Exception msg in MD04

Dear Experts,
I am Having a commercial Item : 5047645, we have a production plant ZXX and distribution plant ZYY, when i execute the MD04 for this particular item with plant ZXX - production plant i am not getting any exception message 82, but when i am executing the same with the distribution plant i am getting the exeception messaage 82.. please let me know the reason for it.
And the exception message says Item is blocked - whether it means the item is blocked for procurement, how and where to check in these case, and can we remove this exception messgaes from MD04.
Kindly suggest.
Thanks & Regards,
Sampath

Sampath,
If you received an MRP message, it means the item is blocked for MRP.  It could also be blocked for other functions.
This is controlled by the "Plant-sp Mat'l status" in the Material Master (MRP1).  Use MM02, remove any status code here, or substitute another code of your choice, one that allows MRP.
Best Regards,
DB49

Similar Messages

  • MRP - want to create query for Exception message number (MD04)

    Dear all MM kings
    consider  i had one purchase against xxxx material , if i go to MD04  In Exception message number  column i got massage number 20 Cancel process, now i want to know how many purchase order exist  in system having the Exception message number  20
    i want to define query for Exception message number 20
    is there any way to do the same

    Hi,
    There are links on the first thread on this MM board that describe how to produce a query.
    But if you have not done this before and have no ABAP experience, you might find it a bit tricky.
    You need someone to find the tabkle that stores the MRP lists and see if this contains the exception message, first.
    the structure I gave you is probably built dynamically by the program and so may not be available for a query.
    One simpler option is to use the "Collective access" tab in MD04. here you can enter an MRP controller etc. and get a list of materials. You can then find out which of the 8 numbered columns contains the exception message 20 and then sort the list in this sequence (the exception messages are linked to one of the columns and this can be different in every implementation and so I can't tell you which one it is)
    This will not just get the "20" messages unless they have been configured to use a separate column, but at least it is avail;able now without config and may be enough for your purposes.
    Steve B

  • Dates and Exception message in MD04

    Hi all ,
                  When i view in MD04 t-code for one purchase order the system shown the below exception message
    Exception  30 = Plan process according to schedule (08/01/10/07/25/10)
               06 = Start date in the past
    I cant understand the dates inside the braket . We are following the factory calender all days working days (No holidays)
    When i calculate the no of days between 07/12/2010 and 08/11/2010 it is more than 28 days (the date format is ( MMDDYYYY)
    Can anybody explains why it is happened?
    Delivery date   D 08/11/2010
    Req. date       07/12/2010
    Release date    07/12/2010
    Plnd dely time  28
    GR proc. time   7

    Hi,
    Refer to Mr. Rajesha's reply in the below thread, it should clarify your doubt, else revert
    exception Message 30 "Plan process according to schedule"
    Regards,
    Vivek

  • Material/Location specific exception messages of MD04

    Hi,
    Any pointers to get a report of all exception message in for specific material,plant combinations so that those can be targeted for correction .
    i.e. In MD04 for a material at location we can see the exception messages ,do we have any table or report to get a consolidated messages so that one need not to load each and every product in MD04 .
    I am not looking for a MD06 or table of standard list of MRP messages.
    Regards,
    Digambar

    Hi,
    Your question is not clear; MD04 is a dynamic report, meaning that it's content cannot be read from a database table (at least not all of it).
    The static alternative (in my opinion even better for exeption massages) is the MD05 MRP list. It exists in the database, and so can be read and processed in the way that you want.
    By the way, both have also BAPIs to be used.
    So, what is that you are in need of?
    Regards,
    Mario

  • Exception Message in MD04.

    I got the following Exception message for a planned order in MD04,
    20: Cancel process
    After getting help for this, system is giving the dignosis that,
    "There is no requirements for this receipt. It should be reversed to avoid unnecessary warehouse stock."
    What this means?
    Regards,
    Deven

    Hi Deven,
    Please check the dates in the planned order. This could be before that  of the date of requirement.
    i.e. If there is no requirement before the date of the planned order then system will propose to cancel the proces...since as per system there is no requirement & hence no need for a planned order.
    To check pass a requirement /PIR before that date & then this error will not be displayed.
    Regards,
    Senthilkumar

  • Exception message in MD04 & MD05

    Hi experts,
    There is an problem related to exception message,
    It has been observed that immedeate after MRP run, no other transactions done, I am getting exception message in MD05 for one of the component as "30 - Plan process according to schedule", and the same i am not getting in MD04. What could be the reason for same.
    Note: No transaction done after MRP
    Regards,
    Lodhi.S

    Hi,
    Please follow the given below link.
    exception message 30 & Reschedule date
    Regards,Kundan

  • GR processing time not taken into account for exception message in MD04

    Hello Gurus!
    In MD04 when we toggle between displaying at GR date and AV date sometimes there is a shortage in AV date view but none in GR date view due to GR processing time.
    How can we include the GR processing time to be taken into account so that an exception message is shown for the shortage during AV view?
    Thanks in advance!
       -Alvin

    Hi There
    What you meant by shortage,,,
    AV- Available date,
    GR- Availble date+GR processing time
    if you have not set up the GR processing time in Master, it may come as ZERO days,, so AV and GR date may be same,,
    if this is not your quesry, please provide more details on your query,,,
    Thanks
    Senthil

  • How to find List of  all materials of exceptions 15 in  MD04 ?

    Dear all,
    In MD04 , we get single material with dates,order, exception , etc..... details.
    If i want to know the all materials having exception 15 - rescheduling out , How to find ?

    No. I could not get answer.
    I want to find List of  all materials of exceptions 15 only.

  • Need Exception Number from MD04 Transaction

    Hi everyone!
    *Can anyone help me to get the additional data for MRP elements.
    In the transaction MD04, when we double click the line item details. We can see 2 Exception Numbers.
    My requirement is to fetch those 2 exception no. I have tried with FM MD_STOCK_REQUIREMENTS_LIST_API and BAPI_MATERIAL_STOCK_REQ_LIST. Both this retrive the exception No...which is shown at the time of executing the tcode MD04.
    For Eg. If material 'xyz' is showing exception no '06'. Then the above 2 FM fetch this '06'.
    But, when we double click on the line item, it should exception no '06' and '07'. So my requirement is to get the both exception no,
    Please help.
    Thanks!

    create or replace procedure p
    is
    cursor c is select e1.id,e1.name,designation.e2,gender.e2 from e1,designation,gender
                 where e1.designation=designation.e1 and e1.gender=gender.e1;
    v e2%ROWTYPE;
    begin
      open c;
      loop
           fetch c into v;
           exit when c%notfound;
           if (...) then
              insert into e2 values(v.id,v.name,v.designation,v.gender);
           end if;
      end loop;
      close c;
      commit;
    end p;Regards,
    Sayan M.
    Edited by: xtender on 15.11.2010 16:44

  • MRP Exception Message in MD04

    Hi team,
    My entire MRP planning is being carried out in APO system. My R/3 system just receives the planned orders from APO & i will convert the planned order to production order (MASS). Hence i did NOT maintain any configuration in OMDW for my plant. Is this OK or should i maintain OMDW for my plant in R/3 even though my planning is happening in APO?
    Thanks

    Hello Sugan
    If the entire planning is made on APO and if you don't controll the rescheduling messages in MD04 or MD05, then it's not necessary to maintain OMDW.
    BR
    Caetano

  • Regarding Exception Messages in MD04

    Hi Gurus,
    Can any body explain what's the main scenario where we get 'Exception message 30' i.e. Plan the process according to Schedule?
    Is there any standard report which will display all the firmed planned/prod.ord based on MRP controller?
    Helpful answers will be rewarded with points,
    Thanks,
    Sekhar

    Hi,
      If your order start date  of the planned order lies in past and the order start date in past indicator  is not allowed in OPPQ the system automatically switches to forward scheduling taking todays date starting date of the planned order. In this case the system issues a exception message 30 Plan process according to schedule.
    System Current Date : 14.07.2007
    Reqmts date             : 01.07.2007
    Planned order start date : 14.07.2007 with exception message 30 .
    If order start date in the past indicator is not allowed during MRP Run the system creates planned order on 14.07.2007 with exception message 30 plan process according to schedule since your reqmt date is 01.07.2007.
    If the order start date in the past indicator is allowed in OPPQ during MRP run
    the system creates planned orders on 01.07.2007since the reqmts date is 01.07.2007.
    Regards,
    nandha

  • Get parent JFrame for displaying exception msg

    I have a problem.
    Lots of my application components are classes that extends JPanel
    In these classes lot's of different exception could be raised.
    Some of them I want[b] to show to user (invalid input, no DB connection error e.t.c.)
    I make may GUI with help of GUI-builder + I write own classes As I said. Then I initialize them on my form in code.
    How can I reach parent form and send message to user?
    Is there any common method like:
    getParentForm.showMessageDialog(String mesage);
    Did I explain my problem clearly...?

    No, FAQ - is pretty useless thing.
    I suggest this one idea:
    see visualization:
    http://foto.mail.ru/mail/ice_holod/114/s-494.jpg
    no read my idea. I hope you will undestand me.
    Excuse me for offtopic.
    I suggest to develop "wisdom master.
    This master will give user solution for his problem.
    It will look like interactive dialog.
    For example, I have a question: �I want to put JComboBox into JTable�.
    I open �wisdom master�
    There I see list of topics:
    1.SWING/AWT
    Database
    Java language basics
    I choose �SWING�.
    2.The I see lest of SWING components, which were discussed million times:
    JFrame
    JTable
    JComboBox
    e.t.c.
    I choose �JTable�.
    3.Then I see list of ready solutions divided into categories:
    Embed something (embed checkboxes, comboboxes e.t.c.)
    Control data in JTable (add/delete row)
    e.t.c.
    I choose �Embed something�
    4.Then I see description and links to several threads:
    Embed combobox (several links to most valuable threads)
    Embed checkbox (several links to most valuable threads)
    e.t.c.
    BUT!
    If I would choose JComboBox instead of JTable on step #2 anyway I will get JComboBox + JTable solutions through master.
    See this chain: SWING->JComboBox (I did not choose JTable)->Embed somewhere->Embed into JTable
    Of course, such �wisdom master� will not help starters. Sometimes they even can�t understand what they need and what to search (I am a starter and sometimes I do not know what exactly to read, and where to search�)
    But, I think such service will help users which familiar with Java technology. The y will not have to read �search results� and million topics.
    The way to solution will be shorter.
    The MAIN PROBLEMS are
    1.     Separate food solutions and useful threads
    2.     Develop categories. We do not have to create many categories, user can lost in these categories, we can�t reduce their quantity. We have to find gold middle.
    3.     Develop good graph (graph branches = search chains). Categories=nodes of Graph

  • How to identify correct action to aleviate all 62 exception msg?

    Hi experts,
    I would like to ask, when I try to run MRP (MD02) system generated planned order will always has an error message "62: Scheduling: Master data inconsistent".
    How to aleviate all 62 exception messages that appearing on plant xxxx materials.
    I did checked on the routing data, and I am very sure that the routing is there and is valid. When I go into the planned order (display mode), I can see that the planned order has selected a routing (under the Detailed Scheduling window).
    I really have no idea why system telling me my master data is incorrect.
    Can anyone give me a hand?
    Many thanks.
    Regards,

    Hi
    Answer is pure assumption
    Pls check the OSS note - Note 88505 - Planned order upload generates exception message 62
    Pls take opinion from SAP / Basis team, if you want to implement the note
    Regards
    Madhan

  • Exception Msg = -1

    Hi -
    The following statement compiles perfectly and intellisense showa all the objects properly but in run time we get an exception:
    Code - wdThis.wdGetCCreateCustController().wdGetContext().currentGp_Detl_008AElement().setForm_Code("008");
    Exception - msgMgr.reportException(ex.getLocalizedMessage(), false);
    Output shows:
    -1
    Help please
    Thanks
    Shahid

    Hi Fellows -
    No body has answered this yet. May be I have not provided enuogh details:
    An action item in our guided procedure through CO calls WD form this works fine we see a form. The form has a submit method which executes the following code:
    public void onActionSubmit(com.sap.tc.webdynpro.progmodel.api.IWDCustomEvent wdEvent )
        //@@begin onActionSubmit(ServerEvent)
         IWDMessageManager msgMgr = wdComponentAPI.getMessageManager();
         String uniqueKey = null;
         String returnMsg = null;
         String message = "One";
         try {
              message = "two";
              //wdThis.wdGetCCreateCustController().wdGetContext().currentGp_Detl_008AElement().setForm_Code("008");
              String proj_num = wdContext.currentProjectInfoElement().getProjectNumber();
              message = wdContext.currentProjectInfoElement().getProjectNumber();
              wdThis.wdGetCCreateCustController().wdGetContext().currentGp_Detl_008AElement().setProj_Num(message);
              message = "three";
              wdThis.wdGetCCreateCustController().callZ_Gp_Save_008_Input();
              wdThis.wdGetCCreateCustController().callBapi_Commit();
              returnMsg = wdThis.wdGetCCreateCustController().wdGetContext().currentOutputElement().getReturn();
              if (returnMsg != null) {
                   uniqueKey = wdThis.wdGetCCreateCustController().wdGetContext().currentOutputElement().getUnique_Key();
              wdThis.wdGetCCreateInterfaceController().wdGetContext().currentContextElement().setUniqueKey(uniqueKey);
              wdThis.wdGetCCreateInterfaceController().complete();
         } catch (Exception ex) {
              msgMgr.reportException(ex.getLocalizedMessage(), false);
         msgMgr.reportSuccess(message);
        //@@end
    When we submit the form the exception shows -1 and our message shows[Proj_num] that means execution fails before this line
    message = "three";
    Any help or if you can guide us how to debug from GP into WD we are on SP10 all the bedug documents show the debugging in SP12.
    Thanks
    Shahid

  • RE: GR Processing Time not showing in MD04 and Exception List

    Hi,
    Just a quick question on GR Processing Time.
    A sales order has been raised and delievery day is for lets say 05/04/2010. MRP runs and it creates a planned order to be finished on the 05/04/2010 but it should finish on 04/04/2010 and as I have a GR time for 1 days.
    All data is correct but it doesn't seem to give an exception message saying reschedule in for the 04/04/2010 based on the GR Lead time build in material master.
    Regards
    Adeel Sarwar

    Dear ,
    Please note that while you are Carrying out MRP in MD02 you might have selected scheduling indicator -2  which triggered Lead times Scheduling based on the sales Order Delievery date , Scheduling Margin Key Timings , GR Processing Time  with an infinite capacity (MRP system does not carry out any Capacity Avalibility check where as does it does Scheduling for Planned Order  considering infitinte capacity in WCs) .As the system calcualtes the Planned order Deleivery date based on those parametrs  with in the planning and re-scheduling horzon , so result is not exceptional from MRP scheduling ponit of view .
    Now if you re-schedule the order as per your delivery requirement date , you will get the exeception messgae as applicable in MD04.
    Otherwise , please check in SPRO-Material Requirement Planning ---Evalution -Exception Msg -Select Key  U1-MSG 10-Double click on that -Check wether the "No Exception Msg " is ticked .Remove the same .
    Regards
    JH

Maybe you are looking for