hi,
    I need to do a program with these requirements:
    <<The substitution program (single process) must run for all sales orders as soon as Delivery block is set to VA and also when delivery block is removed.
    Advice : Trigger program using an output type determined in the sales order>>
    I need to know how to trigger this single process using "output".
    Has any of u done this before? I've no idea where to start! Can anyone help me?
    Tarick.

    Hi ajit
    In VA05 itself you can see Ordered  qty, Open order qty and confirmed quantity , Delivered qty , Delivered  date  .Even  Laxmipathi also said same thing and  i also agree with his words.
    Regards
    Srinath

  • Invoiced blocked for sales order (configurable material external procurement )

    Hello Expert
    Configurable material external procurement
    Invoiced blocked because ,"Error reading the material cost estimate for sales order "75501"
    Message no. KE292
    Diagnosis
    In Profitability Analysis (CO-PA), the system tried to valuate item
    000010 of sales order 75501 by reading the corresponding product cost
    estimate.
    However, no product cost estimate could be found for this sales order
    item.
    The system accessed product costing for product 10820 using costing
    key 002 as defined in the
    CO-PA Customizing
    settings.
    System Response
    The system cannot process the document any further.
    Procedure
    Check your Customizing settings.
    Note:We can't run cost estimate and releasing it because it's a configurable material  but external procurement. We place a purchse order based on configurable sales orser
    Thanks
    Parves

    Hello Declan,
    Thanks for your reply. Could you please give me the steps for Maintain the
    sales order cost estimate?
    Requirement: Customer service receive order with variant configuration product,
    then MRP Crete PeReq, convert  PO and
    send to supplier .Supplier configure the product and direct delivery to
    customer. Supplier sends an invoice to us. Then we send invoice to our customer
    Thanks
    Parves

  • Costins for Sales order & Production Order

    I require an urgent clarification on the following:
    We are in Producing to Sales Order scenario.  We are using separate costing variants for Sales Order and Production Order
    Sales order is costed first. 
    the valuation variant in the costing variant for Sales order treats material valuation in the following order:
    1. Plan price for the period
    2. Price indicator from the material master
    2. Future standard price
    Then the Production order is released.
    In the Production order, the valuation variant says the material valuation as :
    1. Preliminary cost estimate from sales order
    2. Price indicator from the material master.
    My doubt is since the production order costing variant says the first option for material valuation is 'preliminary cost estimate from sales order', which value of the raw materials will be picked in the Production Order cost analysis ?  Is it from the Sales order costimate as prer preliminary cost estimate or is it as per the price indicator from the material master ?

    I require an urgent clarification on the following:
    We are in Producing to Sales Order scenario.  We are using separate costing variants for Sales Order and Production Order
    Sales order is costed first. 
    the valuation variant in the costing variant for Sales order treats material valuation in the following order:
    1. Plan price for the period
    2. Price indicator from the material master
    2. Future standard price
    Then the Production order is released.
    In the Production order, the valuation variant says the material valuation as :
    1. Preliminary cost estimate from sales order
    2. Price indicator from the material master.
    My doubt is since the production order costing variant says the first option for material valuation is 'preliminary cost estimate from sales order', which value of the raw materials will be picked in the Production Order cost analysis ?  Is it from the Sales order costimate as prer preliminary cost estimate or is it as per the price indicator from the material master ?

Maybe you are looking for

  • Flash download/close Internet Explorer Windows

    Can't download Flash. Error message indicates to close all Internet Explorer windows and I have. Any suggestions?

  • Skype 7.1 has stopped working

    Hello, for the past month, on startup on Skype (7.1), appears the message "Skype has stopped working". I have installed and uninstalled it several times but couldn't fix the problem. I also had problems with IE11, so yesterday I managed to have IE9 i

  • From SQL Server to Oracle 10g

    Hi!! My IT staff have been using SQL Server for quite a time and we have set up all our procedures under this platform, for example, our initial concern in this phase of the migration is: Under SQL Server we use templates that we use to import data i

  • Pdf in ibook gets directed to a website

    hi, i am trying to get back to the lib to see the rest of my ebook. With 1 tap i should see the 'lib' button at the top left corner to return back to the main lib. But instead of that it got directed to a website. How can i work around it? please fur

  • If i pre-order the iphone5 will i receive it the same time as when it comes out in the shops?

    if i pre-order the iPhone5 from the apple online store, will i get it the same time as it gets released in the shops on september 21st? please help, thanks