EWA thethe session is shown in status "Data is available"

Hi,
In the EarlyWatch Alert Operations screen the session is shown in status "Data is available" (icon with two small bottles) with the description The service is ready to process session data.
Background job 'SM:EXEC SERVICES' is finished successfully. Few systems EWA report is generated and *for few systems the EWA is not generated and the status is The service is ready to process session data*
ISSUE : Few systems  the session is shown in status "Data is available" (icon with two small bottles) with the description The service is ready to process session data.
As an alternative running the session manually from DSA.
Request you to help me to resolve this issue.
Regards
Reddy

Hi Reddy,
What ST-SER patch level you are?
For the background job sm:exec services, it should be scheduled via
the transaction
solman_setup->Basic configuration->Automatic Configuration
->Schedule background jobs
of course you can also manually schedule it. This job generally runs
daily at 00:30:00.
Also check:
Following notes provide also details about the EWA functionality and
troubleshooting.
976054 - Availability of EWA for Non ABAP components
1332428 - Missing data in service sessions from BI/CCDB
Thanks
Regards,
Vikram

Similar Messages

  • Unable to process EWA service session  for portal instances

    Hi Guru,
    I am in process of generating EWA reports for portal ,below are the steps I have completed successfully.
    1. SMD agent installation on portal.
    2. Defined portal system in SMSY.
    3. completed SOLMAN_SETUP.
    4. Completed Setup Wizard for managed system.
    5. Deploy IS agent via SDM in Solman.
    6. Introscope agent setup done for managed system
    7. Managed system data is visible in IS Enterprise Manager.
    I have created EWA service session for portal but I am unable to process the service session in DSWP ,I have ran SM:EXEC SERVICES  job but still I am unable to process the session data.
    System Configuratoi: SAP EHP 1 for SAP Solution Manager 7.0 and portal is netweaver 7.0
    Thanks
    Abullais

    Hi,
    I have exactly the same problem as this and have performed all the checks as specified but still my Java only NW 7 system shows "Dates for this session are overdue".
    My Solman system is Ehp1 SPS 20 and all the managed system setup using the wizard has completed successfully. In Root Cause analysis I can see the data that the extractors have gathered on the J2EE system and in Enterprise Manager I can see the Introscope data also.
    The only thing I can think of that may be affecting the EWA session is that after I added the system into the logical component that is part of the Production solution landscape the scheduled EWA session that then appeared for the J2EE system in the list of sessions had a date set for the next scheduled EWA run (29th March). To test the EWA report for my J2EE only system I used the "change date" option after clicking on the J2EE session and set it to 25th March (this changed on 24th March). The session date then reflected the EWA session for the J2EE only system woul run on the 25th.
    Checking the session this morning I have the red flag with "Dates for this session are overdue" status.
    The sessions for the ABAP based systems are working fine, it's only this one system that is J2EE only that I have a problem with.
    Any pointers ?
    Regards,
    Brian.

  • Read Printer Status Data

    Dear All;
    I want to read the printer status data which are shown in the printer built in display (ink level, cartridge status, job status) in my PC. Can anyone help me how to do that? Is there any built in function or code that can access the printer control data?
    I need to implement this for both offline and network printer.
    Regards
    Arefin

    Hi,
    Congo,That issue resolved by following process-
    In solution manager use "MAI_TOOLS" transaction then "Acitvate expert mode" and select "Analysis" Tab.Under this tab there is one option "Check Directory consistency".By selecting this option then I entered "Technical scenario" T_SYS_MON and "Managed object name" as my managed object for which data was not reporting,then execute it.
    There I found missing entry point configuration for my managed object.When I select reconfigure entry point then after few minutes data started to reporting.
    But for the same metric data is reporting randomly. For few hours data comes and then again it becomes grey for few hours.I am observing this from last 30 hours.
    Kindly suggest for this situation.
    Regards,
    Piyush Jain

  • I recently purchased an Iphone 6plus and I am receiving pdf attachments that are shown as winmail.dat attachments on the phone. When I check e-mail via  my macbook pro the attachment is a pdf and I can open it. Why is this happening?

    I recently purchased an Iphone 6plus and I am receiving pdf attachments that are shown as winmail.dat attachments on the iphone. When I check the same e-mail on my macbook pro the attachment is a pdf and I can open it. Why is this happening?

    I had this problem too after i upgdatd to OS X Mavericks... only the songs on my iphone 5s that i purchased from itunes would play.
    i read something about it being a syncing issue. when you plug your phone into your computer with the usb cable, the person said to switch from automatic syncing of itunes to the "manual" option. mine was already set to manual so i wasn't sure anything would work. BUT, when i plugged my phone into my computer, it started to sync all of my music on my phone again (top of itunes bar where song playing/time is listed said "now syncing 123/534 songs to x's iphone"). once that was completed, i checked the music app on my iphone and everything was back to normal!
    so, i would suggest setting your music syncing settings to manual if you haven't tried that yet!
    hope this helps!

  • Today at 8am est my card was charged but when checking order status it saids expected ship date not available at this time and  it also saids we received your order and it is in process . payment not taken yet

    today at 8am est my card was charged but when checking order status it saids expected ship date not available at this time and  it also saids we received your order and it is in process . payment not taken yet 
    but card was charged full amount and i havent gotten anything else been checking for update all day and got nothing i did order iphone 6 plus at 3:01am and everything went through and i was finsihed at 3:06am

        chriss2633,
    I know how exciting it is to have all the information on the new phone. I did send you a Direct Message. Can you please respond back to that message? Looking forward to hearing back from you.
    KevinR_VZW
    Follow us on Twitter @VZWSupport

  • User status Date and  time

    Hi EXPERTS,
    In notification when we change user status, system logs date and time in action log
    I want to know in which table does user status date and time can be found.
    Regards
    Anil Kumar

    Anil Kumar,
    I'm not a t a system right now, but have a look at JEST and JCDS.
    PeteA

  • Query referencing session state not consistently returning data

    Hi,
    I have a form that summarizes expense data by category for employees, per fiscal year, fiscal period, and project.
    Clicking on a button next to a particular category takes the user to a new page that should display the detail of those expenses, based on expense_code.
    The expense_code is passed via URL to the second page, and the query region for the detail has the following source:
    select exp_code, JRNL_ID_NO, DESCRIPTION, REFERENCE, CUR_PER_TRAN, CUM_YTD
    from fgspec_ac where exp_code between :P118_EXPENSE_CODE_FROM and :P118_EXPENSE_CODE_TO and project=:P114_PROJECT and fis_year=:P114_FIS_YEAR and fis_period=:P114_FIS_PERIOD
    :P118_EXPENSE_CODE_FROM and :P118_EXPENSE_CODE_TO are passed via URL, and the :P114_% fields reference data on the initial form.
    The problem is that when I click on the button to bring up the detail for the first time, the query returns no rows. If I return to the original form and click on the button a second time, the query the displays the required data. This behavior is consistent, regardless of expense category, fiscal period, etc. The first time I try to access detail, no records returned, but the second time, it works.
    I have used the 'SESSION' link to debug and view the session state in each case, and the results are IDENTICAL whether the query returns data or not. That is, all 5 variables contain the exact same data.
    Do you know what I might be doing wrong?
    Thanks,
    Michelle

    Hi guys,
    Thanks very much for your replies. In fact, I have tried both methods. Yes, I am navigating from page 114 to 118, and passing values to page 118 from page 114 (ie: P114_PROJECT passes to P118_PROJECT, etc...). In my query, I have tried referencing both, with the same results.
    When checking values in session state (by using the 'SESSION' link), values from page 114 are available in both cases (when the query returns rows and when it does not). It is very strange behavior.
    I have been developing with HTMLDB for over a year now, and never seen anything like it!!! I will try loading this on HTMLDB.oracle.com, and see if it replicates, and if so, maybe you can have a look...............
    Thanks!
    Michelle

  • Completion percentage - If my Status date Task finish date & applied completion percentage 100% = ? New finish date for the task?

    Hi and sorry for the title but it well summarize my question.
    In fact I applied a completion percentage of 25% on a task with a finish date inferior to the entered status date.
    MS Project only modified the Act. work  of the task but not its finish date.
    Is it a normal behaviour?
    Thanks a lot for help
    Paul

    Paul --
    To answer your question, yes, what you are seeing is normal behavior.  If you want Microsoft Project 2010 or 2013 to automatically adjust the Finish date based on the Status Date, you will need to do the following:
    Click File > Options > Advanced.
    In the Calculation Options section of the Advanced page, select the option named Move Start of Remaining Parts Before Status Date Forward to Status Date.
    Click the OK button.
    If you select this option and enter task progress as you described in your question, Microsoft Project will force a task split, moving the uncompleted part of the task to start immediately after the Status date.  In the same Calculation Options section
    of the Advanced page of the Project Options dialog, you might also want to select the option named And Move End of Completed Parts Forward to Status Date.  With this option selected in addition to the one mentioned in step #2 above, Microsoft Project
    will move the completed portion of the task to the Status Date so that you do not see a task split at all.
    Whether you use one or both of these options would be entirely up to you, based on what you want to see in the software.  Neither is perfect, but I think one or both of these would give you the automatic scheduling that you seek.  Hope this helps.
    Dale A. Howard [MVP]

  • Worst update ever! On my Vista everything is wrong! Back button never active; If I want open pages as new tab it opens new window; FF starts with blank page instead of Google; No url address shown on status bar when I move mouse arrow on the link etc

    Worst update ever! On my Vista everything is wrong! Back button never active; If I want open pages as new tab it opens new window; FF starts with blank page instead of Google; No url address shown on status bar when I move mouse arrow on the link etc.. Please Help!

    Try the Firefox SafeMode to see how it works there. <br />
    ''A troubleshooting mode, which disables most Add-ons.'' <br />
    ''(If you're not using it, switch to the Default Theme.)''
    * You can open the Firefox 4.0+ SafeMode by holding the '''Shft''' key when you use the Firefox desktop or Start menu shortcut.
    * Or use the Help menu item, click on '''Restart with Add-ons Disabled...''' while Firefox is running. <br />
    ''Don't select anything right now, just use "Continue in SafeMode."''
    ''To exit the Firefox Safe Mode, just close Firefox and wait a few seconds before using the Firefox shortcut (without the Shft key) to open it again.''
    '''''If it is good in the Firefox SafeMode''''', your problem is probably caused by an extension, and you need to figure out which one. <br />
    http://support.mozilla.com/en-US/kb/troubleshooting+extensions+and+themes
    ''When you figure out what is causing that, please let us know. It might help other user's who have that problem.''

  • Product Delivered Status Date should be there in Standard Search and Result screen of Service Order. Product Delivered Time should be Available in Result screen and In Result screen there should be facility to filter on basis of Time

    Hi team,
    Product Delivered Status Date should be there in Standard Search and Result screen of Service Order. Product Delivered Time should be Available in Result screen and In Result screen there should be facility to filter on basis of Time.
    How to add this in search result screen.configuration is it possible? or any changes in development.
    Compnent - BT116S_SRVO
    Thanks
    Kalpana

    Hi Kalpana
    Please reread my comment. I said to try and populate "Requested End" Date.
    Make sure the date profile assigned to the transaction includes this Date Type.
    If you can populate this either manually or programmatically the solution should be quite forward.
    If you cannot do this, only then should you look at making any significant sort of enhancement.
    Regards
    Arden

  • What are the possible Monitor Object status data members

    I have problems connecting to the object over ethernet. I need to know what the status data member text info means.

    Hi,
    The status datamember of the Monitor object gives the state of the "connection" you're trying to monitor. For instance, when this datamember is displayed on a panel, it shows text like: "Good," "Disconnected," and so on.
    Hope this helps,
    Khalid

  • SDM instance is shown stopped status

    Hi,
    I am appling a note 905856 after that SDM instance is shown stopped status.
    I already started je22 engine and restarted SDM 3 to 4 times but no status is changed.
    I need some expert comments .
    Help will be rewarded.
    Regards,
    Gurprit Bhatia

    Hi,
    Kindly check what trace file says..check if SDM is in integrated mode and not on standalone.Because sometimes deploying components through SDM command prompt, we take SDM to standalone mode  and then once deployment is over, we take it to integrated mode. So kindly check its mode
    Regards,
    Ameya.

  • Status Date Shows NA But Really Should Have a Designated Date

    Hello all,
    I receive project files on occasion from which I know have an active Status Date (SD). When I open the file, the SD will show NA, indicating a SD hadn't been designated. 
    I've come across this issue typically, it seems, when I open a file that originated or was saved on a 2010 version of Project (probably standard edition). I have been using primarily MSP Professional 2013 to manage my schedules. When I open the files on
    a 2010 version of MSP, the SD will reflect that correct SD I should be seeing. 
    Is this a bug that's being looked into? A search on here did not come up with any answers to my particular question. Thanks in advance for any knowledge and help!
    Jay M. 

    Hi Jay,
    I cannot reproduce your issue. After saving a project with a SD in Project Pro 2010 SP2, I open it in MS Project Pro 2013 and the SD is still there. Which 2010 service pack are you using?
    2010:
    2013:
    Hope this helps,
    Guillaume Rouyre, MBA, MVP, P-Seller |

  • EWA state="data is available" but there is no "SM:EXEC SERVICES" job

    Hi everybody,
    i have a Problem with EWAs. It seems to work all fine, it does, until the EWA is in the state "data is available".I can generate a EWA without a problem, when i use the button "start service processing", but i want it to be generated automatically. I searched with TA SM37 for the job SM:EXEC SERVICES in SolMan and in the monitored system, but i didn´t find the job?
    Any ideas, what the problem can be?
    Best regards,
    Stefan

    Hi,
    @Rohit
    Thank you for your reply, but this was not what i looked for. Thank you anyway!
    @David
    Thanks, i will check my system and look at the table, i think this is a good beginning. Unfortuneately the note is at the moment not available....
    I am going to give feedback, if i found the finally solution!
    Bg,
    Stefan

  • SAP ER Incremental Reconciliation - Current Status = Data Received

    Hi,
    we are using SAP ER connector for SAP HR Trusted Source Reconciliation.
    The Full Reconciliation works so we switched to Incremental Reconciliation.
    The OIM Job named "SAP HRMS Listener" is Enabled and Active (that means OIM is listening on the TRFC Port of SAP HR system).
    Issue: when the SAP admin hires an employee on SAP HR system, OIM correctly receive the transaction (this means the communication between SAP HR and OIM works as excepted) and create a new Reconciliation Event but that event remains "open" without any error and with Current Status = Data Received.
    Note: no messages into weblogic_oim.log file and no errors into oim_server1-diagnostic.log.
    Regards,
    Gabriele

    Hi Gabriele
    Check the batch size system property. Only after the number of events reaches to that number, your recon events will be processed.
    Please run the scheduled job "Non Scheduled batch recon" to process the recon events immediately.
    Let me know the results.
    Regards
    user12841694

Maybe you are looking for

  • Udevd and creation of /dev/dvb/adapter0 fails for U3100 Asus

    Hello all, I have 3 arch PC's all running  3.14.4-1-ARCH properly updated. For some reason all 3 fail to create a /dev/dvb/adapter0 or adapter1 device when I plug in a dvb usb stick. The DVB USB stick from lsusb: Bus 006 Device 004: ID 0b05:1779 ASUS

  • How many machines can I install the $79.99 version on?

    How many machines can I install the $79.99 version on?

  • Video truncates on import

    I have an MPEG that was converted from an MPG4 using AVS Video Converter. The MPEG plays all the way through in a viewer like Microsoft's Windows Media Player. However, whenever I bring the MPEG into Adobe Premiere Elements 3 to edit, I get only the

  • Disabling Genius

    Is there anyway to disable Genius altogether on my iPod? Specifically, I want to turn off the function that activates Genius when the iPod gets shaken. (I listen to it in my car, and have to tip it forward into the cup holder while I drive, and it ke

  • SQL Cache/Procedure Cache Limit