Factory calendar (Sunday-- work day)

Hello!
That may have implications  in the factory calendar, if I put sunday as work day? what implications can I have?
Thanks

Dear
That may have implications in the factory calendar, if I put sunday as work day? what implications can I have?
From MM/PP standpoint :
1.MRP will consider this in calcualtion of various dates ( Delivery Dates , Planned Dates , Rlease Date of PR/PO ) of procurememnt prposal if you do not follow any planning calander in MRP2 view exclusively
2.All the planned order , production order  will be  having schedule , basucs dates considering thif FC as per work centre set up if the wc does not have seperate calander in CR02-WC-Capacity -Detail capacity tab .
3.You can also recieve PO , STO  etc on  this days becasue it will be working days .
From SD stnadpoint : You can have Invoice , PGI , Sales Order Delivery date inlcuding this set up  if you follow this calander at your shipping point level .
refer this therads for farther cheks at vaious level : Public holiday dates issue
Regards
JH

Similar Messages

  • Factory Calendar and Work Center

    Dear All
    I am confused between factory calendar and work center working.  Kindly guide me what factory calendar does and what work center does?

    Hello,
    Factory Calander :-- Factory calendar contain company specific dates such as alternate working Saturdays, Plant shutdown etc.
    You can create your company factory calendar via transaction code 'SCAL'.
    Assignment of the factory calendar by plant is done in transaction code 'SM30 - V_T001W'.
    An example of a SAP application that uses the factory calendar is the SAP MRP modules.
    Assuming that you have a specified an alternate working Saturday, MRP will postponed the planned orders to the next working day if it happened to falls on a non-working Saturday.
    Work Center :--
    Operations are carried out at a work center. In the R/3 System work centers are business objects that can represent the following real work centers, for example:
    Machines, machine groups
    Production lines
    Assembly work centers
    Employees, groups of employees
    t-code-- CNR1 - Create
    for more information go to this link
    http://help.sap.com/saphelp_smehp1/helpdata/en/40/8ac473d40943ddb23def12bdb33437/content.htm
    Thanks

  • Team Calendar non-working days

    Hi Gurus,
    Is there a way we can configure the team calendar to show non-working days for the employee (public holidays, days off in part-time/shift work-schedules) in green for example?
    I haven't seen any configuration options for this, but I would expect it to show them somehow!?  Will we need to do custom development for this?
    Many thanks,
    Russell.

    Hi Russell,
    You can check this<a href="http://help.sap.com/saphelp_erp2005vp/helpdata/en/2f/d7844205625551e10000000a1550b0/frameset.htm">SAP Help</a> for additional info on the Team Calendar iView..
    ~Suresh
    Russell,
    I didn't think the "10 points offer" was open to all.. ideally, it should be to Duxton only.. You could probably open a customer message in OSS & seek SAP's clarification on Team Calendar
    Message was edited by: Suresh Datti

  • Time stream and Factory Calendar settings issue. Problems in scheduling!!

    Hi,
    We have a factory calendar of working days from SUN-THU only (5 days a week).
    Every working day starts at 07:00:00 (first shift) and ends at 06:59:59 at the following day.
    I am not sure how to set the time stream. Do I set it for daily (5 days a week) with gaps start at 07:00:00. Or, as the standard way as daily (all days 1 -7) 00:00:00 - 23:59:59 without gaps.
    We are using the planning board to schedule production orders that were created in ECC, but we see that we have problems with date corelation between the systems, and we think it is due to some wrong setting of the time stream!
    Thanks for your replies

    Hi,
    For scheduling, the time stream of resource is relevent. As to how to generated the time stream, it depends on your resource capacity setting and your factory calendar. I'm not sure why your factory calendar starts at 7:00:00 daily. For the time steam of the resource, it should be ok to start at 7:00:00, and you mayexecute the time stream generation (ta. /sapapo/rest02) to save the time stream in LiveCache.
    Claire

  • MC44: material usage value affected by factory calendar

    Hi Gurus,
    I've got the following problem: on my 4.6c R3 production instance factory calendar had been setup as 7 working days a week but recently the need was to change it to 5 working days a week due to the introduction of route calculation to determine correct dates for the sales orders.
    We changed the factory calendar (which did deliver the correct result for the sales orders) only to discover that the "Usage" value determined for the materials by MC44 got totally wrong (usage with the 5 working days calendar was approximately 30 to 50% LESS than with the 7 days working calendar !!)
    As soon as we did restore factory calendar back to 7 working days a week MC44 was again fine (obviously sales orders date got wrong...).
    My impression is that everything is based on the way data from table MVER is determined depending on the factory calendar (which is apparently driven by function module DATE_CONVERT_TO_FACTORY_DATE).
    I guess I could change from customizing the calendar for the shipping point: in that case my expectation is that sales orders date should be fine as well as results from MC44 but I'm not totally sure about that.
    Any idea ?  Do you know which is the way table MVER is populated based on the calendar settings ?
    Many thanks in advance for your help.
    Enrico

    Hi Jurgen,
    from the logical point of view sounds reasonable but....
    1) even if I didn't fully debug the program (otherwise I guess I would know the answer   )  looks like MVER is the only one considered in terms of usage
    2) even if you forget point 1 (I could obviously be wrong) you're missing one information that I didn't mention: our usage (or consumption if you prefer) is 98% done from Monday to Friday; sometimes we do something on Saturday but this is kind of an exception.
    Based on the above, despite the factory calendar is setup on 7 working days a week, our material usage is basically done on 5 working days a week.  Described this way you'll immediately understand that, even if the program reads the data based on the number of working days, changing the calendar from 7 to 5 should cause a decrease of only 2-3%, in our case changing the factory calendar from 7 to 5 working days is causing a decrease of 30% to 50%.
    I believe the program is reading the table in a different way based on the factory calendar, I'll try to give you an example:
          Day     Usage
    01   Mon       10
    02   Tue        20
    03   Wed      30
    04   Thu        40
    05   Fri          50     ---> total week 1 far 150
    06   Sat         2
    07   Sun        0      -
    > total of the weekend 2
    08   Mon       100
    09   Tue        200
    10   Wed        300
    11   Thu       400
    12   Fri        500     -
    > total week 2 1500
    13   Sat        6
    14   Sun       0        -
    > total of the weekend 6
    For the 2 weeks, factory calendar 7 working days a week, total usage would be 1658.
    In your case, switching to 5 working days a week, it should deliver usage only for Monday to Friday, which is 1658 - (2+6)=1650    (i.e. difference is peanuts)
    As I said, I couldn't get to the end of the debug, but my impression was that, switching to 5 working days a week (based on the above example) the program would read 10 "days" so from Monday 01 to Wednesday 10, in that case the total would be 1658 - (4005006) = 752  (now difference is huge...).
    So......  maybe main question could be: which is the way MVER is populated ?
    Best regards,
    Enrico

  • Factory Calendar vs. Intervals and Shifts

    Experts,
    I have a question in regard to Factory Calendars & Intervals,
    Factory Calender W7 determine seven work days per week from Mo.-So.,
    Factory Calender W5 determine five work days per week from Mo.-Fr.
    1) Setting in CR12, Factory Calendar W7, Interval incl. shifts from Mo.-Fr.
    With this setting the system counts five days for the In-Houese Production Time via scheduling if Queue Time are scheduled over Sa.,So.
    2) Setting in CR12,Factory Calendar W5, Inerval incl. shifts from Mo.-Fr.
    With this settings the system counts two days for the In-Houese Production Time via scheduling if Queue Time are scheduled over Sa.,So.
    my assumbtion is that the calculation of work days for In-House Production time foots on the amount of work days in the Factory Calendar and the Factory Calendar must be alligned to the days determind in the Interval to get a correct result.
    In our system we run Intervals on a weekly base and we change shift incl. or excl. Sa. and So. on a weekly base too. Unfortunatly I can set only one Factory Calendar per Work Center in CR12, that effects the amount of work days per week.
    So is there a way to determine the amount of work days based on the days determinede in the Interval, or align the Factory Calender to a Interval ?
    What are the comon setting for such cases?
    Thanks in advance
    Jörg

    Dear,
    Please refer my reply from this link which has adress the same issue.
    [Factory Calendar and working days|Re: Capacity schedulling using calendar with man-hours per day/per work center]
    Hope it will help you.
    Regards,
    R.Brahmankar

  • How to define just every month's 10th and 20th as the factory calendar?

    Dear professor:
    I want to define every month's 10th and 20th as the factory calendar's working days.and all the other days are holidays?

    Please try this link
    http://**********************/2008/09/factory-calendar-for-plants.html
    Regards,
    Nitin

  • System see sunday is not working day

    Hi guru,
    i maintain both factory calendar and holiday factory as 7 working day per week. and in work center's master view capacities select maintained calender 's id.
    when create production order, I select scheduling type as "only capacity requirement" and select finish date at Sunday. when scheduling order, system warned me as Finish date is not working day and postpone finish date to next day. 
    suggest me if there any thing i miss?
    point of useful answer.
    Regards
    Kittisak

    Dear,
    Please check thein SCAL factory clander as sunday (that particulat Date) as working day on production client?
    Then check factory assigment to plant OP03 and to work center CR02?
    IAre you using the shift sequence the check it have you given sift on sunday also in OP4A.
    Regards,
    R.Brahmankar

  • Carrying scheduling cosidering all 365 days are working days

    when I am carryying out scheduling for a process order in which resource is assigned with 365 days as working days calender, it is displaying saturday  and sunday as non working days and no operations being planned on those days. Even plant is assigned with factory calender 0f 365 working days. Can you please anybody let me know what may be the problem.

    Dear,
    Factory calendar is maintained in SCAL transaction and assgined in the capcity tab in resource. or Whether you have maintained the shift sequence in resource?. ie for each dates have you maintained the shift pattern with all days are working days.
    Please refer thess threads for details,
    Re: change the Factory calendar in work center
    Re: Factory calendar in work center
    Regards,
    R.Brahmankar

  • Working day

    Hi all, I have a situation that reference to working factory.
    My working day is begin at Monday to Friday Saturday and Sunday is off. But in some case, I want to specify some of saturday and sunday is working day for some week to satisfy customer requirement.
    How I do it, thanks all
    Regard
    Vu Pham

    Dear
    You need to create the Factory Calander with Special rule where u need to include the Sunday as Off-days.
    Let me explain you ,
    U have to create(SCAL/OP03) a factory calender with 6 work days along with your Holiday calander .
    Now, SAP Factory Calendar allows companies to key in their own factory work days. Individual SAP application such as MRP will take into consideration these individual factory customizing.
    Now goto OP03>Select Factory calendar >Select change mode -> Select Special Ruels
    Inseret Valid from and Valid to daye  with spefic date rage  and do not mark WorkDay check box .
    Re: Release Date /Planned Opening  Date is not correct
    Hope this is clear
    Regards
    JH

  • Reg factory calendar

    Dear Gurus,
                        Here in our client place they have assigned the factory calendar for 5 days a week..since they are working 6 days a week, I need to change it. Kindly suggest me how to change the calendar for 6 days a week. Thank you.

    Hi,
    Go to SCAL
    Select Factory calendar,
    Select Factory Calendar ID relevant to you / your client
    tick mark as per the requirement.
    Hope this should be useful.
    Regards,
    Suresh

  • Working days between two date fields and Changing Factory Calendar

    Hi,
    I have to calculate working days between two date fields excluding the weekends and public holidays for Switzerland.
    I have written the routine using factory calender and its working fine except for two problems now:
    1. If any one of the date field is empty then teh rsult should be zero.
    2. And the below code is working from 1996 but my cleints wants it to work for years before 1996 as well.
    I also tried to change the Start date in SCAL for factory calendar but it says enter values between 1995 to 2020.
    I am new to ABAP. Please help me how i can achieve these for below code.
    DATA: IT_HOLIDAYS type TABLE OF ISCAL_DAY,
          IS_HOLIDAYS TYPE ISCAL_DAY.
    DATA: T_DATE TYPE SY-DATUM,
          P_DATE TYPE SY-DATUM.
    DATA : X_DATE(4) TYPE C.
    DATA: CNT TYPE I.
    REFRESH : IT_HOLIDAYS.
    CLEAR : IT_HOLIDAYS.
    T_DATE = SOURCE_FIELDS-/BIC/ZCCCHP812.
    P_DATE = SOURCE_FIELDS-/BIC/ZCCCHP810.
    CALL FUNCTION 'HOLIDAY_GET'
    EXPORTING
    HOLIDAY_CALENDAR = 'CH'
    FACTORY_CALENDAR = 'CH'
    DATE_FROM = P_DATE
    DATE_TO   = T_DATE
    TABLES
    HOLIDAYS = IT_HOLIDAYS
    EXCEPTIONS
    FACTORY_CALENDAR_NOT_FOUND = 1
    HOLIDAY_CALENDAR_NOT_FOUND = 2
    DATE_HAS_INVALID_FORMAT = 3
    DATE_INCONSISTENCY = 4
    OTHERS = 5.
    DESCRIBE TABLE IT_HOLIDAYS LINES CNT.
    X_DATE = T_DATE - P_DATE - CNT.
    RESULT = X_DATE.
    Please help
    Regards
    Zabina
    Edited by: Syed786 on Nov 2, 2011 9:15 AM

    Hi Zabina,
    Try this function module  'DURATION_DETERMINE'.
    Give the factory calendar and unit as DAY
    With regards,
    Rajesh

  • Working day to factory calendar date

    Hello Experts,
    I wish to get the factory calendar date, specific to a factory calendar, based on a working day.
    Basically, if i pass say 4, then i want to get the date for the 4th working day based on a specific factory calendar.
    Can someone throw some light on possible function module that i can use in BW ?
    Thanks

    That's what I was giving you, you give the working day and the factory calendar and you get the date, or you can use this function and you can do it the other way:
    (Unless I'm completely missing your point here...)
        CALL FUNCTION 'DATE_CONVERT_TO_FACTORYDATE'
      EXPORTING
        CORRECT_OPTION                     = '+'
        DATE                               = G_WORKAREA3-CREATEDON
        FACTORY_CALENDAR_ID                = L_S_PLANT-FACTCAL_ID
      IMPORTING
    *   DATE                               =
       FACTORYDATE                        = L_FCDATE
      EXCEPTIONS
        CALENDAR_BUFFER_NOT_LOADABLE       = 1
        CORRECT_OPTION_INVALID             = 2
        DATE_AFTER_RANGE                   = 3
        DATE_BEFORE_RANGE                  = 4
        DATE_INVALID                       = 5
        FACTORY_CALENDAR_NOT_FOUND         = 6
        OTHERS                             = 7.
      ENDIF.

  • Factory Calendar to prevent delivery on a non-working day

    Hi Guys,
    You may have already come across this problem and hence requesting your inputs on the same.
    I'm able to create a delivery for a sales order on a week-end even though they happen to be 'non-working days' in my Factory Calendar. I have gone through the search forum and the 2 things that most of them said was to attach the Factory Calendar (having Sat and Sun as non-working days) to the Plant and Shipping Point, which I have already done, inspite of which I'm able to create a delivery for a schedule line date which falls on a non-working day.
    My business scenario requires that even though a Sales Order may be created on a non-working day, the delivery should only be possible on the next working day, even if stock is available on those non-working days.
    Your thoughts/suggestions/ideas would be useful.
    Regards,
    Shripad

    Hi Shripad,
    In Customer Master, General Data , We have  Unloading Points  Option. There we can opt for the delivery to the cutomer.
    Then we can stop delivery for that day.
    Award points if it adds information.
    Thanks
    Mohan

  • Pass working day to get factory calendar date

    Hello Experts,
    I wish to get the factory calendar date, specific to a factory calendar, based on a working day.
    Basically, if i pass say 4, then i want to get the date for the 4th working day based on a specific factory calendar.
    Can someone throw some light on possible function module that i can use?
    Thanks

    I want to pass sy-datum to get factory date and then check if this factory date is the 4th busiess day for that month based on a specific calendar.
    Or if i can pass in 4th bus day for a month (just pass 4) based on a specific factory calendar (just pass calendar id), then i would want the factory date, which i want to compare against sy-datum in my subsequent logic.
    I am trying to trigger a data load stating if factory date for this month = 4th business day, then run load, else dont. And this in BW.
    I dont have the FM that you mentioned above, in BW and is available only in R/3