EtherChannel configuration between Copper interface and fiber Interface

Hi,
Need to check if Giga Etherchannel can be configured between Copper 10/100/1000BaseT and SFP 1000BaseT between two blades on a Cat 6506 with either Sup 720 or Sup32.

I have configured etherchannel between two 3560G 48 port switches. Using a combination of 2 sx fiber and 2 1000tx copper interfaces. The resulting layer 2 channel supported upto 4gb. The notes from the cisco site indicate the following:
Configure all LAN ports in an EtherChannel to operate at the same speed and in the same duplex mode.
The following link refers to etherchannel for 6500 series switches:
http://www.cisco.com/en/US/customer/products/hw/switches/ps708/products_configuration_guide_chapter09186a008007e6d3.html
This link refers to etherchannel for the 3560 series:
http://www.cisco.com/en/US/customer/products/hw/switches/ps5023/products_configuration_guide_chapter09186a00801cdea1.html

Similar Messages

  • Configuration between SAP PI and BPM in SAP PO

    Dear Experts,
    I am working on SAP PO 7.31 and want to carry out configuration between SAP PI and BPM in SAP PO. I carried the post installation
    activities in NWA i.e. CTC.
    Helplessly , I could not find any documents and notes to refer the configurations.
    Regards
    Rebecca

    AAEx configuration:
    Advanced Adapter Engine Extended (AEX) - Installation and Configuration - III
    Configuring SAP BPM and PI runtime:
    Configuring Message Processing from PI to BPM - Process Orchestration - SAP Library
    Sample BPM
    NetWeaver BPM for System-to-System Message Orchestration (Including Migration of ccBPM to NW BPM)
    Hope this helps

  • Etherchannel issue between 3750 stack and WS-CBS3012 for IBM blade centre

    Hi,
    We are trying to configure Etherchannel between four ports of cisco 3750 stack(2ports from one switch of stack and two ports from another switch of same stack). We are facing issues with this setup. The ports in WS-CBS3012 are going to err disable mode.
    Is  there any limitations associated with such a cross-stack etherchannel configuration. Please suggest if there is any particular sequence of configuration involved.
    Switch1 in stack
    int gi 3/0/3
    switchport mo trunk
    switchport trunk allowed vlan 10-30
    sw tr en dot1q
    channel-group 1 mode on
    spanning-tree guard root
    switch 2 in stack
    int gi 3/0/3
    switchport mode trunk
    switchport trunk allowed vlan 10-30
    sw tr en dot1q
    channel-group 1 mode on
    spanning-tree guard root
    int port-channel 1
    switchport mode trunk
    switchport trunk allowed vlan 10-30
    sw tr en dot1q
    channel-group 1 mode on
    spanning-tree guard root
    in WS-CBS3012 ports are configured with trunk,allowed vlan and etherchannel configuration with mode on.
    With Regards,
    Madhan kumar G

    Hi,
    The commnad "no spanning-tree etherchannel guard misconfig" on WS-CBS3012 resolved the issue.
    Regards,
    Madhan kumar G

  • Stream Configuration between different 11gr1 and 11gr2

    I have oracle downstream set-up between two DBs both are 11gr1, i want to upgrade my my target DB to 11gr2. I want to ask whether my streams set-up would work after this or not.
    OR
    Is it possible have streaming between two version of oracle.
    I shall be V thankful for you guidance.

    Hi,
    Yes it possible to have streams configured between 2 different versions.
    Anand

  • Etherchannel suspended between Catalyst 4948 and VSS 6506E

    Hello,
    I describe an issue when i need to performe an L2 or L3 Etherchannel from a Catalyst 4948 IOS Enterprise and 2 xCatalyst 6506E bandled with VSS.
    From the VSS Side when i plug cables i see on the physicals and Etherchannel that Physical and protocole layer are up. On the 4948 side,
    I see that physical layer is up and protocol and Etherchannel interfaces are down.
    On the Etherchannel port summary i see that the port state is supended.
    On the first attempt, i have test with a L3 etherchannel on both side using no switchport with two IP addresses one at each side on etherchannel interfaces.
    The etherchannel are bundled with LACP mode active and on the second attempt with PAGP mode ON.
    The same configured on VSS 6506E work fine with Catalyst 3560E.
    Please do you have any idea?

    Hi David, when ı type "no mls qos channel-consistency" under port-channel
    the issue was solved. But ı am not comfortable with that, Because ı want to use Qos feature
    here the "show module all"
    GedizCore#show module switch all 
     Switch Number:     1   Role:  Virtual Switch Standby
    Mod Ports Card Type                              Model              Serial No.
      1   48  CEF720 48 port 10/100/1000mb Ethernet  WS-X6748-GE-TX     SAL10478XGB
      4   16  CEF720 16 port 10GE                    WS-X6716-10GE      SAL17204RU1
      5    5  Supervisor Engine 720 10GE (Hot)       VS-S720-10G        SAL1833YQER
      8   16  CEF720 16 port 10GE                    WS-X6716-10GE      SAL16010BSU
    Mod MAC addresses                       Hw    Fw           Sw           Status
      1  001a.2f08.6930 to 001a.2f08.695f   2.11  12.2(18r)S1  15.1(1)SY1   Ok
      4  4c4e.3591.2378 to 4c4e.3591.2387   2.0   12.2(18r)S1  15.1(1)SY1   Ok
      5  bc16.655b.a27c to bc16.655b.a283   4.3   8.5(4)       15.1(1)SY1   Ok
      8  7081.055f.91c0 to 7081.055f.91cf   1.2   12.2(18r)S1  15.1(1)SY1   Ok
    Mod  Sub-Module                  Model              Serial       Hw     Status 
      1  Centralized Forwarding Card WS-F6700-CFC       SAL10478RZ7  2.1    Ok
      4  Distributed Forwarding Card WS-F6700-DFC3C     SAL172052B2  1.6    Ok
      5  Policy Feature Card 3       VS-F6K-PFC3C       SAL1834Z3M7  1.3    Ok
      5  MSFC3 Daughterboard         VS-F6K-MSFC3       SAL1827VVKQ  5.2    Ok
      8  Distributed Forwarding Card WS-F6700-DFC3C     SAL160315JW  1.6    Ok
    Mod  Online Diag Status 
      1  Pass
      4  Pass
      5  Pass
      8  Pass
     Switch Number:     2   Role:   Virtual Switch Active
    Mod Ports Card Type                              Model              Serial No.
      2   48  CEF720 48 port 10/100/1000mb Ethernet  WS-X6748-GE-TX     SAL1442WG3X
      3   16  CEF720 16 port 10GE                    WS-X6716-10GE      SAL1441WAPL
      5    5  Supervisor Engine 720 10GE (Active)    VS-S720-10G        SAL1441VWRG
    Mod MAC addresses                       Hw    Fw           Sw           Status
      2  1cdf.0f90.89e8 to 1cdf.0f90.8a17   3.4   12.2(18r)S1  15.1(1)SY1   Ok
      3  f866.f220.3258 to f866.f220.3267   1.0   12.2(18r)S1  15.1(1)SY1   Ok
      5  c47d.4ffe.40b0 to c47d.4ffe.40b7   3.2   8.5(4)       15.1(1)SY1   Ok
    Mod  Sub-Module                  Model              Serial       Hw     Status 
      2  Distributed Forwarding Card WS-F6700-DFC3C     SAL1442WFR0  1.4    Ok
      3  Distributed Forwarding Card WS-F6700-DFC3C     SAL1441W1B8  1.4    Ok
      5  Policy Feature Card 3       VS-F6K-PFC3C       SAL1440VPD4  1.1    Ok
      5  MSFC3 Daughterboard         VS-F6K-MSFC3       SAL1441VWZG  5.1    Ok
    Mod  Online Diag Status 
      2  Pass
      3  Pass
      5  Pass

  • What are the network restrictions for a Tuxedo MP configuration between the Master and Backup?  Can they be on separate networks?

    We are migrating from one data center to another and want to keep 100% uptime during the process.  The two data centers are on separate networks but in the same city.  I want to migrate the Master and the Backup to the new data center with zero downtime. 

    Hi Harvey,
    Tuxedo machines just need TCP/IP connectivity.  So machines can be in different subnets, different Ethernets, etc.  I know of one customer that has a 13 machine MP configuration that is distributed across the entire country.  So as long as there is a route between the machines, you should be fine.  Here's an old but probably useful white paper on bridges, multiple networks, etc., from Aurora Information Systems:  "Exploring High Availability Issues with BEA Tuxedo and Third Party High Availability Software".  While it's a pretty old white paper, from what I can see most of it is still applicable.
    Regards,
    Todd Little
    Oracle Tuxedo Chief Architect
    PS  You should write some articles about what you've been up to and how you've accomplished it!

  • Cross switch etherchannel config between two 6500 and 3750

    Dear All,
    I would like to design the network and got some problem, my network have one 3750 and two 6500, I would like to setup the etherchannel from 3750 (total two uplink port together), one link to the first 6500 and the other link to second 6500, one trunk between 6500 for redundance.
    I tried to use PAgP (auto/desirable, on/on), but the channel misconfig error occurred, the etherchannel keep in suspected or standalone state.
    Anybody can suggest/recommend some method for this case.
    Thanks

    Unfortunately, you cannot create an etherchannel from one device to two different devices. for example, from 3750 you have gig 1/0/1 and gig 1/0/2. gig 1/0/1 of 3750 connects to port 1/1 of switch A and gig 1/0/2 of that same 3750 connects to port 1/2 of switch B. You can NOT create an etherchannel on 3750 to combine gig 1/0/1 and gig 1/0/2 to create a bigger pipe. That is not how etherchannel is designed to do.
    However, if you have gig 1/0/1 and gig 1/0/2 on 3750 connecting to port 1/1 and 1/2 of switch A, you can create a channel on bith devices to create a bigger pipe (4 GBPS @ full duplex) and let's say that on that same 3750, you have an additional gig 1/0/3 and gig 1/0/4 that connects to ports 1/1 and 1/2 of switch B, you can create another separate channel that combines gig 1/0/3 and gig 1/0/4 and switch B's port 1/1 and 1/2, this scenarion is totally acceptable.
    I hope that helps clear up channeling.
    In your described scenario, channeling is not what you are asking, it's STP and you really do not need to do anything as STP is enabled by default, maybe you just need to make sure that the root is where you wnat it to be and that is configureable. With your looped physical topology, STP will prevent loop from forming and will give you the redundancy you seek as when one link fails, the ones blocked by STP would go forwarding once STP detects that it should forward that port.
    Please rate helpful posts.

  • SSL Configuration between Web Dispatcher and Portal

    Here is the scenario:
    INTERNET -
    https--> WEB DISPATCHER (decryipts)-https> PORTAL
    When a request for portal page is sent to WEB DISPATCHER, it gives the following error in dev_webdisp:
    [Thr 1087416640] ERROR in ssl3_get_server_certificate: (9/0x0009) the verification of the server's certificate chain failed
    ERROR in af_verify_Certificates: (12851/0x3233) Verification of one certificate of path failed because the CA flag of its basic constraints is set to FALSE
    ERROR in check_basicConstraints: (12851/0x3233) Verification of one certificate of path failed because the CA flag of its basic constraints is set to FALSE
    I am using SAP's test certificates and there is no documentation for the error as far as I know.
    Any ideas ?

    Hi Cristiano,
    I solved the problem.
    This error message is being caused by the mismatch between the issuer (SAP Test) and server pse generation strings (for example O and OU values ).
    As the documentation suggests:
    "For example, if you use the SAP CA, the naming convention is CN=<host_name>, OU=I<installation_number>-<company_name>, OU=SAP Web AS, O=SAP Trust Community, C=DE."
    Thanks for the reply,
    Best Wishes
    Edited by: Yuksel Guney Hanedan on Aug 6, 2010 4:35 PM

  • May I know the wiring configuration between DAQCard-AI-16E and scb-68

    We have the 'DAQCard-AI-16E-4' with PSHR 68 68 cable and a scb-68 connector block to connect the signals to this daq card. and also NI-DAQ software.
    May I know the wiring configuration between DAQCard-AI-16E and scb-68.
    Kindly provide me detail wiring configuration between that two. and also application note if any for perticular this card with Laptop connection.
    Thanking You,
    Rajesh Patel,
    Research Scholar
    IIT Roorkee (INDIA)

    Hello,
    Please find attached a file in the bmp format that gives the pin-out diagram for the PSHR68-68M cable (PSHR68-68 is a shielded cable kit that contains a PSHR68-68M cable).
    You can also get the same pin-out diagram from National Instruments website if you go to the following link and type '2XIH98R9' in the search box.
    http://search.ni.com/?layout=KB
    Here's the webpage for PSHR68-68 and you can find more information about it here in the Product Data Sheet.
    http://sine.ni.com/apps/we/nioc.vp?lang=US&cid=11808
    This DAQCard has 16 AI channels, 8 DIO lines and 2 counters. These can be located in the diagram for the PCMCIA end (DAQCard-AI-16E-4) as well as the SCB-68 connector end, alongwith GND lines.
    I hope this answe
    rs your question. Please let us know if you have further questions. Thank you for choosing National Instruments !
    Swapnil P.
    National Instruments Engineer
    Attachments:
    PSHR68-68M.BMP ‏825 KB

  • Could I configure local switching between sub-interface and global interface on ASR9k?

    Could I configure local switching between sub-interface and global interface on ASR9k?

    For 2 interfaces it is probably best to use an xconnect. It is faster and saves system resources (eg mac learning doesnt apply to xconnect).
    Config example:
    l2vpn
     xconnect group link
      p2p link
       interface Bundle-Ether100.4321
       interface Bundle-Ether500.4321
    EFP config:
    interface Bundle-Ether100.4321 l2transport
     encapsulation dot1q 4000
     rewrite ingress tag pop 1 symmetric
    interface Bundle-Ether500.4321 l2transport
     encapsulation dot1q 2000
     rewrite ingress tag pop 1 symmetric
    This example shows that you can link 2 EFP's with different vlan's together if you'd pop the tags.
    If the EFP's are of the same vlan, then popping the tag can be done but not a must. In general it is recommended to always pop vlan tags so there is a standard EFP design, but not for any technical reasons.
    When you use a bridge domain and using a BVI, you MUST pop the tags as the BVI has no notion of a vlan tag and wants to see "plain ethernet".
    regards
    xander

  • How to configure one dsl connection and one public ip in cisco router and map to one interface for using exchange server

    how to configure one dsl connection and one public ip in cisco router and map to one interface for using exchange server

    Hi ,
     Have you got any additional public IP Address from your service provider , If yes on router you can have static route for those additional IP Address pointing to your ASA  outside interface . 
    Accordingly you can configure NAT 
    HTH
    Sandy . 

  • Whats the difference between an INTERFACE and a CLASS?

    Whats the difference between an INTERFACE and a CLASS?
    Please help.
    Thanx.

    http://search.java.sun.com/search/java/index.jsp?col=javaforums&qp=%2Bforum%3A31&qt=Difference+between+interface+and+class

  • Difference between abstract interface and normal interface

    Hello Friends,
    What is the Difference between abstract interface and normal interface?....

    What is the Difference between abstract interface and
    normal interface?....The difference is that you didn't follow convention in the first case. All interfaces are implicitly abstract so you don't have to declare them as such.

  • Differences between Convensional interfaces and XI interfaces

    Differences between Convensional interfaces and XI interfaces

    hi,
    wat do u mean my "Convensional interfaces"?
    let me know.
    kvr

  • ISA-95/B2MML centric interface between Oracle ERP and MES

    Hi :
    A customer wants to know if we have any ISA-95/B2MML centric interface between Oracle ERP and Microsoft Exchange Server. Specifically, they are interested in learning about compliance to OPC UA standards in such integration.
    Please reply if anybody has any information. Your help will be greatly appreciated!
    Thanks and Best Regards,
    Harris

    Hello,
    I guess this is not the right forum to address this query. Please post this question in some E-Business Suite related forum..
    Let me know.
    Rgds,Ramesh

Maybe you are looking for

  • Find open and close smart quotes

    Dear scripter, Here I am trying find whether all the open double smart quotes(") are closed with close double smart quotes("). Here is my small work to find how many open and close quotes. myopenqu=app.activeDocument.search("^{", false, false, "^{");

  • I have a new iMac - how do file share my music and photos from my old mac to my new mac?

    I want to transfer my music and photos from one Mac to another - but I don't want to transfer anything else - what is the best way to do this? Thanks

  • Ucm: displaying some fields on a profile based on a workflow step

    Hi, Is it possible to hide/display some standard/custom metadata fields on a profile based on a workflow step/ e.g. I am having a workflow with 3 steps 1. manager step 2. specialist step 3. reviewer step On the 3 step, a reviewer can decide calling a

  • Pass parameter in EPCM.doNavigate

    Hello! I have JSPDynpage the button, that have OnClientClick: addPosButton.setOnClientClick("EPCM.doNavigate('ROLES://portal_content/Webdynpro/java_local_add_lot_position_jwd_nrj_applications_AddLotPositionApplication', 1, 'width=400,height=500');");

  • Concurenncy - synchronization problems

    Hello, I have read about synchronization in about 5 sources so far and I still don't understand it and mostly because of codes that sources show do not work as they are intended to work. For example I will show the code from this webpage: http://www.