EX lot size for maximum value

Hi Could someone answer this, my minimum lot size is 100 and max is 500, when my PIR qty is 90 it will generate planned order for 100 where as when my PIR is 600, i am expecting the planned order qty for 500 but it always the same with minimum lot size, is there any specific reason? using mrp type PD.

Hi Sprint,
Well you have to go through with the lot size procedures OK. EX means lot for lot order quantity so it does not consider the MINIMUM lot size OK please check once again OK.
If you are order quantity is 600 and maximum lot size is 500 then after running the MRP go to MD04 screen you can see there planned orders will be created so there first it will create Planned order for 500 quantity and then there will be another planned order for 100 please check once OK.
It will consider only maximum lot size OK.
Regards,
Madhu.G

Similar Messages

  • Rounding Value,Minimum Lot Size and Maximum Lot Siz parameters

    Hello Gurus,
           Please explain me the what is the use of the parameter Rounding Value
    ,Minimum Lot Size and Maximum Lot Size parameters in the product master and how does it in impact during the Heuristic Run?
    Thanks.

    Rounding value is the incremental quantities in which the order can be produced/procured. Eg. if orders are possible with quantities 40,60, 80, 100 etc..then rounding value is 20.
    Min lot size is the minimum quanity in which order can be produced eg. 40 in above example
    Max lot size is the maximum quanitity in which the order can be produced/procured. eg. 100 in our example
    Impact on Heuristic run: heuristics takes all the above parameter to plan supply order. eg. if requirement is 55, it will supply plan for 60. If requirement is 120, it will produce two orders - one for 100 and the other for 20. if the reuqirement is 10, the order size will be 40.
    Hope this helps.

  • Default lot size for MRP type

    Hi,
    Can we set default Lot size for MRP type ?
    Regards
    Karthik

    Dear,
    Yes you can do it by creating material master with MRP Pofile.
    First you need to create MRP Pofile in MMD1 where you need to define the LOT SIZE and MRP TYPE which you want then make these value as Fix Value.
    Then Create material master MM01 with this MRP Profile and check your result.
    Regards,
    R.Brahmankar

  • Min Lot Size and Rounding value

    Hello MM  Gurus
    need a small help!
    I m a bit confused regarding the  use of Min lot size and Rounding value in material master "MRP 1" view..
    can some body teach me a detailed functionlity for both..
    As both serve the purpose ..for e.g. my requirement is 7 and min lot is 10 system will create proc.proposal for 10
    in similar way if i use rounding value as 10 , then als system will create proc.proposal for 10 only even if requirement is 7.
    grateful if you could pl expain me the functionality of both...
    another query..if I use Min lot size in material master will the same will serve the puspose of  <b>min order qty ( maintained in PIRs)</b>
    i'lll appriciate with good reward points...thanks in advnace
    Br
    Sumit

    Helo Guys..
    Thanks for valuable inputs..
    i have assigned the appropriate rewards ..
    pl clear my this doubt also
    e.g. for a materials
    Min Lot size - 40
    Rounding value 25
    requirement is for - 35
    will it be 40 or 50 ..i understand 50..
    j
    ust anothe rquery..pl treat this separate issue..and separate rewards will be given
    <b>can I use max stock level w/o use of  lot size "HB"</b>
    e.g. if my max stock level is 80
    and min lot size is 30 and current stock is 60
    what'll be my proc proposal created by MRP , i dont want system to cross 60 stck,,
    Thanks in advance
    BR
    Sumit

  • Is it possible to change the Costing Lot size for preference calculation?

    Hi Gurus,
    Is it possible to change the costing lot size for the preference calculation?
    Reason for my question is: We have all prices on price unit 100
    and we want to use also the price unit 100 for preference calcalation.
    But the preference calculation always take price unit 1.
    Is there any possibility to set somewhere the costing lot size for pref.calculation?
    Thanks
    Regards
    Dieter

    Does really nobody has a hint?

  • Configure lot size for MRP

    Hi Experts,
    I would like to configure lot size for 3 monthly, can any one explain me the configuration procedures?
    Thanks alot
    Rgds,

    Hi Vivek,
    I copied the Z3 form MB, and changed the no of periods into 3. and there're no difference between material assigned with Z3 or MB.
    We haven't activated MRP4 view, do I have to activate that view first to make this happen?
    for your additional info, I use MRP type (configured) based on ROP.
    Pls help.
    Thanks

  • Minimum Lot Size with Rounding Value

    Hi I have an interesting scenario.
    I just want my procurement proposals to be generated in multiples of 40000. But I have agreed to my vendor on Minimum Lot Size of 75000 qty. My aim is to generate the proposals with 80000 qty even for the demand of 25000.
    But when i am carrying out the MRP run for the demand of 20000, ssytem is plan only for 75000. But when i increased the demand to 50000 or more system plans in multiples of 40000, i.e. 80000 qty.
    Is there by anyways can we plan in multiples of 40000 eventhough the min lot size is 75000 and the demand is 20000?
    -solai

    Hi,
    Maintain lot size as EX, Minimum lot size as 80000 and rounding value as 40000 in the MRP to get the procurement proposals in multiples of 40000.
    Regards
    Venkat.V

  • Lot Size for Split Cost

    Hello,
    My company has just had SAP installed and I am trying to confirm whether there is a  general calculation in SAP or whether it is due to the configuration that has been choosen from our implementor.
    I have costed some materials we have setup as a split cost (choice of either purchased or manufactured) and setup the mixing ratio. I then cost it but SAP generates the Lot size automatically and this can not be changed.
    i.e. 90%:10% split gives a lot size of 280 (252 and 28) and 50%:50% split gives a lot size of 200 (100 and 100).
    Please can you confirm that this is normal and also if it can be overriden?
    Thank you for your assistance

    Hi,
    This is a normal behaviour of the system.
    regards,
    Sayujya

  • Default font size for a value in a table in Answers

    Hi,
    I am trying to set a default font size for a column of table view in Answers, so that when I create a new report, this default font size is used. Can someone please point me to the file where I can make this change?
    Thanks

    Well if you have a tag like this:
    element.style {
    background-color:#FFFFFF;
    font-size:9px;
    It means it's coming from the formatting in the request in Answers...not from a style sheet! You'll note in Firebug, that there's actually no *.css file mentionned. I.e. example from here:
    element.style {
    color:#00AF00;
    .OORD {views.css (line 1574)
    text-align:right;
    .PTE {views.css (line 1077)
    background-color:#FFFFFF;
    First part element.style comes from my conditional formatting and doesn't reference any css file
    The other two elements are from the views.css which control my pivot table.
    See the difference?
    Cheers,
    C.

  • Select querry for maximum value

    Hi,
    I want to select fields A B C D from a database table TAB using some selection criteria from selection screen, but the greatest value of A has to be selected for all unique entries of B C and D. Please suggest an appropriate select querry.
    PS: I cannot use SELECT and then DELETE ADJACENT DUPLICATES as it will effect performance in some cases.
    Regards.

    Try using aggregate function MAX with SELECT statement.
    MAX Returns the greatest value in the column determined by the database field f for the selected lines. Specifying DISTINCT does not change the result. NULL values are ignored unless all values in a column are NULL values. In this case, the result is NULL .
    Have a look at below link:
    [Select Clause|http://www.sts.tu-harburg.de/teaching/sap_r3/ABAP4/select_c.htm]
    I hope it helps.
    Best Regards,
    Vibha
    Please mark all the helpful answers

  • Rounding Value is not considered for MB lot size

    Hi
    I have a scenario where MB (Monthly Lot size) lot size is used with rounding value. Example as below:
    Lot size: MB
    Min Lot size: 15000
    Rounding Value: 20000
    DEMAND: 16000
    When MRP run, System is creating the 16000 as P Req instead of 20000 which is the rounding value.
    Pl let me know, if I need to apply OSS note / any other solution for this.
    Thanks,
    JK
    Edited by: Janakiram Katakam on May 17, 2010 4:57 AM

    Dear ,
    Are you using any Rouding Profile in MRP1 view ?
    What is the Setup in OMI4 for MB-Lot Size .Remove the tick mark in Last Lot Exat if it is marked .By specifing the rounding value, the system will determine during lot size calculation that lot size qty is a multiple of of an order unit(eg : pallet size if mtrl is delivered in entire pallets...).
    Please check what is the Lot Size Indicator or Lot size procedure assinged to it ?
    2.you can use rounding profiles...its used to define the setting of rounding up or rounding down the order proposal qty into deliverable quantities...rounding profile maintenance the t-code is OWD1. Here for static rounding profile
    Rounding profiles are defined under:
    spro-> purchasing->consumption based planning->planning->lot size calculation ->maintain rounding profiles...
    it consist of threshold value and rounding value...
    the threshold val is the value from which the system rounds the value of the next deliverable units upto...
    the rounding value is from which the systemshd round up to as soon as threshold value is exceeded...
    Otherwise ,  Check FM MD_ROUNDING_VALUE
    Regards
    JH
    Regards
    JH

  • Lot size calculation for Purchase order

    Hi all,
    I want to purchase Labels which comes in lot qty such as in lot of 100,200 etc.
    For that particular items i want to do mandatory qty lot size in PO when buyers places the purchase order.
    Can anybody tell me How i can map that lot size for the particular item.
    Regards,
    Anant

    Hi,
    You can done it with change Material Master.
    Enter MM02 t-code, enter your material code and select MRP1 view.
    Here maintain Rounding value as 100 in material master.
    After when your create purchase order system put quantity as 100, 200, 300 etc.
    Regards,
    Mahesh R.

  • Lot Size Planning for Procurement

    Hi  guys
    In our company we work with minimum lot sizes for procurement, and we need to configure minimum lot sizes for procurement in the SNP optimization run. It´s posible to do it in SNP, pls can someone tell me how to configure this in SNP?
    David

    Hi David,
    I am glad to hear that.
    Regarding your performance issue: it is very usual to have long runtime when using discrete model.
    The complexity of this model is much higher than a linear problem; so the optimiser takes time to find THE optimal solution.
    However there is a lot you can do to make it better:
    1. Split your model: instead of running 1 big optimiser, run serveral smaller one in parallel.Ensure your model are all independant (e.g. no common product or resource)
    2. Use decomposition: (product/ time/resource; based on your scenari) to simplify the porblem, hence speeding the solution.
    3. Set a maximum time
    You do not have to wait for THE optimal solution. The optimiser can sometime very quickly find a very good solution; the last hours are spent "fine tuning" it. Potentially, you might not be able to see the difference between a 4h job and the 15H one).
    Hence SAP advises to set a maximum runtime when working with discrete model.
    The question is how to define this maximum time to optimise the ratio solution quality / runtime.
    Answer: test it, check the result. Be aware that perfomrance testing for the optimiser can take a while.
    4. fine tune you optimiser setting
    There is a couple a finetuning that can be done to improve performance, especially for discrete model.
    I will not be able to help you woth that.
    As far as I am aware only the SAP optimiser team has the expertise to help here.
    I strongly recommand to contact them; their help is often invaluable. They will also help you to define the 3 first points.
    I hope this will help you.
    Thanks and Regards
    Julien

  • Min max lot size time based for use with SNP and PPDS

    Hi all, Is there anyway to set up time based min and max lot sizes? ie we want to have a Max lot size which is small for use with the first 3 months of our plan which starts life in SNP and then converts to PPDS and into blocks for block planning, but months 4 to 36 we want to leave as large max lot sizes as there is no need to have the small max lot sizes for the different horizon.
    As far as I can see there is only a material/plant lot size  and Max lot size and no way to have a different setting in a different time period.
    Thanks
    j

    Hi John,
    As you know, in the product master, the lot size maintenance is time-independent, so that obviously can not be used for your scenario. As per my understanding, to meet this using standard functionality, you can maintain multiple product specific t-lanes (for STRs) and PDSs (planned orders) with required lot size ranges and validity dates (for short or long term horizon). But, again since the validity of t-lanes and PDSs will not be automatically rolling forward so the updating the validities will be a challenge.
    The other option could be to enhance the heuristic functionality at lot size selection step while creating order.
    Regards,
    Umesh

  • Generating alerts in Purchase Requisition = 3*Lot size of material

    Hi Experts,
    We want to create alerts in SNP.
    Below is the condition.
    Heuristics for multiple product-location will run in background.
    After the Purchase Requisitions are created, we want to compare the quantity of created purchase requisition at each time bucket with lot size maintained for that product-location.
    Alert should get generated if the PR qty is >= 3*lot size of that product-location.
    is there any user exist or function module avaialble to call the tabel which contains rounding profile/lot size details in APO?
    Thanks for looking at it,,
    Rgds/
    Jay

    Jayprakash,
    You can extract the Lot Size values using the macro function MATLOC()
    MATLOC( 'FIELD_NAME' ; <'product'> ;  <'location'> ; <'version'> ) returns the content of a numerical field in the location/product master record of the specified product and location. The arguments for product, location, and version are optional. If you do not specify an argument for the product and/or location, the system uses the current product/location. However, it is better for performance reasons to use the functions ACT_LOCATION and ACT_PRODUCT. For example, MATLOC( 'BSTMA' ; ACT_PRODUCT ;  ACT_LOCATION ) returns the maximum lot size for this location product.
    In your case you can use:
    MATLOC( 'BSTFE' ; ACT_PRODUCT ;  ACT_LOCATION ), assuming you are using Fixed LOT Size. You can store this value in a layout variable 'V' and raise alerts based on condition:
    IF ( KF for PREQ > 3 * Layout Variable V) RAISE Alert
    Hope this helps
    Cheers!
    Abhi

Maybe you are looking for