Dear Exparts,
I need a way to copy all the children materials in a BOM to the component of a service order as individual componenet. How can I do that. in configuration I could not find anything helpful. please guide.
Thanks
Subhro
Edited by: Subhro_86 on Feb 15, 2010 10:22 AM

Hi  Subhro,
I thought you are talking about the BOM material for the ref technical object say functional location or equipment in the service order. If you have maintained the BOM for the equipment you can pull the all the component list in the component tab.
In the component tab click on the List button available in the component tab. You will see the list of BOM material.
DP

Similar Messages

  • Setting for "Exploding BOM in Process order"

    Hello All,
    I have a requirement where I want to create BOM for sales order using CS61 and then I want to explode this BOM automatically in Process order(Production order) and it should happen automatically.Please let me know the settings for the same.
    Regards,
    Rohit

    Hi  Subhro,
    I thought you are talking about the BOM material for the ref technical object say functional location or equipment in the service order. If you have maintained the BOM for the equipment you can pull the all the component list in the component tab.
    In the component tab click on the List button available in the component tab. You will see the list of BOM material.
    DP

  • Explode Bom in Purchase Order without Subcontracting

    Hi Colleagues,
    I have a sales BOM to represent a 'kitted item' (Lets say TV and TV stand) that are stocked as standard individual products.
    These component level items are purchased from the same supplier
    Is there a way of being able to raise a purchase order for the BOM header and then the PO explodes the component items and quantities? We are not using subcontracting, we simply want to be able to order the Kit header and then suggest the sub components that we can receive them seperately
    Thanks
    Steve

    Hi,
    In retail there's a similar functionality called structured article:
    http://help.sap.com/saphelp_47x200/helpdata/en/2b/b03886df3611d1953b00a0c930e0da/frameset.htm
    ...but in standard SAP you have no such option - as per my best knowledge.
    Generally, you get PurReqs during MRP run and you will create a PO from several individual PurReqs that belong to one vendor.
    Other option is to copy the same PO (that already contains the components).
    The BOM function in PO is for subcontracting exclusively as I know.
    Regards,
    Csaba

  • Material BOM explosion in Service Order components

    Hi experts,
    I created a Material BOM with transaction code CS01.
    Then I try to add this BOM in the component of a service order.
    What I expected is the BOM to be exploded in the service order. But this behaviour doesn't occur.
    Do you know what I can do to trigger a Material BOM explosion at service order level.
    By the way, the BOM is not exploded after the service order (in the reservation or in MIGO).
    Thank you for your help.

    Hi Özgen,
    Thank you for help.
    Special Procurement 50 didn't exist in my system.
    I created it in SPRO for the plant with the Procurement Type F (External Procurement) and the flag Phantom Item checked..
    Then I created
    - Material A (MM01)
    - Material BOM A (CS01) with:
    -- item 1 Material B (which has Spec Proc Type 50 in MM02-MRP2)
    -- item 2 Material C (which has Spec Proc Type 50 in MM02-MRP2)
    After that I created a Service Order (IW31)
    I put Material A in the Component tab with quantity 1.
    The BOM remains unexploded.
    Did I miss something?

  • Explode materials in  SD order

    Hello!
    I want to explode Bom in sales order, and for few customer i need to add material automaticly in any metod(free goodqitem determination/product det').
    can i do thet.
    thanks for your help
    shay

    Hi Shay
    BILL OF MATERIAL
    The Material Ordered, Delivered and Billed consists of one or Several Components.
    These components are called as Bill Of Materials
    The Material Ordered by the Customer is referred as Main Item or Higher Level item. The Components are referred as Sub-items.
    When we enter the Main-item in the Sales documents, the Components are automatically determined and this is called as expansion of Bill Of Materials.
    In SD, we treat the processing of Boms in two ways.
    Processing at Main-item.
    Processing at the Sub-item
    The Processing in both cases is controlled by the Item Categories and Schedule line Categories.
    Step: 1
    Prepare the Martial Master for all the Materials, which is main-item and Sub-item.
    In the Material Master, the Item Category group of the Main-item is important.
    We need to Maintain the item category group for the Main-items and sub-items as follows.
    Scenario Main-Item Sub-Item
    Processing at ERLA NORM
    Main-item level
    Processing at LUMF NORM
    Sub-items
    Item Category TAQ TAE
    Schedule line CP CT
    Category
    Step: 2
    Let us take Computer as a Bom. It has Varies parts like Mouse, keyboard, Motherboard, Ram, CPU.
    Let us take Computer has the main-item, and sub-item as the rest.
    Prepare Material Master. We have to Prepare Material Master for Main-item and Sub-items.
    T-Code: MM01
    First Prepare for Computer which is the Main-item.
    In Sales: General/Plant. Maintain ERLA in the Item Category Group
    Then Create and Save the Material Master
    Step: 3
    Create Material Master for the Sub-item. That is for Keyboard, Mouse,
    Motherboard, Ram & CPU.
    In Sales: General/Plant. Maintain NORM in the Item Category Group
    Similarly Create Material Master for the rest of the Sub-item and SAVE.
    Step: 4
    Create Material Bom.
    T-Code: CS01
    Enter the Details
    Material no: xxxxxx
    Plant: xxxxxx
    Bom Usage: 5
    Then Enter
    Step: 4A
    A screen will pop-up. Enter the details of Components such as:
    Mouse , keyboard, Motherboard, Ram etc, in the screen
    Then SAVE
    Step: 5
    Create Condition Record.
    T-Code: VK11
    Maintain Pricing for only the Main-item.
    Maintain Pricing only for Main-item.
    Thas is Computer.
    Then SAVE
    Step: 6
    Create Sales Order
    T-Code: VA01
    Enter only the Main-item.
    Then ENTER
    Step: 7
    The Bom Explodes
    Bom Explodes with the Sub-item.
    Pricing is done only for the Main-item.
    Then SAVE
    Step: 8
    Create Delivery
    T-Code: VL01N
    Picking is happening only for the Main-item and not the sub-item
    Then SAVE
    Then do billing.
    Reward if helpful to u

  • BOM component in service order

    Hi guys,
    I have plant A as a maintenance planning plant for plant B and C and equipment 123 in plant B.
    Can I create an equipment BOM in maintenance planning plant A and when I explode the BOM in my service order, it will list out the components to be drawn out from plant B?

    Dear Sir,
    Can U tell me is It Right method to adopt the BOM to Order ?
    In order- components tab - list is there, when i click on that, the particular BOM - materials are Viewed, and  i double click  , the materials are transported to the order . is it right method.,
    In pp order all materials in BOM are Transfered to Production order.In maintenance order is not that such scenario?
    Regards
    SMC

  • Prod Order Type - do not explode bom

    Hi Gurus,
    Can we set a certain order type not to explode bom at order creation? Thanks for the advice!
    Regards,
    Manoj

    I thnk you may create an alternative BOM which does not contain any components and select it for the order type, please go to customization OPL8, there is a field for BOM application for certain order type.
    Then, go to customization Production > Basic Data > Bill of material > Aternative determination, there are 3 transactions for determining BOMs associate with BOM application (e.g. selection ID etc), please try if you can confirue them to have the system select the alternative BOM.

  • How to re-explde the BOM in Sales order

    Dear Friends,
    In sales orer there is any provision to Re-explode the BOM in sales order.we have make some changes in BOM.Now we want to re-explode the BOM in Sales order so that BOM Components can be available in sales order.
    There is any field available in sales order for that?
    Please relpy.
    regards,
    NITIN

    Dear Nitin,
    go to VOV4 do this confioguration for item catagory determination.
    ZB01     ERLA               TAQ
    ZB01     ERLA          TAP     TAE
    ZB01     ERLA          TAQ     TAE
    ZB01     NORM               TAE
    ZB01     NORM          TAN     TAE
    ZB01     NORM          TAP     TAE
    ZB01     NORM          TAQ     TAE
    here ZB01 is the order type
    now you can see we used three item catagory TAP , TAQ and TAE
    TAQ is the first level TAP is the second level and the final level is TAE.
    now  for multy level explosion go to your item catagory
    and go to bills of material tab in the field "structure scope" select "B-Explode multi-level bill of material"
    then do a transaction and check
    Regards
    Subrat
    Edited by: subu sd on Apr 2, 2009 1:11 PM

  • BOM at Sales Order

    Dear All,
    My client have 3 material, contract is created with material one, but on sales order level when i call material one, system should explode BOM, and shows second and third material, price is only applicable with material 2nd and 3rd, no price with 1st material.
    Can you pls advise that which item category I should use for material master.. and or what areas further need to be configure...
    Looking for the feedback..
    Rgds,

    hi,
    Youcan use TAP, TAN for sub it Level pricing anf at main item level pricing you can use TAQ,TANN.
    AND CHECK IN TAP AND TAQ  That is there structure scope and application  in the BOM section is configured.
    and configure the sub item  sales item category as
    for pricing at sub item level
    sales document type-item category group(lump)-usage-higher item category[TAP]- TAN
    pricing at main item level
    sales document type-item category group(lump)-usage-higher item category[TAQ]- TANN
    you will get this in sales order
    go to Or  add the main material 1 you will get material 2 and material 3 as a subitem to item
    and check the pricing whether it applies to main item or sub item
    gajanan
    Edited by: Rudrag on Feb 10, 2010 8:48 AM

  • Costing indicator in Repair Service Order

    Hi Gurus,
    I am facing pblm in Repair Service order for component cost.
    Actually the flow is creation of a Service Order automatically using Requirement type from a Return Sales Order.
    Items returned in Return Sales Order are Non - valuated & hence appearing as non-valuated in my Service Order Component tab as well (Defaulted Parent Item -->" Not relavant to costing")
    This is creating pblm to me. Whatever parts, materials I am issuing to Service order are not getting costed. Also the Costing indicator for all the components lines appearing as Not relavent to Costing.
    How I can set it Relavent to Costing for the Child items. Is this control lies in Task List/BOM setting?
    regards
    Ravi

    Spare components are not influenced in anyway by the actual repairable equipment. Pls check other settings.

  • Unable to view Spare Part Components in SAP CRM Service Order

    Hello All,
    We are implementing CRM 7.0 Ehp 2.0
    As per the following video it is now possible to integrate the spare part components in the CRM Service Order, using the BOM replication and Product Proposal functionality in SAP CRM
    SAP CRM 7.0 - Integration of ERP BOM Information in the CRM Product Proposal
    However in our case we are not able to achieve the desired results.
    Following configurations are done
    1) The BOM is replicated from ECC to CRM the same can be viewed in commpr01
        Material 4561 is the main product and 4562 is the component
    2) The item category for the main product is YRVS where the customization for structure scope is done
    3) For the Product Proposal customization's, I have created a new method schema
    4) The transaction type and the sales org are assigned to the method schema
    5) However now when I am creating the service order, I enter the sold to party, the product id
    6) Next  I go to the line item to click on product proposal.
    7) The system issues the below message
    Please advice if I am missing on any configurations.
    Kind Regards
    Atul

    Hi Raghavendra,
    Thanks for your reply, appreciate the same, I have now added the relationship objects as per your post above in comm_hierarchy for the particular category
    Now  in the product master , I am now able to view the tabs(screen shot attached)
    Next I create my BOM in ECC with BOM Usage 5 and save the same
    Next I run the initial download for the adaptor object  BOM in SAP CRM
    When I check in commpr01 for the material 4561 the component and the main material have not come.
    Can you please advice further.
    Kind Regards
    Atul

  • Explosion of BOM In sales order

    Hai Techies,
    I have a clarification in the BOM explosion in sales order. How to make the setting for the first or second level of  BOM to explode in the sales order? If we do so can we change the respective BOM in the sales order and save it specifically for the particular sales order.
    Can any one help me with this please?
    thanking you all in advance.
    Regards,
    Gopalakrishnan.S

    Hai thanks,
    But the client don wanna use the variant configuration concept. But if we use the standard configuration can we change the first level or second level of BOM in the sales order like editing a particular material with a new material in case of non standard products.
    For Example
    The material  Car is the header material
    CAR
        - Engine
            --Component 1
            --Component 2
            --Component 3
       - Tyres
       -Chasis
    Can we make the sales order for the car to explode the first level of BOM and by selecting the Material Engine can we edit component 1 with component 4
    I have enabled this with variant configuration concept. But now the situation wants to use this without variant configuration.
    Can any one please help me on this?
    Thanking you in advance.
    Regards,
    Gopalakrishnan.S

  • Actual cost is coming zero in service order

    Hi experts
    I am newer in CO.i can not recognise that "Actual cost is coming zero in service order".Please let me know that sollution
    thanks in advance
    sachin

    Have the cost data been archived? If not, please check configurations and whether there is do actual goods issue or activity confirmation posted. Check plan and actual costing variant under tab page 'Control', BOM structure under tab page 'Components' and Routing structure under tab page 'Operations'. And if any goods issue or activity confirmation to the order, cost can be analysed under tab page 'Cost'.

  • Concept of Alternate BOM in Process Order.

    Hi,
    We are having Process order Scenario & we watn following options.
    1.       Having 2-3 BOM of the same FERT/HALB with alternate Raw Materials.
    2.       Selection of Specific BOM for Process Order depending on the Availability / Requirement.
    3.       Creating Issue Slip / Reservation for the Specific BOM.
    4.       Issuing Material accordingly.
    5.       Booking consumption accordingly.
    Thanks in advance.
    DON

    Dear
    Please find below the answers of your question ;
    1.Having 2-3 BOM of the same FERT/HALB with alternate Raw Materials. ; Goto CS01-Enter Plant-Enter Material -Enter Usage and List down all the items in frist Alternative .Again to create Alternative 2 and so on , you need to go CS02 with same menu path -System will automatically take the Alternative 2  or you can copy Alternative 1 if you have similar items with additional new items..
    2. Selection of Specific BOM for Process Order depending on the Availability / Requirement ; As far as MRP is concern , BOM selection  and explosion of BOM for depdent , needs to have BOM Selection methods  Blank , 1,2,3 in MRP4 view .If you have maintained Producton version with all those aternative  with proper validity and lot size , then MRP will explode as per lot size and valididrt depeding on the order qty  or you can also create demand MD61 with Production Version based on the avalabity of BOM [MD61-Enter User parametes -Scheculie Tab -Goto Settings-Production Version -Enter PV with spefic BOM based on availablity ]   and then run MRP in MD02-NETCH ,3,1,1,3,2 .Howver , you can also select this production version manually while creation of Process order  based on the Order Type Depent Parameters in OPL8-Select Process Order Type-Goto Detals-Here Master data tab -Select Production Version -Keep it 1-Manula Selection .Remember , as sequence , MRP will select the frist PV listes in MRP4 view of Material master if it does not find proper lot size and validity.
    3.Creating Issue Slip / Reservation for the Specific BOM. ; Generally , MMD/Store will be given Reservation Number  and they will chekc in MB51 for open reservation for Goods Issue and carry out MIGO-261.Frosm Shop Fllor you can try Pick List  or you can print Process Order Print out in COP1 or MD4C print out also .Otherwise develope customs Forms as per the information permissible from you business to store .
    4. Issuing Material accordingly.; It will happen in MIGO-261 or automatcally based on Backflkashing in MRP2 view -Always back flash so that at the confirmation time in co15/c011 , you can automatically goods issue the material .
    5.Booking consumption accordingly ; It is Process Order Cycle from Releasing of Process order to till Goos Recipt of Process Order in MIGO-101.You can also use Auto GR based on the Control Key set up in Master Recipe which triggers the Auto GR.
    Regards
    JH

  • BOM in purchase order

    Hi experts,
    Is it possible to use the BOM in purchase order? In the sense, if material a = b + c, then If i create the purchase order for material a, it should explode to b and c as the BOM explodes in a sales order.
    Please let me know if this possible? And if yes, then how to go about it? If no, what is the reason we cant use it in PO?
    - Prashant

    Hi,
    Please check the following things :
    1. In Material master MRP4 view - Field "Individual/Coll" should have value "2" or "Blank" & In BOM (Transaction code CS03) item detail section - Field "Explosion Type" should have value  "LB" ("Individual/Coll" should have value "2" or "Blank") .
    2. PIR should have PIR Info category "3" , i.e., Subcontracting PIR must available for header material which we receive back from subcontractor.
    3. Special Procurement Key must be "30" in material master MRP2 View.
    4. Purchasing Item Category must be "L" and production BOM must be maintained, if you want to explode BOM in PO.
    5. Please check BOM valid period is effective from in Tcode cs03 
    6. Please check your PO date against the valid date of the BOM valid period.
    regards,
    Siddharth.

Maybe you are looking for

  • BIB-16633 Cannot connect because the database version is incompatible with

    BIB-16633 Cannot connect because the database version is incompatible with Feb 15, 2005 9:28 PM Reply why is this? oracle.dss.connection.common.ConnectionException: BIB-16633 Cannot connect because the database version is incompatible with this BI Be

  • Applet in a Tomcat and Tapestry web application

    hope this is the right forum... My problem is that I have an applet (as a jar file) which needs to have access to other jar files. My relevant project structure looks like this: context |--res ...|--applets |--WEB-INF ...|--lib So the jars the applet

  • Compressor 3.5 "Submit" button inactive

    Hi Everyone, The Compressor (3.5version) "Submit" button is inactive when I try to compress an external .mov file or a file from the timeline. I recently installed Final Cut Studio 3 (FCP 7) keeping the 6 version as well. When I try to use old Compre

  • Proxy object to consume web service

    Hi, I want to consume a web service in ABAP (on a WAS 7 box) and have read many blogs/posts about using a proxy object. I've gone to SE80 and selected create a service consumer, enter the URL for the WSDL. The generation of the proxy fails with the f

  • Get One to One relation information from SMO

    Hello I have 2 tables. Business & categories. Both are connected using one to one relation. In business table I created ForeignKey relation to Category & then I made CategoryId column of Business Table Unique Key in index. In this way I create One to