Suppose a particular plant wants to add 2 days this month as holidays in their factory calendar.
Before doing the actual change I want to actually check whether there are work centers in other plants in the company code which is using this calendar. How can I check this ?
Is there a where used list for factory calendar?

HI
Check Tables CRCA for capacity allocation of work center then KAKO for the same capacity id assigned to work center and Factory calender ID
Check and revert
Regards
Anupam Sharma

Similar Messages

  • Factory Calender Where use list.......

    Hi there ,
                    Can any one please tell me how can I find the places (shippping point & plants).......where any factory calender is used......
    or in short the where use list for the factory calender.......
    Thanks
    Kaushik

    Dear Kaushik,
    Fetch the data from Tables T001W (Plants) and B024 (Shipping point) based on FABKL (Factory Calendar).
    Tables related to Factory Calendar: (Field IDENT - Factory Calendar)
    TBKFK                          Factory Calendar Identification Using Currency
    TCALS                          Central entry for factory calendar
    TFACD                          Factory calendar definition
    TFACS                          Factory calendar (display)
    TFACT                          Factory calendar texts
    TFAIT                          Calendar: Text for factory calendar intervals
    Regards,
    Naveen.

  • How to find out the Factory Calendar ID used by  an Organization

    Hi Experts,
    I want to know Factory Calendar ID used by an Organization.
    Which table store the Factory Calendar information for an organization.
    Is there any function module to get the Factory calendar of an organization.
    Please help me ASAP.
    Point will be rewarded for helpful answers.
    Thanks in advance
    Kulvendra Kumar

    Hi
    chk the view v_001p_m
    there u can find ur org nization so there u wull find the calender assigned to them.

  • Which Factory Calendar is used to determine the Sales Order delivery date

    Hi ,
    There is Factory calendar assigned to sales Org and shipping point as well.
    I want to know which Factory calendar is used to determine the promise date on sales order acknowledgement and which one is used to determine the delivery date?
    Appreciate your help/inputs.
    Regards,
    Ram

    Ramy,
    I am not sure what you mean by 'promise date'.  For a given sales order item confirmation schedule, the system calculates the following dates:
    Delivery Date
    Goods Issue date
    Loading Date
    Material Availability date
    Transportation planning date.
    These dates are dependent upon what you have configured, and what your master data is.  If you have transportation scheduling turned on (IMG>SD>Basic Functions>Delivery scheduling and transportation scheduling), then the durations are:
    Route duration (transit), - affected by factory calendar assigned to the route (0VTC, that's a zero)
    Picking time, packing time, Transportation planning time, and Loading time- affected by the factory calendar assigned to the shipping point (OVLZ, not a zero)
    In addition, the Material availability date will be affected by the calendar assigned to the plant (WB03).  The calculated dates may also differ on a given order schedule line, based on whether the sales order is backward scheduled or forward scheduled.  This is particularly important when the calendars all have different holiday schedules.
    Standard SAP help on the matter, with a couple of nice pictures.
    http://help.sap.com/saphelp_erp60/helpdata/en/dd/5607e7545a11d1a7020000e829fd11/frameset.htm
    Rgds,
    DB49
    Edited by: Dogboy49 on Feb 16, 2010 5:08 AM

  • How to determine which Factory Calendar to use in BI - Help!

    Hello,
    Need some help? Any input would be much appreciated.
    Basically I am creating a query in BI 7.0 based on Utilisation for a particular business Unit. However, I need to define or incorporate somewhere, to use the GB Factory Calendar.
    I have done the normal SCAL maintenance and transferred Global settings from R/3. So all the Factory calendars have been transferred over. Our BI system is picking up the default factory Calendar as 'DE'.
    How do I now tell BI I want to use specific Factory Calendar 'GB' (Great Britain) at ALL TIMES since this is the only one we will use.
    Do we need to use a particular info object in query?
    0CALMONTH to check working days as opposed to 0FISCPER
    Many thanks in advance
    Kuljit

    Try tcode RSRHIERARCHYVIRT customizing setting - specify your factory calendar and check if it works.

  • Determining in BI or in the queries which Factory Calendar to use

    Hello,
    Need some help? Any input would be much appreciated.
    Basically I am creating a query in BI 7.0 based on Utilisation for a particular business Unit. However, I need to define or incorporate somewhere, to use the GB Factory Calendar.
    I have done the normal SCAL maintenance and transferred Global settings from R/3. So all the Factory calendars have been transferred over. Our BI system is picking up the default factory Calendar as 'DE'.
    How do I now tell BI I want to use specific Factory Calendar 'GB' (Great Britain) at ALL TIMES since this is the only one we will use.
    Do we need to use a particular info object in query?
    0CALMONTH to check working days as opposed to 0FISCPER
    Many thanks in advance
    Kuljit

    Hi Del,
        Its so easy just create exit variable , wirte a logic for finding working days. and use it in Query.
    Regards,

  • Factory calendar table update

    Hello gurus,
    An urgent requirement!!!
    I have three Source system configured in BW.
    The FActory cal id for the two systems were not found in BW.
    When i use rebuild table for the factory calendar id using transfer global setting option in the source system it updates the table but over writes it when i use the same option for other source system.
    Suggestion please
    Thanks in advance
    Ram

    Hi,
    the program doesn't admit the update on factory calendar!!
    You need an alternative way.
    I suggest two possibility:
    Transaction SCU0 to compare all the tables by RFC in remote system, (you can automate this comparison in a program) But the comparing will be for all tables:
    TCALS
    TFACD
    TFACS
    TFACT
    TFAIN
    TFAIT
    THOC
    THOCD
    THOCI
    THOCS
    THOCT
    THOL
    THOLT
    THOLU
    or for the IMG activity related to calendar.
    Other way is to use the BC set functionality. When you make modification in a calendar in source system you insert all modifications in a request, then you can get this request in a BC set. After you can download it and upload in BW.
    Regards,
    Sergio

  • Where do we use factory calendar

    Hi All,
    Can any one tell me where do we use factory calendar in SAP HR?
    Thanks
    Veer

    Hi Veeresh
    A factory calendar distinguishes between working days and non working days. It is company specific calendar. when you have entered an exception rule for non working days and have chosen factory calendar then you must enter the factory calendar relevant to your company.
    Hope it helps.
    Regards
    Kasi
    Note: Points are the best way to say thanks in SDN.

  • Difference between calendar used in capacity profile & factory calendar?

    Hello experts
    I am trying to check available capacities in planning book & found some ambiguities.
    In /SAPAPO/RES01, factory calendar maintained in the resource is say Z1, but in the same page, the capacity profile tab uses a different calendar.Say in Z1, if X/X/XXXX is a working day, the one present inside capacity profile considers it as a holiday & the  available capacity doesn't reflect in planning book.
    In ECC, the plant where this work center is defined follows calendar Z1.
    So my doubt is which calendar the capacity profile follows & how to ensure that it follows the same factory calendar Z1?
    Regards
    Soum

    Hello Soumyajit,
    few things you can check,
    Plant and work center calender assignment should be same, Plant has precedent over WC
    Check if in CFC9 you have correct change transfer mode set for resource.
    Once calender updated in ECC, use program RSIMPCUST to rebuild the tables for factory calendars in APO and then run /SAPAPO/CRES_CREATE_LC_RES to extend the resource in LC
    also run /SAPAPO/TIMESTREAM_UPDATE for any time stream update.
    This will update capacity profile as well resource capacity in planning book/ planning board.
    Hope this info will help you,
    Thanks,
    Rajiv

  • Factory calendar uses

    Hello,
    in my factory there are some factory calendar which are used but not assigned to any plant.
    can any one tell me when can be used?
    thanks.

    Hello Alaeddine,
    Check this list:
    SCAL - Maintain factory
    SFT3 - Maintain factory calendar Basis
    OP03 - factory calendar C PP - Routing
    OY05 - factory calendar Cross Application - Global Organization Customizing
    OIZH - factory calendar PM - Plant Maintenance
    OPJX - factory calendar C PP - Order Planning
    OPDD - factory calendar PP - Capacity Leveling
    OODK - Shift Planning: factory calendar Personnel Time Management - Shift Planning
    OOFK - factory calendar Training & Event Mgmt - Training and Event Management
    OVZ4 - C SD factory calendar SD - Basic Functions
    If you want to see a Where is used, you can go to SE11 and see where is used the data element..
    Check specially the tables starting with "T", like:
    T001W --> plant assignment
    TVRO --> Routes
    Kind Regards,
    Mariano

  • Using factory calendars in BI transformations

    Hello All,
    Do we have the option of using factory calendars in BI transformations, like we had in 3.x version update rules.
    I did not see any option for choosing the factory calendar, so i guess we will have to use function modules.
    Please let me know if there is any option available.
    Thanks in advance.
    Manoj

    hi Anton Moskvichev,
    I check in the source system assignment. The source system is checked. While replicating the DS from source system i replicated based on BI 7.0 only. While activating the cube or infoobject from BI content i did not get any transformation or transfer rules for activation. I just got the cube alone..

  • IPhone 5S IOS 8. Can't figure out how to disable the "live" location feature within the native calendar app used for mapping/travel time.  Have looked everywhere and it's driving me nuts.  Thanks for any help on where to make the change!!

    iPhone 5S IOS 8. Can't figure out how to disable the "live" location feature within the native calendar app used for mapping/travel time etc.  Have looked everywhere and it's driving me nuts.  Thanks for any help on where to make the change!!

    iPhone 5S IOS 8. Can't figure out how to disable the "live" location feature within the native calendar app used for mapping/travel time etc.  Have looked everywhere and it's driving me nuts.  Thanks for any help on where to make the change!!

  • Vendor Evaluation using Factory Calendar?

    Hello,
    Can I set up Vendor Evaluation to consider the Factory Calendar when scoring with the Standard Delivery Date Variance?
    I have set it up to allow the delivery to score 100% of the points if the delivery is in by 6AM the following day.  But this does not work over the weekends.
    Thanks,
    Matt

    Please help.
    There must be some way to do this. 
    If the factory is closed on the weekends and you miss a Friday delivery, even though you could have made the Saturday delivery you have to wait until Monday and SAP scores you as though you were 3 days late instead of the actual 1 day late.
    How can I make Vendor Evaluation use the factory calendar?
    Thanks,
    Matt

  • How get the duration in days of 2 key figures with use  of factory calendar

    Hi all,
    in a query i have two key figures (dates!). Now i want to get the duration in days between the two dates with the use of one factory calendar.
    FYI
    I made this in the past in the update rule (...DURATION_DETERMINE..) but now in this situation i have two cubes and i want to make an report on a multicub.
    Thank you very much for any help.
    Frank

    You would probably accomplish this with a virtual key figure.  I did this and the performance was not bad.  I developed a class with a signature for 2 dates and a calendar to return the number of business days. 
    Hope that helps...

  • No of days using factory calendar

    Hi Gurus,
    I know effective date(Example 01/01/2007). How to calculate no. of working days for effective date 01/01/2007 using factory calendar.
    Thanks
    Liza

    Hi Liza,
    start date and end dates are needed only if you want to know the number of working days between the two dates. In your case you can get number of working days  between effective date and the begining of factory calendar validity date.
       Check  FM "DATE_CONVERT_TO_FACTORYDATE"  . You have to pass parameters      Date  and  Clendar ID. The output will be number of working days .
    ie  effective date  minus    TFACD-VJAHR
    Table TFACD gives you the calendar ID and the validity dates(  VJAHR and BJAHR)
    Jaya

Maybe you are looking for

  • Report customer master data comparison

    Hello Experts, Using transaction SE38, we would like to run report customer master data comparison. Could anyone provide the report name? Thank you

  • Air Tunes and Multi-Pass

    I just started getting the Daily Show and I have AirTunes. When I play it, I wanted it to come over the spearks in the house so that everyone could hear. When I have iTunes switched from "computer" to the wireless AirTunes router, nothing happens. I

  • Including a form on a dynamic page (ORA-01036)

    I created a form based on a proceedure. I also created a dynamic page which consists of: DECLARE BEGIN PORTAL.wwa_app_module.new_instance('1235532770'); END; When this dynamic page is run in development using the "Run" buttons, it works. When I inclu

  • [Solved] Removing package installed by AUR

    I installed digikam and would like to remove it. [burt@bobland ~]$ sudo pacman -Qs digikam local/digikam-beta 1.0.0-7 Digital photo management application for kde [burt@bobland ~]$ sudo pacman -Qi digikam error: package "digikam" not found Because th

  • Problems Navigating this Discussion Website

    Using either Safari or Firefox I have big problems navigating this site. I can log in OK but it keeps hanging. With Firefox I sometimes get the message box 'This document contains no data'. With Safari I get 'Safari can't open the page "http:/discuss