Hi colleagues!
I have an error when I try to delete a planning version. I get the error "live chace is not available" with error message number "/SAPAPO/MVM071". I think is a basis error.
Any help would be appreciated.
-Italo

Hi Hugo,
The first thing to check would be if liveCache is up and running. If you have access to transaction LC10 >> Click on liveCache: Monitoring or F5.
In this screen make sure the Operating condition of your livecache is active (green signal). If this is not green contact your BASIS team.
Thanks,
Somnath

Similar Messages

  • Internal error [/SAPAPO/OM_TS_TGRID_CREATE]

    Hi All,
    I am using  BAPI BAPI_PBSRVAPS_GETDETAIL to read live cache key figure. Its working finr when I execute the program in foreground and returns values but when I try executing this is background it gives me following error in Job Log:-
    Internal error [/SAPAPO/OM_TS_TGRID_CREATE].
    Can somebody suggest me the root cause and remedy for the same. I try doing planning area initializationa and live cache consistency check also but no luck.
    A timely reply will be highly appreciated.
    Thanks !
    Regards,
    Chandan

    Hi Chandan,
    I checked and found no sap notes similar to scm 4.0.  I would suggest to raise a OSS message to SAP so that they will advise on suitable support pack or sap note to implement.
    Regards
    R. Senthil Mareeswaran.

  • Error /SAPAPO/TSM 041 when loading from InfoCube to SNP planning area

    I am using APO V5.1.
    I have a 'backup' InfoCube with characteristics 9ARNAME and 9AVERSION which I'm loading to an SNP planning area via trans /SAPAPO/TSCUBE. The InfoCube is itself populated from the 9ARE aggregate of the SNP planning area.
    But I get error /SAPAPO/TSM 041when I run the load, suggesting absence of a required characteristic or navigation attribute in the Cube. Do I need 9ALOCNO for instance?
    Can anyone advise me here?...

    Hi,
    I am not very sure about the 9ARE aggregate (haven't used it in backups), but RTSCUBE is used to copy time Series (TS) KF data from cube to planning area (SNP or DP).
    Are you trying to restore some time series data from your backup cube to the planning area? If yes, then do a mapping of characteristic from cube to planning area in RTSCUBE, and also map the TS KF between cube and planning area.
    If your KF is not a time series KF, then you can't copy it from cube to planning area. You could get data to cube for some reporting, otherwise I am not sure what use the backup is for you. For SNP, most of the data would be received from R/3, so there's not much point in having a backup.
    Hope this helps.
    Thanks - Pawan

  • Planning Book Error (/SAPAPO/ADVX_MACROS_GET )

    I created a planning book and used /sapapo/sdp94  to enter into planning book
    when deleted using same transaction /sapapo/sdp8b , and now when i am trying to use trans code /sapapo/sdp94 ..its not letting me go in .
    It is giving  an  Internal error: /SAPAPO/ADVX_MACROS_GET
    When i use some other id and go to planning book through  /sapapo/sdp94 ..i am able to go there .
    Anybody knows about it . It would be highly appreciated and suitably rewarded

    Issue resolved . I recreated planning book with same name

  • Error /SAPAPO/TSM227 in APO SNP capacity view

    I am using APO V5.1.
    In an SNP capacity view (copied from SAP standard 9ASNP94 view but modified with some bespoke key figures), I have error /SAPAPO/TSM227 (Key figure not available for selection) when I do the following:
    - open the view
    - select a resource
    - drill down by product (or by dependent objects, by product)
    - save
    Can anyone advise on the cause and correction of this error?
    Thanks...

    Hi,
    This error is due to missing keyfigure assignments in some aggregtes eg 9AMAPR,9AMALO,9AMALA.So make sure that
    you assigned the kefigures to aggregates correctly .
    Regards,
    Sunitha

  • Error /SAPAPO/OM102, return code 40,015 in APO DP

    I am using APO DP V5.
    In interactive DP, we are getting error /SAPAPO/OM102 with return code 40,015.
    Had anyone had experience of this?
    Thanks,
    Bob Austin, Atos Origin.

    Hello,
    As per my understanding of your qurery...
    You are accessing intractie Demand planning
    that time you are getting error.
    /SAPAPO/OM102 Return code 40015
    With the above understanding ... I am trying to reply your query as
    When I tried to execute transaction /SAPAPO/OM10 - Display Meaning of Return Code
    And entered return code 40015
    I received Display messages as "Date is before start date of time buckets profile"
    ON long text it is "Date is before start date of time buckets profile
    Message no. /SAPAPO/OM_TS015
    Diagnosis
    The date lies before the start date of the time buckets profile used.
    This problem is due to an error in the application.
    Procedure
    Open an OSS message in accordance with SAP Note 167280.
    Please check the details above.
    In Intractive demand planning what type of work you were doing during this error occured?

  • Optimization run terminated with errors  /SAPAPO/OPT012

    Hi All,
    While running the PPDS Optimizer I am getting the error "Optimization run terminated with errors  /SAPAPO/OPT012" . ..
    I had check the Connection in SM59 for the Optimizer server and it is working but still i am getting this error.
    Optimization get terminated without run.
    any pointer Please.
    Regards,
    ketan

    Dear Ketan,
    Maybe note 1097169 can be referred to. Partially fixed campaigns can lead to the failed optimization run - that this
    will somehow throw error OPT012, etc.
    BR/Tiemin

  • Internal error [/SAPAPO/LOO_TS_PAREAFG1:get_start_of_bucket]

    Hi Experts,
    We are using the process chain for time series extension, during the time series extension we used to get the error message that "Internal error [/SAPAPO/LOO_TS_PAREAFG1:get_start_of_bucket]".
    Please help out to fix the same,
    Thanks in advance,
    Regards,
    Venu

    Dear Venu,
    This error occurs if the start date for a specific key figure init. is before the overall start date which must not be.               
    Regards,
    Tibor

  • APO Planning Calendar error /SAPAPO/CAL404

    Hello friends, I am working in the transaction /sapapo/calendar trying to change a Planning Calendar and when I try to Calculate the periods in the view "Calculation Rule" i got a error message saying: Factory calendar TU not found (message number  /SAPAPO/CAL404).
    I have looked into SCAL transaction and the factory calendar is OK created and valid.
    Thank you very much in advance.
    Regards.
    Ricardo Pereira

    Hello Senthil,
    Thank you for your help!!
    In the Time Stream I have changed the field Factory Calendar for another one for testing and it worked well, I mean I could caculate the periods using another calendar. Comparing both It's all the same there is no difference beteween them.
    But when I put the one that I really have to use (the correct one) in the time stream it gives the message Calendar not found. Although it exists and appears in the match code and If I get in the SCAL in APO as well as in R/3 I can edit it.
    I have checked the calendar parameters in SCAL and also the time zone including in one of the locations that use this time stream and it's all fine.
    Do you have any other idea?
    :O(
    Thank you very much indeed.
    Regards.
    Ricardo

  • Live Cache Error -/SAPAPO/OM (242)

    Hi,
         I use the function module '/SAPAPO/DM_ARC_ORDER_CHANGE' for fixing the orders. But sometimes this function module throws an error as 'Multi-level error propagation carried out' -/SAPAPO/OM (242). When I restart my program the error is resolved. Please let me know ur thoughts about the issue.
    Thanks in advance.
    Regard,
    Siva.

    Hi
    You need to implement the appropriate SAP NOTES for your requirements. generally the error Multilevel error propagation can get solved by implementing SAP NOTES
    Suggest, pls check the SAP Notes. and implement. I'm sure you will not get this error
    regards
    Vijay

  • BDC batch interface error /SAPAPO/SCC05

    I have created an ABAP program that does a CALL TRANSACTION to transaction /SAPAPO/SCC05 (in an APO program).  If I run the program in foreground (the CALL TRANSACTION in background mode), everything works correctly.  However, when I try to run the program as a batch job, I receive an error message: "Error calling up user interface components".
    I tried changing the CALL TRANSACTION to simply create a BDC session I could run via SM35.  The BDC, when run in background mode, gives the same error, but runs fine in foreground.
    I located an OSS Note (below) that references the error message (/SAPAPO/SCC 032) (<--message class/message number).  I tried changing the settings outlined in the alternative solution in the OSS note, but the problem is still there.
    In addition, I have tried to toggle all the different parameters that one has control over in the CALL TRANSACTION (default screen-size, commit work, etc.)  No differences that I could find.
    Has anyone run into a similar issue?  I can be reached at [email protected].  Thank you.
    Here is the OSS Note:
         SAP Note No. 396020                          15.12.2005           Page 1
         Number              396020
         Version             2 from 17.04.2001
         Status              Released for Customer
         Set on              16.04.2001
         Language            EN
         Master language     DE
         Short text          Error when calling PPM maintenance, SCE or SCC
         Responsible         SAP AG
         Component           SCM-APO-OCX
                             ActiveX controls
         Long text
         Symptom
         When you call the graphical PPM maintenance or SCC/SCE, the system
         displays error message "Error calling up user interface components"
         /SAPAPO/SCC032
         Additional key words
         APO-SCC
         Cause and prerequisites
         You installed a valid APO Frontend patch correctly. When you use
         PPM/SCE/SCC now a very rare constellation can occur, a graphical user
         setting may be outside of the allowed value area. Thus, when you call
         the respective application for the specific user the system displays an
         error message of the frontend.
         Solution
         Workaround:
         If possible, create a new user ID for the respective user.
         Alternatively:
         In database table /SAPAPO/CP_USRPRfor the respective user and for the
         respective application (field APPLID) set fields 'MAP CO ********' to
         initial (value 0). Note that for changes directly in database tables you
         have to be very careful
         A solution is being developed. We will update this note as soon as
         possibly.
         Source code corrections
                                                                           Page 2
         Valid releases
         Software Component                        Release
                                                   from            to
         SAP_APPL   SAP Application
                                                   46C          - 46C
         SAP_APO    SAP Advanced Planner & Optimizer
                                                   30A          - 30A
         Further components
         SCM-APO-MD-PPM
          Production Process Model

    Hey Mike.   If it is using any enjoy controls, it is really not a good idea to do a BDC over the transaction.    You should find another way to do the transaction,  maybe there is a BAPI available or a function module.  Or, is there a transaction that does the same with out the controls.  In R/3 v46c,  there are transaction like ME21(Creat Po) that is the old version, but works the same way as the ME21N which is the enjoy transaction.
    My advise is to find another way to do the transaction besides using the tcode that you are currently using.  I know that this is not much help.  Sorry 
    Please remember to award points for helpful answers and mark your post as solved when solved completely.  Thanks in advance
    Regards,
    Rich Heilman

  • SAP CCR error /SAPAPO/CIF561

    Hi,
    We are getting the following error in CCR report. Have not found anything on OSS. Secondly after scheduling the dates are not getting updated from APO to ECC. Any help on this is appreciated.
    Operation 0050 for order 000XXXXXXXX: Differences in 'scheduled' status
    Message no. /SAPAPO/CIF561
    Diagnosis
    Operation 0050 for order 0000XXXXXXX has the following differences for the Scheduled (EIGP) status in SAP APO and SAP R/3:
    Status in SAP R/3: Deallocated
    Status in SAP APO: Scheduled
    Thanks,
    Sandeep

    Hi Sandeep,
    You need to check /SAPAPO/CP1 (Maintaining Distribution Definitions).
    You need to maintain entry for In-house production as you mentioned your production orders are not getting transferred to ECC.
    If you want to read about distribution definition you can go to SPRO> APO>Integration with SAP Components> Integration via APO Core Interface (CIF)> Basic Settings for Data Transfer> Publication> Maintain Distribution Definition
    Once you maintain this and you have CIF model active for production order then data will flow automatically to ECC and you should be able to solve your problem.
    I hope this helps.
    Thanks,
    Anupam
    Edited by: Anupam Sengar on Aug 11, 2011 12:24 AM

  • Error:conversion of PPDS order from SNP order-error /sapapo/rrp_heur45

    Hi,
    I am converting a snp planned order from ppds order in transaction /sapapo/rrp_sap2ppds and using heuristic sap_pp_002.But it is canceling the heuristic and giving above error message.I have given 60days ppds horizon and 61days snp horizon.lot size:lot-for-lot.Please suggest what to do?
    Thanks&regards
    venkadesh

    Hello ,
    The hueristics sap_pp_002 you are using is based on algorithm "planning of std. lots".
    For converting Supply Network Planning (SNP) orders or Capable-to-Match(CTM) orders into Production Planning and Detailed Scheduling (PP/DS) orders, try to  use a heuristic based on the algorithm /SAPAPO/HEU_SNP_CONVERT, such as the standard heuristic SAP_SNP_SNGL..
    I think the above mentioned hueristics should be able to solve the problem .
    Also for more information refer to below link.
    http://help.sap.com/saphelp_scm2007/helpdata/en/8a/475c3c3906b106e10000000a11402f/frameset.htm
    Thanks & Regards
    Abhijit S Nakhwa

  • PP/DS Subcontracting error "/SAPAPO/RRP327"

    Hello,
    we setup subcontracting for trading goods in APO. Now i get for some materials the following error if i run the product
    heuristic
    Order not created for product XY location AB date 05.10.2010 00:00:00 quantity 3 ST
    "Messg. No:  /SAPAPO/RRP327".
    If i try other products it works fine.

    Hello nandha,
    in the log i see only the error in my first post. No other things mention there.
    kind regards,
    Bernhard

  • Resolution of /SAPAPO/TSM207 errors in APO SNP planning

    I am using APO V5.1 connected to a SAP ECC system.
    When I CIF across a new product to APO and use it for the first time in SNP interactive planning I get error /SAPAPO/TSM207, because of missing time series objects.
    The SAP recommendation in the error help text suggests to either re initialise the planning area, or to use pgm /SAPAPO/TS_LCM_PLOB_DELTA_SYNC. But I can only resolve the problem via the former approach (ie to re initialise the planning area). The use of /SAPAPO/TS_LCM_PLOB_DELTA_SYNC does not resolve the problem.
    Is this expected behaviour?
    What exactly is /SAPAPO/TS_LCM_PLOB_DELTA_SYNC designed to do?
    If I look at help.sap.com for SCM 7 I see mention of a transaction /SAPAPO/TSINIT, which can be used as a 'delta' planning area re initialisation. But I do not see this transaction in APO V5.1 - so is this a new transaction in APO 7?
    Thanks for any advice on this...

    Hi,
    Please refer to he note 402046 which explains this.Eventhough the note validity is not for your release ,but the conent of
    note is still valid to all releases.
    Regards,
    Sunitha

Maybe you are looking for

  • Error while creating BOM with FM CSAP_MAT_BOM_MAINTAIN

    Hi All, While creating the bom with the FM "CSAP_MAT_BOM_MAINTAIN" using change number i am getting the below error message. " Processing of this object is not supported with change number." Please help me out. Regards Suresh

  • Error while displaying file " C:Temp Filename.Ext cannot be created"

    Dear Friends Some users face problem while display the file. They get message " C:\Temp\ Filename.Ext cannot be created ". I checked Details. I got explaination as follows. Caution! You are not authorized to work with temporary storage Message no. ED

  • How to permanently stop and delete a download?

    Hello, I started downloading a free movie on iTunes and I no longer want to finish the download (I don't have enough free hard drive space). I keep stopping and deleting it, but the next time I open iTunes it resumes the download. How can I stop and

  • AdvancedDatagrid Grouping question

    Getting the hang of this AdvancedDataGrid control. I think it has a lot of potential but I just cant figure out how to do one thing. As you can see from the picture I am grouping by Section and then SubSection. The problem is when there is no subsect

  • Need info on DDL and Data propagation

    Greetings Guys,      I have a requirement for moving data and DDL from lower environment to production, this would be done on some frequency say weekly for deploying the latest code for the application, I would like to know what are the possible tech