Exception message 30 & Reschedule date

Hi All,
This is about the exception message 30 which is displayed in MD04 and the rescheduling date.How is this date determined and what does the exception message signify. how the system determines this dates?Also, what is the criteria for this rescheduling date to be displayed in MD04?
For Ex
Material XYZ , MRP Type : PD, Lot size :Monthly,PIR is 100 for march, After MRP run I am getting reqmnt date is on 1st April. Reschedule dt is 02-March, Expn Msg is 30. Inhouse production is 1 day & GR time is 2 days.
Please let me know how system arrives on 2 march as rescheduled date & what does it mean?
Thanks and regards,
Kundan Kumar

Dear,
Within this rescheduling horizon, the net requirements calculation checks whether, after a requirement, a firmed receipt exists, which can be used to cover this requirement. Then the system displays a rescheduling date as well as the exception message Bring process forward for this receipt. The net requirements calculation then uses this receipt and the system will only create another procurement proposal if the receipt quantity is not sufficient to cover the complete requirement. Several firmed receipts can be used to cover one requirement.
The rescheduling horizon is always calculated from the MRP date.
Please refer this link,
[Exception message 30 |exception 30]
Have you assigned a range of coverage profile to the material?
Regards,
R.Brahmankar

Similar Messages

  • Analysis of rescheduling date

    Hi Experts,
    I am a buyer. i am facing problem in rescheduling cases.
    I want to analyze in mass the MRP dates and the reschedule dates with the exception messages.
    I tried Md06 but it does not give the comparison between the MRP dates and reschedule date.
    I wnat report in the following format:
    Material     Plant     Exception message         MRP date     Rescheduled date.
    Thanks,
    Sachin

    There is no place to add the specfic fields in the evaluation list. The only options are user-exits.
    Solution 1:
    Please use customer exit M61X0002 to program company-specific additional information in your own columns for the display of the MRP list and the stock/requirements list.
    You can define that additional data fills each of up to three columns in the display of the individual lines and the period totals. The user uses pushbuttons to access this additional data in the lists.
    Solution 2:
    Function module LM61XU11 MD_STOCK_REQUIREMENTS_LIST_API includes the basic functions for setting up the MRP list and the stock/requirements list. Use this function module to program lists, which are exactly tailored to the requirements of your company.

  • Exception Message number 30 and rescheduling date

    Hi everybody,
    This is about the exception message 30 which is displayed in MD04 and the rescheduling date.How is this date determined and what does the exception message signify. Further, it would be great if i can get any link on forward/backward scheduling and how the system determines the dates?Also, what is the criteria for this rescheduling date to be displayed in MD04?
    Thanks and regards,
    Deepthi.

    Hi,
    Exception Message 30 - Plan process according to schedule
    say , if there is a PIR on 02.7.08 and a planned order to cover this reqmt is generated with Ord finish date as 05.7.08 , system will now throw an Exception Message - 30 with the rescheduling date as 02.07.08 to complete the order on the same day as that of the requirement say 02.07.08.
    also , pls go thru the foll links
    http://help.sap.com/saphelp_470/helpdata/en/55/6704a195d711d3b6fb0000e8359890/content.htm
    http://help.sap.com/saphelp_470/helpdata/en/f4/7d294a44af11d182b40000e829fbfe/content.htm

  • MRP Type V1 - Does it create Exception Message for "Reschedule-in"?

    Hello Experts,
    We are using MRP Type V1 (Which has the Manual Re-Order Planning + External Requirements). However we are facing and issue with the Rescheduling part. Scenario is as following:
    Material ROP is - 5000
    Open Pur Ord is - 5000 (due in 01 June'09) based on the Std Lead time of the Material
    Stok on hand is - 0
    At this point a Sales Order is entered for 1000 pcs
    After MRP Run, we expect an Exception Message for the Purchase Order to have "Reschedule-in". But, instead, system creates a PReq for 1000 pcs and the required date is NOT the Sales Order required Date but based on the Std Lead Time of the Material.
    I have set the Material Lead time - 60 Days
    I have set the Reschedule horizon - 0 Days ( I even tried with different Days but NO use)
    However, when I change the MRP Type to PD, system generates a "Reschedule-in" Exception Message for the Purchase Order.
    How can I get the "Reschedule-in" Exception Message for the Purchase Order with the MRP Type V1?
    Thanks for your help in Advance!

    Anil,
    Reorder point/External MRP performs net requirements calculation (within replenishment lead time).  If the existing firmed supply elements minus the existing requirements bring the projected stock below ROP, it will propose an order that will bring the projected stock back to reorder point.  The proposal will generally come at replenishment lead time.
    In the normal business cycle, your sales order would confirm to lead time, and you now have a confirmed sales requirement at lead time, plus a new purchase req to bring the stock back to the reorder point.  The scenario you have described is working exactly as it is designed.  Consumption based MRP will not normally try to reschedule supply elements to match requirements inside of lead time.
    Rescheduling horizon generally is counted from the end of lead time.  It won't help you here.
    I guess if you insist on having a reschedule message, you could change your lead time to 0 days.  Not a wise move in my opinion.  You then have locked yourself in your choices of types of Sales order availability checks into one that ignores lead time.  You also have to find a way to let your buyers/planners know what the 'real' lead time is when they place their orders on the vendors.
    I don't know why you are using a consumption-based planning type (reorder point).  It sounds like your business requirements are that you actually need to be using a demand-type planning method (eg, your supply elements are driven by your demand, not by a reorder point/desired stock level).  If PD works the way you want, why aren't you using it?
    Regards,
    DB49

  • Report to get the Material with Exception message"10"  Rescheduling in

    Hello All
    We want to get the report to get the materials with exception message"10".We can get deatils from T code MD06,but it is restricted to MRP Controller/Vendor and we can get the details from Table "MDKP".Plese provide any report or T code to get the details of the exception message "10"
    Thanks
    Suresh kumar

    Hello
    You can use BAPI_MATERIAL_STOCK_REQ_LIST todata from MD04 or BAPI_MATERIAL_MRP_LIST to get data from MD05.
    BR
    Catano

  • Dates and Exception message in MD04

    Hi all ,
                  When i view in MD04 t-code for one purchase order the system shown the below exception message
    Exception  30 = Plan process according to schedule (08/01/10/07/25/10)
               06 = Start date in the past
    I cant understand the dates inside the braket . We are following the factory calender all days working days (No holidays)
    When i calculate the no of days between 07/12/2010 and 08/11/2010 it is more than 28 days (the date format is ( MMDDYYYY)
    Can anybody explains why it is happened?
    Delivery date   D 08/11/2010
    Req. date       07/12/2010
    Release date    07/12/2010
    Plnd dely time  28
    GR proc. time   7

    Hi,
    Refer to Mr. Rajesha's reply in the below thread, it should clarify your doubt, else revert
    exception Message 30 "Plan process according to schedule"
    Regards,
    Vivek

  • Exception Message: The form cannot connect to the data source. Login failed for user 'NT AUTHORITY\ANONYMOUS LOGON'

    When opening a form in SharePoint 12013 that was created from Infopath 2013, I get the following error.
    You do not have permissions to access a database that contains data required for this form to function correctly.
    An entry has been added to the Windows event log of the server.
    Log ID:5566
    When I go to the log files on the SharePoint server. I see the following error.
    Exception Message: The form cannot connect to the data source. Login failed for user 'NT AUTHORITY\ANONYMOUS LOGON'
    I am guessing this has something to do with the UDCX connection and the database.
    Can anyone help me get this fixed?

    Hi Jim,
    Please check the following kb article when it occurs 5566errro with the UDCX conection file, try the method of using the Secure Store Service to store alternate credentials for the data connection method, or the method of stating the credentials
    in the UDC file explicitly.
    Also check if it could help with setting sql server as "SQL Server and Windows Authentication mode".
    http://support.microsoft.com/kb/981684
    Thanks
    Daniel Yang
    TechNet Community Support

  • Reschedule Exception message in MRP

    Hi ALL.
    MRP suggests rescheduling a PO to create a new one for delivery in the past. The planner clicks the Processing Indicator (Dealt With). As soon as additional orders come in and change the quantity, the "Dealt with is over-ridden" Can this be prevented? Suppress "Reschedule" exception messages?
    Please Advice,
    Jinen

    Hello
    I have just created a new WIKI about the rescheduling check on MRP.
    Please take a look on the link below:
    http://wiki.sdn.sap.com/wiki/x/xAJhE
    BR
    Caetano

  • Exception message 62 - Master Data Inconsistant

    I'm getting the referenced exception message when generating an MRP run with scheduling value of "lead time scheduling and capacity planning".  I've done consistency checks on all master records - routings, work centers, etc - and all have come back clean.  Anyone have any idea why this may be happening?
    Thanks!
    Bob

    Hi,
        62 Scheduling: Master data inconsistent Check master data !
    Remove "In House Processing Time" from the Material Master MRP2
    view. Ensure that the Production Version & Routing are correct. Run
    MPS/MRP manually once corrected.
    Regards
    Sunil

  • Exception & Rescheduling date in MD04

    Hi all,
    Can anyone explain what is exception in MD04 screen.PR generated automatically for the unconfirmed schedule line quantities in the sales order.The exception 30 is automatically proposed by the system.How is it?
    Please expalin the rescheduling date also
    Regards
    Mano

    Hi,
    MRP Message30 = Plan process according to schedule.
    This means that all the requirements as calculated during the MRP run are satisfactory and that the process can continue.
    What to do:
    Proceed with the process; i.e. convert the planned order and purchase requisitions.
    Regards

  • Significance of Rescheduling Date and Exception group

    Hi Guys:
    could you somebody explain the significance of reschedule date and exception group in MD04 Transaction?.
    thanks
    sweth

    Hi,
    Rescheduling dates are not stored, they are calculated dynamically every time you execute or refresh MD04.
    Rescheduling date is based on the Stocks Requirement date.  It does not take into account the parameters in Procurement and Scheduling in the Material Master. In the net requirements calculation, the system checks whether warehouse stock or firmed receipts are available to cover requirements. If a material shortage exists, the system usually creates a new procurement proposal.
    Most catchable runtime errors are assigned to exception groups. For this go through the link. Thanking you.
    http://www.sapnet.ru/abap_docu/ABENSYSEXC-ERRKL.htm

  • Is there a report to track the exception messages after a MRP run ?

    We have a scenario at our client site where MRP run is not optimized to the fullest.
    The planners are not trained on how to interpret those exception messages.
    They are not trained on how to reschedule / expedite planned orders resulting from an MRP run.
    Is there a report out in SAP that keeps track of
    1) History of number of exception messages by type ( Expedite/Reschedule/Cancel)
    2) History of number of exception messages that were acted on or ignored by the planner.
    This is to create metrics on the usage of MRP exception reports by planners.
    Appreciate your inputs..

    Hi
    The exception messages are dynamic and time dependant. You cannot have history of exception message.. If your user is feeling difficult to use standard MRP reports. Create a new report using a function module MD_STOCK_REQUIREMENTS_LIST_API
    It gives all MRP data including exception messages.
    Regards
    Antony

  • What table are Exception Messages in MRP stored?

    The requirement is to develop an error report from an MRP run to capture the exception messages along with the selection groups.
    Ex:Selection Gr 2; Exception Message 15: Reschedules In.
    I am unable to track where exactly the exception messages are stored after an MRP run. Any suggestions as to how to go about this requirement.
    Thank You.

    You can basically get a list of all tables MD06 (colelctive MRP list) uses to fetch data. GO to tran se30. Under Measurement restrictions click new and in Duration/Type tab select none. Go back to se30 main screen enter tran MD06 and execute. It will take you to MD06, run it with any material and go back to se30 screen. At the botton select evaluate and on the evaluation screen select "Data base hit list" or F6. That will give a list of all tables accessed by MD06. SO basically you will know all the tables that were filled during last MRP run.
    Atul

  • Exception message for PrdOrd and Planned order

    Hi Gurus,
    It possible based on prdord and planned ord we need to get the Exception message information. It's there any standard transaction code or any sqvi report?
    Note:
    Exception Message:
    10 - Reschedule in
    20 - cancel
    05 - Opening date in the past
    26 - Excess in individual segment
    Please find this information in MD04 (single order). i am looking for same time multple orders with exception message report.
    Thanks and regards,
    Deethya.B

    Hi
    You can use MD06 with refrence to you plant and MRP Controllers. Also you can define your own traffic lights so that based on these you get your exception messages.
    Hope this helps,
    Regards,
    Ravi

  • Exception message 10 and safety stock

    Hello
    When I have a ressource in the past (we have this case), and if the safety stock is not complet, the exception message is "10" (reschedulling in) without date.
    Normaly the result should be exception message "15" (rescheduling out) with a date.
    Why have I an exception message "10" without date ?
    Is it the custo, but I found nothing ?

    Hi Christian,
    I've seen this myself, and believe that it happens only if you allow start in the past and have got insufficient coverage for safety stock.
    I guess it doesn't have a date because of the start in the past, which will set availability date even today. Try to change the "start in the past" indicator, and see what happens.
    Regards,
    Mario

Maybe you are looking for

  • How to Call complex data type in ALBPM

    Hi, I want to call webservice. I took wsdl from other system(example MessageBroker or OSB).Now that wsdl file is referring to internal xsd. The input format of wsdl(webservice) is just like:- <SOAP-ENV:Envelope xmlns:SOAP-ENV="http://schemas.xmlsoap.

  • Portal Integration Scenario

    Hi Friends,    I am jus trying to integrate BW and Portal through XI. Can anyone suggest me a complex scenario that involves a 3rd party application say a java appln? Thanks in advance. Regards, Nathan.

  • To insert the xml data's generated dynamically it to orac very very urgent

    I AM WORKING IN A PROJECT WHICH RECEIVES THE DATA FROM FLAT FILES AND CONVERT IT TO XML FILE> I am in need to convert the xml file generated dynamically through out the year map it to correct datafield it the database and insert it in to oracle data

  • Create a PD infotype

    Hi experts, Can anybody guide me on how to create a PD infotype? I don't know if I have to use PM01 transaction or PPCI transaction, can anybody solve my doubt? Thanks a lot Regards, Rebeca

  • Convert 7.1 VI's to 7.0, please help

    Can someone convert these VI's from 7.1 to 7.0 for me? Thanks in advance. Attachments: 7.1VI's.zip ‏189 KB