Error while doing OASV T Code in ECC 6

Can anybody help me how to fix this while doing T Code OASV.
I will assign good points.
Balance in 1 currencies
Message no. F5842
Diagnosis
Balances have been found in 1 currencies with the following details:
Currency type Amount Currency
30            0.01  USD
(A maximum of three differences are listed)
System Response
The prerequisite for posting a document in financial accounting is that the balances for all currency types are zero.
Procedure
This is a system error in the calling application or the FI/CO interface.
Thanx,
Edu

Hye
When you are using multiple currencies this error arrises. You can not transfer the values through OASV.
You have to follow the other way :
first reset the asset reconcilation account.
post the transaction through fb50 or f-02
after posting the entry re-set the reconcilation account.
The path :  Assets accounting preparing for production start upset or reset recon account.

Similar Messages

  • ''Vendor not specified'' error while accesing SXMB_IFR t-code in ECC 6.0

    Hi,
    I have installed ECC 6.0 server & i have selected PI component while installing. Installation is successfully completed. But when iam accessing the SXMB_IFR t-code it is showing the error " Vendor not specified " .
    Please can any body suggest me what to do with this error. I need to apply any patches or any content to the server?.
    Please suggest me.
    Thanks in Advance,
    Babu.

    HI Kishore
    Hope these can help you. i used the same
    https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/70c3b830-9a54-2b10-008f-b8547efc040a
    https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/20669448-9a54-2b10-89b5-ff50f6de8061
    With these for Post installation
    Logon to the NWA with administrator id and password and Click on the Deploy and Change execute the template installer please refer the following for more information
    Configuration : Go to the following:
    http://service.sap.com/instguidesNW2004s -> Installation -> Technology
    Consultant's Guide. -> Enabling Application-to-Application Processes ->
    Application-to-Application Integration -> Configuration of Usage Type
    Process Integration (PI) -> Template-Based Basic Configuration.
    You can use either the Template-Based Basic Configuration to carry
    out the configuration steps OR you can do the configuration steps
    manually:
    Please see the following link regarding this:
    http://help.sap.
    com/saphelp_nw04s/helpdata/en/61/6e8c42c398173be10000000a155106/frameset.htm
    For the central SLD, further manual steps are required.
    For more information, see SAP Note 939592.
    If you want to use an Integration Server client other than 001
    further manual steps are required. For more information, see SAP Note
    940309.
    Thanks
    Gaurav Bhargava

  • Error while doing Transaction data loading from ECC to BW

    HI,
    I faced error in data records so i corrected it manually by going PSA Maintenance. then now when i am trying to schedule data laod by going to that Data source then right click on Manage then select Request which i have updated with correct records. then Again right click-->UPDATE WITH SCHEDULER .now next screen is SCHEDULER(PSA SUBSQUENT UPDATE) here i am not getting any Data Target means data target field is disabled  so i cannot schedule it for load.
    Any solution for this error.
    Thanks
    Nilesh Pathak

    Hi,
    I guess you have not deleted the request from the InfoCube 'Manage' Screen. If the request is already updated to your InfoCube/ODS ,then it will not show the Data Target in PSA Scheduler.
    You can try to re-load the data using 'Only PSA'  in the InfoPackage and then correct the errors and load the data using Update option from the Manage screen.
    Thanks

  • Error while posting FB50 transaction code

    Hi I am getting the below error while doing FB50 transaction code. Please help me
    My company code is using EUR & country is Greece
    Company code not assigned to country or country to calculation procedure
    Message no. FF703
    Diagnosis
    An error occurred when checking the tax code. Either the assignment of company code and country or of country and calculation procedure is not correct.
    Procedure
    Check the system settings.
    To do this, choose Maintain entries (F5).
    If the program error occurred
    In a standard SAP program, then create an OSS message
    In a program you wrote yourself, then correct the program.
    Thanks
    Kishore

    Hi
    Go to OBBG -->Assign Country to Calculation Procedure and assign the Tax procedure( ie like TAXIN) to the GREECE Country.
    This helps you resolve your issue.
    Regards
    Venkat

  • Error while doing Goods receipt for process order. Error code: "BS027"

    I am getting error while doing GR for a day whereas previous day(s) GR is already done and also 2 days post that day are also done successfully.
    Error :  ""Goods receipt for prodn. order" is not allowed (ORD XX-CEMTSAL) " (XX = First two characters of plant code)
    Error code: BS027.
    Thanks to all in advance.

    Hello,
    This issue would occur when you want to post a confirmation for a production order. The error message is generated if you wanted to post a backflush for a component and if this component was assigned to a sales order stock. The sales order itself was assigned to a work breakdown structure element which should be debited with the actual costs. However, the business transaction 'Confirm' is not permitted for a work breakdown structure.
    Please look into SAP Note 62367 and 64370
    Hope the information is helpful
    regards

  • While doing cross company code postings I get an error

    Hi experts,
    I have an issue on cross company code postings through FB60. There is a vendor account which has been extended to both company codes. The amount of invoice is Rs.10000 of which 6000 to be accounted in company code 1000 and 4000 in company code 5000. When this is done we get an error 'A unique company code has not been assigned to company number A001'.
    After trying several options, I have found one solution. In the test system I Went to classify FI  document types for document splitting, against document type KR transaction 0300 (Vendor invoice) was there. I changed to 0000 (unspecified posting). Once this was done, I was able to post cross company transactions without any problem.
    I would like to know as to what would be the impact? Would this change create any other issue?
    I request you to give your expert opinion on this.
    Regards,
    Ramkumar B.
    Duplicate thread, therefore it will be locked, please avoid creating different threads for the same subject.
    check the responses in thread While doing cross company code postings I get an error
    FI Moderator

    Dear,
    When you are posting vendor Invoice through FB60 then system creates accounting document "KR" and when document splitting is activated in system the you have to assign Doc type KR to Transaction 0300 and 0001.
    This is standard requirement. There will not be any changes by doing this.
    Hope it is clear..
    Br,Vivek

  • Getting Error while doing Control Panel - Windows Update Error code is 80070103

    Getting Error while doing Control Panel -> Windows Update Error code is 80070103. The optional Windows 7 update is
    Microsoft - Other hardware - WinUsb Device
    Please provide your email ID to send the Error screen shot.

    Hi!
    Check the following link to see if it solves your problem:
    http://support.microsoft.com/kb/952032
    Best regards
    Andreas Molin
    Andreas Molin | Site: www.guidestomicrosoft.com | Twitter: andreas_molin

  • Error while doing f111

    Dear Experts,
    I am getting below error while doing f111.
    Company codes 1100/1100 do not appear in proposal 29.05.2011 00008R; correctMessage no. FZ003
    In the LogNo check can be made in SAP GTS in an automatic payment processMessage no. FIPAY_GTS001Run is continued. System writes entries for subsequent checkMessage no. FIPAY_GTS006?
    Is there something related with GTS i am doing testing in Ides.
    Thanks in Adv.
    SN.NOORIE

    Yes, this is related to SAP GTS. I think you have GTS (Compliance screening) activated for your FI payment through ECC or R/3.
    Check these two note for further information and touch base with your GTS consultants.
    1. Note 850365
    2. Note 1027403
    From your error message, it seems the organizational setup is not proper.
    Cheers,
    Abir

  • Error while doing EHP4 upgrade in downtime phase

    HI .
    Iam facing the below error while doing the EHP4 upgrade , in downtime phase.
    Checks after phase MAIN_SWITCH/STARTSAP_TRANS were negative!
    Last error code set: RFC call to subst_get_uvers failed with key RFC_ERROR_COMMUNICATION (open): SAP_CMINIT3 : rc=20 >
    Connect to SAP gateway failed Connect_PM GWHOST=Hydhtc4526D, GWSERV=sapgw04, SYSNR=04  LOCATION CPIC (TCP/IP) on local host with Unicode ERROR partner '10.136.162.30:3304' not reached TIME Mon Jun 06 18:17:46 2011 RELEASE 720 COMPONENT NI (network interface) VERSION 40 RC -10 MODULE nixxi.cpp LINE 3286 DETAIL NiPConnect2: 10.136.162.30:3304 SYSTEM CALL connect ERRNO 10061 ERRNO TEXT WSAECONNREFUSED: Connection refused COUNTER System start failed
    Please help me in resolving this error.
    Sanketh.

    Hi,
    Upgrade tool is trying to start the system but system is not coming up. Try to start system manually and see if system comes up or not. If not then check logs in work directory for why system is not coming up.
    Thanks
    Sunny

  • Error while doing  GR for scheduling aggrement

    Dear Experts,
    We are facing error while doing GR for scheduling aggrement.
    we have done the following steps.
    1) Scheduling aggreement in ME31L
    2) Released in ME35L
    3) Mainatined Sch.Agmt Schdule in ME38 for todays and date 200 qty and other line is 800 qty.
    When we are trying to do GR in MIGO system is giving the following message.
    Document 5500000152 does not contain any selectable items
    can I know what I have missed in the above steps.
    Please guide me to resolve this.
    Regards,
    Prasad

    Hi,
    Please check Please check if Gr is already done against this document.  Also please check whether you have attached SA in the source list with line items.
    T-code:ME01
    Enter Mat.code & Plant.
    In the next screen pl.do the following:
    Valid from - commencement date of the SA
    Valid to - End date of the SA
    Vendor - Vendor on whom the SA is released
    POrg - Your purchase organisation
    PPL - Leave it blank(This is only for interplant)
    OUn - Ordering unit
    Agreement - SA number
    Item - 1
    I hope this will resolve your issue. Thanking you

  • Error while doing F-90 Asset Acquisation

    Hi,
    I am getting the below error while doing F-90 Asset Acquisation scenario. Please help me to fix this issue.
    Tax code V1 country IN does not exist in procedure TAXINN
    Message no. FF713
    Diagnosis
    You entered a tax code which is not defined for the country of the company code to be posted to in the tax calculation procedure.
    System Response
    Procedure
    Check and, if necessary, correct the entry.
    Procedure for System Administration
    If it is not an input error, check and possibly change the system settings.
    To do this, choose Maintain entries (F5).
    Check whether the company code is assigned to the correct country and whether the correct tax calculation procedure has been entered for the company code country.
    Create a new tax code if necessary.
    Caution:
    Since it is possible that the tables in question are being updated at a different time on another computer, it can take a certain amount of time for the tax code to be on all local machines in client server architectures after saving the new code.
    Thanks
    KB

    Hi,
    you need to maintain Tax Code A0 & V0 in t.code OBCL t.code.
    and also ensure to check whether you have created tax code V1 or not in FTXP t.code. If not, create V1 tax code and assign GL on that in the right Transaction event keys in OB40.
    Try.... if not working let me know....
    Regards,
    MOhan.

  • Error while doing File to File Scenario

    All,
    I am trying a simple file to file scenario - where xi picks up the file from a location and maps the message and dumps it in another location.
    I am Getting the below error while doing the same .........
    Time Stamp Status Description
    2009-03-30 14:30:24 Success Channel Test_send_cc: Send binary file  "d:\input\input.xml". Size 203 with QoS EO
    2009-03-30 14:30:24 Success Application attempting to send an XI message asynchronously using connection AFW.
    2009-03-30 14:30:24 Success Trying to put the message into the send queue.
    2009-03-30 14:30:24 Success Message successfully put into the queue.
    2009-03-30 14:30:24 Success The application sent the message asynchronously using connection AFW. Returning to application.
    2009-03-30 14:30:24 Error Attempt to delete file "d:\input\input.xml" after processing failed. Retry
    2009-03-30 14:30:24 Success The message was successfully retrieved from the send queue.
    2009-03-30 14:30:24 Success The message status set to DLNG.
    *+2009-03-30 14:30:24 Error Transmitting the message to endpoint http://filip:8000/sap/xi/engine?type=entry using connection AFW failed, due to: com.sap.aii.af.ra.ms.api.RecoverableException: Received HTTP response code 401 : Unauthorized.*
    2009-03-30 14:30:24 Success The asynchronous message was successfully scheduled to be delivered at Mon Mar 30 14:35:24 GMT+05:30 2009.
    And i cant see the meesages using the SXMB_MONI trasaction
    please help me resolve ths issue
    Regards,
    Mahesh.
    Edited by: mahesh uma on May 3, 2008 2:12 PM

    Hi Uma,
    Go through this links::
    Hope these links are useful to you..
    Urgent: Message not transmitted from AFW to Integration server
    Error with huge file
    File to JDBC error
    Thanks,
    Satya Kumar..

  • Error while doing MIRO

    Hello Everybody,
    I am trying to do MIRO for a Purchase Order.
    But I see the following error while doing that -
    "G/L account  is not defined in chart of accounts 1000".
    Can someone tell me whats going wrong and where do I have to check to set the following conditions right for a MIRO posting to be done?
    Please help. All the help is appreciated.
    Thanks,
    Sneha.

    Hello Sneha singh
    In addition to Mr.srinath's suggestions please check whether you have maintained Reconsallation account for your vendor in the Vendor masterdata in XK01 in the company code level
    have you maintained properly the OBYC settings (take the help of your MM or FI consultant for this) and also check in OMWD whether the valuation grouping 0001 code is assigned to your plant
    Mostly along with Mr.Srinath's suggestions  Reconsallation account checkings in the Vendor masterdata in XK01 should solve your issue
    Regards
    Raja

  • Error while doing PGI for Outbound delivery using BAPI BAPI_GOODSMVT_CREATE

    Hi All,
    I am getting an below error while doing PGI for outbound delivery using the BAPI BAPI BAPI_GOODSMVT_CREATE:
    Goods movement not possible with mvmt type 601
    Can anyone suggest me what will be the solution for it?
    Regards,
    Raghuraman.k

    I tried with the above BAPI but it is not working.
    In my case a delivery has one line item with batch split and other line item without batch split.
    Below is my code :
    DATA : gwa_header_data TYPE bapiobdlvhdrcon,
           gwa_header_ctrl TYPE bapiobdlvhdrctrlcon,
           lv_delivery     TYPE bapiobdlvhdrcon-deliv_numb,
           git_item_data TYPE STANDARD TABLE OF bapiobdlvitemcon,
           gwa_item_data TYPE bapiobdlvitemcon,
           git_item_ctrl TYPE STANDARD TABLE OF bapiobdlvitemctrlcon,
           gwa_item_ctrl TYPE bapiobdlvitemctrlcon,
           git_return    TYPE STANDARD TABLE OF bapiret2,
           gwa_return    TYPE bapiret2.
    *Header data
    gwa_header_data-deliv_numb = '0808000002'.
    *Header Control data
    gwa_header_ctrl-deliv_numb = '0808000002'.
    gwa_header_ctrl-post_gi_flg = 'X'.
    *Delivery Number
    lv_delivery = '0808000002'.
    *Item data and its corresponding control data
    gwa_item_data-deliv_numb      = '0808000002'.
    gwa_item_data-deliv_item      = '900002'.
    gwa_item_data-dlv_qty         = 4.
    gwa_item_data-dlv_qty_imunit  = 4.
    gwa_item_data-fact_unit_nom   = 1.
    gwa_item_data-fact_unit_denom = 1.
    APPEND gwa_item_data TO git_item_data.
    gwa_item_ctrl-deliv_numb      = '0808000002'.
    gwa_item_ctrl-deliv_item      = '900002'.
    gwa_item_ctrl-chg_delqty      = 'X'.
    APPEND gwa_item_ctrl TO git_item_ctrl.
    gwa_item_data-deliv_numb      = '0808000002'.
    gwa_item_data-deliv_item      = '900003'.
    gwa_item_data-dlv_qty         = 6.
    gwa_item_data-dlv_qty_imunit  = 6.
    gwa_item_data-fact_unit_nom   = 1.
    gwa_item_data-fact_unit_denom = 1.
    APPEND gwa_item_data TO git_item_data.
    gwa_item_ctrl-deliv_numb      = '0808000002'.
    gwa_item_ctrl-deliv_item      = '900003'.
    gwa_item_ctrl-chg_delqty      = 'X'.
    APPEND gwa_item_ctrl TO git_item_ctrl.
    gwa_item_data-deliv_numb      = '0808000002'.
    gwa_item_data-deliv_item      = '000020'.
    gwa_item_data-dlv_qty         = 10.
    gwa_item_data-dlv_qty_imunit  = 10.
    gwa_item_data-fact_unit_nom   = 1.
    gwa_item_data-fact_unit_denom = 1.
    APPEND gwa_item_data TO git_item_data.
    gwa_item_ctrl-deliv_numb      = '0808000002'.
    gwa_item_ctrl-deliv_item      = '000020'.
    gwa_item_ctrl-chg_delqty      = 'X'.
    APPEND gwa_item_ctrl TO git_item_ctrl.
    BREAK-POINT.
    CALL FUNCTION 'BAPI_OUTB_DELIVERY_CONFIRM_DEC'
      EXPORTING
        header_data    = gwa_header_data
        header_control = gwa_header_ctrl
        delivery       = lv_delivery
      TABLES
        item_data      = git_item_data
        item_control   = git_item_ctrl
        return         = git_return.
    BREAK-POINT.
    IF git_return IS INITIAL.
      CALL FUNCTION 'BAPI_TRANSACTION_COMMIT'.
    ENDIF.

  • Error while doing file to mail scenario

    Hai All,
              I am getting the following errors while doing the file to mail scenario.
    Error:Exception caught by adapter framework: Failed to call the endpoint
    Error:Delivery of the message to the application using connection AFW failed, due to: Failed to call the endpoint.
    Can anyone please give me solution...

    Try this:
    Re: "Could not determine code page" inbound side error
    and this
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/d19fe210-0d01-0010-4094-a6fba344e098
    https://www.sdn.sap.com/irj/servlet/prt/portal/prtroot/docs/library/uuid/cdded790-0201-0010-6db8-beb9bb2b2660

Maybe you are looking for

  • How to display document last modfied date time in core result web part?

    Hi, We have a requirment in the sharepoint application where we need to display last modified date&time of document in core result web part. To support this we have specify the property <Column Name="Write"/> in custom XSL. But it displays only the m

  • Messages are in HOLD state

    Hello ALL, We have all messages processed sucessfully in Monitor but in "HOLD" state in the Audit log...EO is the QOS...Not sure why the messages are in HOLD state..There are atleast 15 receivers for this interface..ANy ideas guys.. -Teresa

  • Avi videos in elements 10

    How to make avi videos in elements 10?

  • Help please on advanced MySQL...

    Dear all: Sorry for posting some MySQL-related topics here, which neverthess is a portion of a Java intensive project =) I tried to ask for some help on MySQL forum but it seems here would be more gurus on MySQL!! Basically I need to do some manipula

  • Dreamweaver CS4 Installation Fails after 95% installed + mcschield.exe

    Hello, I would like to know if we need to stop Mcafee real time scanner during Dreamweaver CS4 installation. And also I am installing English version of Dreamweaver in my German Vista home premium.Will there be any possible problem for this? Please h