F-90. asset value date field is not displayed

Dear all
In asset acquisition posting through F-90. asset value date field is not displayed at the time of entering acquisition. It is in supress mode. so system is capturing the capitalisation date. But we can see this capitalisation date as asset value date in fb03 display. Now i want to display this field as optional field while creating the entry and also i want to change the field in display mode to change mode. kindly tell me the menu path to access the settings.
Thanks With  Regards
RSS.

Hi,
You can enter a diff asset value date for your acq posting, only thru transaction ABSO using TType 100.
This will resolve your issue.
Thanks,
Srinu

Similar Messages

  • FA-retirement-Asset value date and posting date are not in same fisc year

    Hello,
    I would like to post retirement in the new fiscal year but with asset value date in the previous year so that NBV is calculated correctly. It is not possible neither in ABAON nor in ABAVN with any transaction type.
    I always get message 'Asset value date and posting date are not in same fiscal year'.
    Is there any way how to handle this?
    Thank you,
    Jan

    Hi,
    I have tried this but the settings of our Depr keys works in the way. That if you use asset value date in the new month it will calculate depreciation for the whole month.
    This means if I retire with asset value date 31.12.2008 - NBV will be calculated as at 31.12.2008.
    If I retire with asset value date 1.1.2008 - NBV will be calculated as at 31.1.2009.
    Thank you anyway!

  • Asset value date and posting date are not in same fiscal year

    Hi,
    Our business user has created an asset under an incorrect asset class, which he is trying to transfer to a new asset whcih was created under correct asset class. However system is restricting user with the error message "Asset value date and posting date are not in same fiscal year". Can you please advise me how we can proceed further with this error.
    Regards,
    Asam.

    Hi,
    To transfer one asset to another asset within a company code can be done through ABUMN only.
    While doing this transfer you have enter the document date, posting date, and value date for the transaction, but all these dates should be in same fiscal year only.
    In your case you must have been entered the dates for asset value date and posting date , and these two dates are in diff financial years.
    Please make sure that both the dates are in same FY.
    Hope this will fix your issue.
    Thanks,
    Srinu

  • Asset Value Date determination during settlement from Orders or WBS!

    Hi,
    I have a scenario on the asset value date and I am not sure what went wrong, asset side or CO side.
    The scenario is as following:
    1. Asset was converted into the system by 7/31/2008 with $10000.
    2. The capitalized on date is 2/29/2008 on the asset master data.
    3. On 8/31/ 2008, I charged $300 to an internal order and settled the $300 to this asset. The Asset Value Date on the Asset Explorer is 8/15/2008.
    4. On 9/30/2008, I charged #500 to the same internal order and settled the $500 to this asset, the Asset value date on the asset explorer for this charge is still 8/15/2008.
    This messed up the depreciation of this asset. Does anyone know how to control the asset value date from the settlement? Do we need to config in Asset side or in Order side? I want the $300 charge's value date is on 8/15/2008 and $500 value date on 9/15/2008. Is this possible?
    Thanks,
    Ting

    In the settlement you can fill in the asset values date.
    The first posting is the basis for capitalization date(when you don't fill it in manual), when you fill it in for the second time the Asset Value Date it is no longer relefant.
    This is only important when you have say in your depreciation key that the depreciation is based on days( see the help on this field)

  • Asset Value Date - Wrong posting

    Dear All,
    Company code is on live, Assets legacy data taken as on 31st-March-09.
    Later we find that some of the assets [new purchases, in previous fiscal year (2008)] was not posted.
    For that recently we posted that transactions F-90 using posting date is current date and document date is Actual acquisition date.
    Due to document date in previous fiscal year system taten posting date as asset value date.   So, depreciation posting missing for previous year.
    I need your help.  How can I rectify this???
    Other than reversing the existing posting, what is the scenario????????
    Thanx
    Regards
    partha

    Hi,
    In order to post ,post capitalization please closed the previous asset accounting year.In ABNAN T.Code screen please update the original val date field with the date  of the previous year from where you need to start calculating the dep. Doc date and posting date should be of the current FY.Also check T.Code Ao90 for updating the field Revenue from post capitalization with proper GL Account.
    If your statutory audit for 2008-09 is not yet completed then you can think about T.Code AS91.While  using T.Code ABNAN the following line items are generated.
    Asset        dr
    Acc Dep         cr
    Rev form post capitalization cr
    The system will only calculate dep of previous year.For the current year dep which are yet to be posted will be posted in the next schedule dep posting run.
    Thanks
    Monoj

  • Asset value date in Internal order settlement ko88

    Hi.
    I have posted some expenses to the internal order. I m trying to settle it to AUC with tcode KO88.
    In the selection screen of ko88 i gave asset value date as 15.07.2011 but system is posting with month end date only as 31.07.2011.
    I read the sap note 98496. In that its mentioned that the asset value date given in settlement parameters will override the asset value date given in the selection screen of ko88.
    I tried to update the AUC asset value date in KO02 where we give settlement rules but i couldnt find any field there.
    Where do i update the AUC asset value date in settlement parameters. Can anyone provide me the tcode and the field where i update this asset value date.
    Regards,
    Padmavathi

    Hi
    You can the same in transaction code KO02 
    1. Click on 'Settlement Rule'
    2 Select 'Goto' in toll bar
    3.Select 'Settlement Parameter F8"
    4 there you will get" Asset value date"
    Table  Name" COBRA" field "BZDAT"
    Hope this will helpful for you
    Regards
    Praveen P C

  • Visio 2010 - Shape Data Fields Are Not Saving

    I am having a problem with a number of shape data fields which are not saving data that has been entered into it, whether by entering it through the "shape data" or "define shape data" dialog boxes, or by editing the "shape
    sheet". 
    All data fields appear to save normally while file is open, it remains as entered.  However, when file is closed and later reopened select data fields do not retaining data correctly.  Some retain nothing (null), or revert back to a "default"
    value, see below for a couple examples:
    Rack Units:  Want to enter data as 1U, 2U, etc. ... in some cases it will save it as entered while in other cases it reverts to "1 RU", "2U", etc.
    Room:  Enter the data as I want it stored, most of the time it appears to come back empty, there are some shapes which will retain as entered.
    Comments:  Fails to retain any data
    I have looked at a number of reasons to explain why, whether the problems occur with stencils is supplied by Microsoft, a vendor, or were custom created.   Looked into whether it might have to do with a particular vendor's stencils/drawings
    but I have a number of Cisco drawings where some save those fields as entered while others do not.  I believe it could be a setting within the stencil preventing it from saving the data as entered, enabled in some cases and not in others.
    I have checked "Protection" under the "Developer" tab, but nothing appears to be set to prevent editing/storing data entered. 
    Is there some setting(s) or field(s) somewhere that I can look at to allow this data to be saved as entered?
    Is there a GLOBAL setting that can be set once within a file?
    Thank you in advance for your time to assist me in fixing these problems. Have a great day!
    MJ_NWE
    MJ

    >Can I build logic so that they can't fill in a field unless the previous field has been filled in?
    It's theoretically possible to do this (e.g. each field has an action
    of removing read-only on the next). It's considered extremely bad form
    design, because people don't always fill in fields in the order
    specified. If you watch people with a form they fill in their name,
    address, other easy stuff; then they go back for the harder stuff.
    They may want to save a form because one piece of information needs
    research.
    What you might like to consider is a large splash "FORM INCOMPLETE" in
    Red or whatever, which vanishes when all the fields are completed.
    Aandi Inston

  • Asset Acquisition with Asset Value Date earlier than GI post.date

    Dear all,
    I am curently using SAP ECC 6.0. We are not creating AuC assets but directly capitalizing assets from investment accounts.
    If a material is issued with a date in March and i try to acquire it with asset value date from a previous period, for example in February, the system doesnt issue any message and lets me post the transaction. The accountants claim that this hadnt been possible in the earlier version of SAP 4.6 that we had been using and that the system had issued an error message - "Posting not possible (Value date earlier than capitalization date)"
    The accounting logic is that you cant capitalize an asset with a date earlier than the date when it has been in use, i.e. in our case it`s the date the material has been issued from the warehouse.
    Does someone know what logic does SAP follow in this case - and if i can set a validation control that will check and compare the two dates?
    Any opinion would be appreciated
    KR
    Severina Koleva

    We are on ECC 5.0 and we do get that message, but it is a warning.
    AA348...
    that said, you can setup a validation using GGB0 and asset accounting

  • Asset value date

    Hi Guru's
    I have uploaded asset with  capitalization date is 02.07.2008 the i have uploade the data with the posting date 02.10.2008, the depreciation is calculated from the period 02.10.2008 and not fromt the capitalized date
    can one let me know please?the depreciation calculate from teh date of acuisition or from teh date of posting date?
    regards
    Sunitha
    Edited by: sunitha reddy on Mar 3, 2009 4:26 PM

    hi thanks to all.
    my situatui is littlebit different. normally capitalization date will take with end date of  the asset. in my case asset value date, capitalization date and aquisition date and dep start date also same.but as per these date when we compared with end date the asset useful life should be 10.3 yeaes but i has calculated as 10.1 from the posting date of the document
    now i want change teh asset useful life for 10.3 year in master data, how can i change it in mass? and what are the implications?
    thanks
    sunihta

  • Asset Value Date in Settlement

    Hello!
    We would like to settle investment measure to a completed asset, so the settlement rules have been updated with the completed asset, status of the order has been changed to TECO (technically complete).
    When we settled the order (not via u201Cko88u201D but via automated program which uses our client) it turned that out asset value date is different than posting date, so the system takes the date when investment measureu2019s status has been changed to TECO instead of posting date, as asset value date.
    Would anybody know where and how to change config, so asset value date is the same as the posting date?
    Thanks in advance for any hints.
    Regards,

    Hi,
    Are you looking for below mentioned settings...
    Financial Accounting (New)->Asset Accounting->Transactions->Specify How Default Asset Value Date is Determined
    Best Regards,
    Madhu

  • Asset Value date in KO88 Settlement type=FUL

    We do KO88 for Settlement type=PER and the posting date and value date are the end of the month.
    But if we do Settlement type=FUL the posting date is end of the month and Asset value date is not (for the example we made it is 15/MM )
    This is wrong and the customization of the default asset value date is Posting date.
    OSS says it is consulting
    Regards,
    Alon G.

    Hi
    Check OSS Note : Note 98496 - Information: Asset value date in settlement to fixed assets.
    https://websmp230.sap-ag.de/sap(bD1lbiZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=98496
    The above not explains the logic as how the Value Date is determined during settlement.  The above not is release independent hence applies to all SAP Releases.
    Thanks
    Prasad

  • Asset Value Date & Posting Date as defaulte date

    Dear All,
    In CJ88,the posting date & value date is 31.10.2009 by default. The asset value date provided by us is 28.10.2009. The posting date & value date should be the actual date of entry (28.10.2009 in this case) by default.
    How can we do this.
    Do revert
    Regards,

    Regrettably to inform you that in R/3 standard, posting date is always 
    the last day of the period to settle as settlement is a period end     
    operation. The document date is the day when the operation is performed.
    Considering AuC is involved in this case, please check transaction CJ88,
    where you will find the field 'asset value date', where you can manually enter the asset value date you want to have.
    Blaz

  • Value date field is missing in MIRO

    Hi Gurus,
    When I insert an account in transaction code MIRO, in tab "G/L account", the system shows the follwing message error: "An entry is required in Value date field for account XXXXXXXXXXX".
    I try to create a variant to display this field but it' s impossible.
    Could you please say me how I do?
    I would insert the value date in MIRO.
    BR.
    Thanks.
    Angela

    Hi Angela,
    there is an old SAP note available regarding your issue: 391683
    It seems the value date has been removed from the MIRO dynpros. (Nvertheless, when you try to change the layout and set value date fo visible, the length of the field is 0. So no use setting it to visible.)
    But you can activate the "Define default value date" in the Company code global data (T001). So for g/l accounts with required entry for value date, the value date is filled with the system date.
    Hope this helps.
    Best regards,
    Stefan

  • Define assets value date.

    Dear experts,
    i have one problem, when i am posting f-90 of assets acquisition (giving current date) geeting one error meesage that is.
    "check assets value date" but i do not understand where i have to define this assets value date what is relation with f-90.
    pls tell me the t-code so that i can define.
    pls reply me.
    Bikash.

    HI Bikash,
    Asset value date is to be specified by the user, it help to determine the quantum of deperciation for specific period. You can get more understanding on asset value date by following the link given below:-
    [SAP Help (FI-AA)|http://help.sap.com/saphelp_erp60_sp/helpdata/EN/4f/71e122448011d189f00000e81ddfac/frameset.htm]
    Just write back to me if you have any doubts.
    Regards,
    Anand

  • Value date field BSEG-VALUT

    i want to populate BSEG-VALUT field at customer line item when i am using FB01.But i can populate only at GL account line item.Can some one tell me how can i populate Value date field at customer line item.I checked all the field status groups and its still not showing up.
    Regards,
    Nettem

    Hi Nettem
    this field will be taken from the field status of the reconciliation account. So check the reconciliation account in the customer master data and then the field status group on this gl account. This should help you to find out.
    please assign points if useful
    rgds Adi

Maybe you are looking for