Factory Calender and Planning Calenderr
Hi,
i want to plan my production for 7days a week. and want to plan for Raw materials also 7 days a week.
but here my requirement is that i dont want to receive raw materials on weekends. i mean no one will be in Factory to receive raw materials on Weekends.
If i maintain Planning Calender for 7 days and assign to Raw materials in MRP View 2 and Factory Calender for 5 days can i achieve this requirement?
for in house production i have to plan for 7 days a week. (Scheduling and Capacity Calculation)
i dont want to receive rawmaterils in weekends.
Please suggest.
Thanks
Nag
Dear
Based on your business requirement , you should have the following set up :
1.One Factory Calender with Work Days Monday-to-Friday Let say FC1 .This will be used on all the organisational level starting from Materials Planning to Sales .But will not be assinge to Capacity Requirement Planning Purpose or Any Production Activity in Work Centre .
2.You should have one more Factory Calander with work Days Monday to Monday ( 7 days week ) with some special rule like Plan Shutdown Days , Breakdown Maintainnece etc and this should be assinged to all the work centres -CR02-Capacity Tab -Capacity Header -Factory Calader ID -Let say it is FC2.
You need to ceate Calander in OP03/SCAL .It does nto have any transport and it will be a Cleinet level changes which requires proper approval .Please rememeber , you need to assing only FC1 to Plant assingement in OP03 where as FC2 will be asisnged only in Work Centre level .
Steps : Goto -OP03
1.Identify all those Public Holidays frist with Fixed or moveable as per business requirement
2.Goto Holiday Calander -Hit the pencil -Hit Create option -Enter ID , Description , Valid To/From Year ( shd be 20 yrs differnce )
Add all those holidays as per Public holidays as applicable in your business with proper valididty and finally SAVE
3.Goto Factory Calander -Hit the pencil -Hit Create option -Enter ID , Description , Valid To/From Year ( shd be 20 yrs differnce )
Asisng Hioliday Calander . In case of FC2-Work centre Calander , here you can hit the Special Rules .Include Special Activity like Plan Shut down of factory with Validity etc and SAVE .
4.Come back to OP03 main screen -Assing the factory Calender in plant .
5.Goto -CR02-Capacity -Capacity Header -Available Capacity Header -Factory Calander-Assing FC2
I do not think you should have planning calander seperately if you do not have any specific reason .
Hope it helps
Regards
JH
Similar Messages
-
Factory Calender and Holiday calender
Hai experts,
I am new in CRM. Can anyone tell me what is Factory calender and holiday calender in detail? And how to create it?
AnoopHi
this below blog will solve ur problem
How to create a new Factory Calendar in BI system
hope above solves ur issue
regards
prakhar -
Factory Calender and Time Stream
Hi,
I Maintain a factory calender A
where monday to friday is working
and holiday on 1/1/2009
My Distribution centre is working 1/1/2009
How do i set up in APO?
thxMaintain Production calendar (For Factory) and Distribution calendar (For DC) using transaction
S_AP9_75000138 - Maintain Planning Calendar (Time Stream)
In calculation rule maintain 5 days as working day using calculation rule "Weekdays"
then go to bucket delete day 1/1/2009 if showing as working day in Production calendar and keep this day as working for Dist calendar.
Then go to Location master in Calendar tab
assign Production calendar for factory location and distribution calendar (in shipping and recving) for DC. -
Set factory calender and user requirement date calculation
Hi Gurus,
I've requirement to do calculation for start user requirement & end user requirement. The calculation must exclude public holiday and weekend. Therefore factory calender need to be maintained.
Please guide me into doing this.
regards,Dear
Based on your business requirement , you should have the following set up :
1.One Factory Calender with Work Days Monday-to-Friday Let say FC1 .This will be used on all the organisational level starting from Materials Planning to Sales .But will not be assinge to Capacity Requirement Planning Purpose or Any Production Activity in Work Centre .
2.You should have one more Factory Calander with work Days Monday to Monday ( 7 days week ) with some special rule like Plan Shutdown Days , Breakdown Maintainnece etc and this should be assinged to all the work centres -CR02-Capacity Tab -Capacity Header -Factory Calader ID -Let say it is FC2.
You need to ceate Calander in OP03/SCAL .It does nto have any transport and it will be a Cleinet level changes which requires proper approval .Please rememeber , you need to assing only FC1 to Plant assingement in OP03 where as FC2 will be asisnged only in Work Centre level .
Steps : Goto -OP03
1.Identify all those Public Holidays frist with Fixed or moveable as per business requirement
2.Goto Holiday Calander -Hit the pencil -Hit Create option -Enter ID , Description , Valid To/From Year ( shd be 20 yrs differnce )
Add all those holidays as per Public holidays as applicable in your business with proper valididty and finally SAVE
3.Goto Factory Calander -Hit the pencil -Hit Create option -Enter ID , Description , Valid To/From Year ( shd be 20 yrs differnce )
Asisng Hioliday Calander . In case of FC2-Work centre Calander , here you can hit the Special Rules .Include Special Activity like Plan Shut down of factory with Validity etc and SAVE .
4.Come back to OP03 main screen -Assing the factory Calender in plant .
5.Goto -CR02-Capacity -Capacity Header -Available Capacity Header -Factory Calander-Assing FC2
I do not think you should have planning calander seperately if you do not have any specific reason .
Hope it helps
Regards
JH -
Invalid factory calender error in creating subcontrating po
hello all,
during creation of subcontracting po,system shows the error message "invalid factory calender error".
i have checked the assignment in oy05.seems ok.
pls provide some input.
regards
sumit simran.Hi,
Please check the path.
IMG>Enterprise Structure>Definition>Logistics - General>Define, copy, delete, check plant-->Define Plant.
Here you can find the which factory calender is assigned to your plant.
Then go to Tcode SCAL , select the Holiday calender and edit it . Double click on your holiday calender and change it i.e valid From year to To year. Go back , select the factory calender and edit it , give valid From year to To year.
Thanks. -
How to define a new factory calender?
Hi guys,
I want to have a factory calender that I can use for scheduling batch jobs to run each last sunday in the month. Such factory calender doesn't seem to exist in the system and I'm wondering how I could create it?! Is there a transaction that I can use to create a new factory calender?
BR,
ArminHi,
1. In TCode: SCAL, initially check the public holidays existing in the system, whether those public holidays are sufficient or not, if not create your own public holidays.
2. Then Create public holiday calender and attach your public holidays to this public holiday calender.
3. Then create your own factory calender and attach your public holiday calender to the factory calender and select the working days in a week and then save.
The above are the steps involved in creating a new factory calender.
Hope this helps.
Thanks,
Viswanath -
Date is not Defined in Factory Calender
Dear all,
We are facing some issue while releasing Process order. It states that Date is not defined in factory calender. and it throws out dates of for particular process order from 21.05.2014 to 15.07.2017.
Please check the attached screen shot & revert your thoughts.
Thanks in advance.I have found the issue. Actually operation quantities in the phases in the recipe was maintained improperly. Hence the charge quantity was getting multiplied with huge number hence resources allocated to them was considering that huge amt of quantity to be processed on it. Hence dates were coming the ranges of period 2014.
Deep Dave.
However thanks for your all prompt response. -
Factory Calender taking wrongly
Dear Experts,
We have extended the factory calender which are assigned to the plants. But after New year the system is thrwing error like " Date lies after factory Calender 01", even though we assigned another factory calender and holi day calender..? This is happening to particulary one plant in one server. All other servers are OK .Then We extended the 01 calender in the development then it is OK. I want to know why system is considering 01 calender instead of assigned calender???
Regards,
Praveen_sapDear Experts,
Thanks fopr your reply..!
The Only one calender is defined and found one Definition only. As SAid by one of our expert there be BUFFER problem as SAP also suggested to refresh the FACTORY CALENDER as it is ending with 2010 year.
My Problem got solved as We updated/extended the 01 calender eventhough it is not attached to any plant.
My question is Why Particular Plant only behing like this ? If any BUFFER problem is there it will be applicable to all the Plants in that Server. I am getting this error when creating Sales Order (VA01).
For this I raised a request Note to SAP.My problem got solved Can I open this question as unanswered or Can I close it as I got solution ? Please Let me know Sir.
Regards,
Pravs. -
hi experts,
what is factory calender,and how do u maintain and see our own factory,s calender.
plz help me..Hi Ravi,
here you can find sample which I've used to convert date to factory calender date..might be useful for you...
reward points if useful
thanks
data : ret_date like scal-date, " ''
fac_date like scal-facdate, " ''
workday like scal-indicator, " ''
temp_date like scal-facdate. " ''
loop at display_tab.
select single * from t001w where werks eq p_werks. " ''
call function 'DATE_CONVERT_TO_FACTORYDATE' " ''
exporting " ''
correct_option = '+' " ''
date = display_tab-eindt " ''
factory_calendar_id = t001w-fabkl " ''
importing " ''
date = ret_date " ''
factorydate = fac_date " ''
workingday_indicator = workday " ''
exceptions " ''
calendar_buffer_not_loadable = 1 " ''
correct_option_invalid = 2 " ''
date_after_range = 3 " ''
date_before_range = 4 " ''
date_invalid = 5 " ''
factory_calendar_not_found = 6 " ''
others = 7. " ''
temp_date = fac_date + ( display_tab-webaz - 2 ). " ''
call function 'FACTORYDATE_CONVERT_TO_DATE' " ''
exporting " ''
factorydate = temp_date " ''
factory_calendar_id = t001w-fabkl " ''
importing " ''
date = ret_date " ''
exceptions " ''
calendar_buffer_not_loadable = 1 " ''
factorydate_after_range = 2 " ''
factorydate_before_range = 3 " ''
factorydate_invalid = 4 " ''
factory_calendar_id_missing = 5 " ''
factory_calendar_not_found = 6 " ''
others = 7. " ''
move ret_date to display_tab-delvdate. " ''
modify display_tab. "C12K926660
endloop. "C12K926660 -
Create a plane with a own factory calender
Hi,
I would like to create a plan with our own factory calender. (spro-entreprise structure-definition-logistic general-define plan) Because we have some particular free days in the company the system already has some factory calender but we need our own one.How can I do
Thanks
DedeI' ve the result.
With the Code "SCAL" you have to create a public holiday. After that you can choise the holiday kalender and assign the public holiday you have created.
Thanks -
Urgent *** Is No. of Planned delivery days depends on FACTORY CALENDER DAY
Hi ,
I question for all . Is No. of Planned delivery days calculated on <b>FACTORY CALENDER DAY or normal difference between PO delivery and GR date .</b>
Please let me know ,its urgent.
Regards ,
Amarnath Reddy.<b></b>Hi,
Planned delivery period is CALENDAR days NOT Work days.
It does not use the factory calendar and you should not even TRY to make it do so.
Steve B -
Difference between Holiday Calender and Factory Calender
What is the difference between Holiday Calender and Factory Calender.
Holiday Calendars is used in Time and Payroll. It is Holiday Calender which is used in defining Work Schedules Rules for different regions.
In simple, we can say... it is defined for Employees.
Factory Calendar in turn in used in Shift Planning concept, T&E Mng, in defining/planning for Units.
In simple, we can say... it is defined at Unit(Area) Level.
Eg: Employee can be on holiday based on holiday calendar assigned to his area. But Factory may be running/open on the same day.
Regards
...Sadhu -
How to Transport Factory Calender to QTY and PRS systems
Hi All,
I had done a small change to Holiday calender in SCAL. I have read that it's not suggestive to transport it. Can any one let me know the procedure to transport the change to QTY and PRD systems.
The transport button is greyed out .
Best Regards,
SriThe following OSS Notes have also been checked.
356483 : Customizing: Current settings in the test system.
077430 : Customizing: Current settings .
328916 : Cust Changes despite "System cannot be changed" setting
Can any one provide an input on the procedure to move a factory calender - Individual entry..
Thanks in advance
Sri -
How to get past date based on duration and factory calender?
Hi All,
when i enter the duration ,i want to get the past date based on factory calender w.r.t current date
i.e if current date is 26th jun and duration is 10 , the past date should be 12th jun (which should exclude all holidays and weekends).
Thanks
VasumathiHi,
Please check this FM: I think this will resolve ur issue.
END_TIME_DETERMINE
Cheers,
Vijay. -
Factory calender importance in Sales Organisation.
Hi Experts,
Hope you all doing Gr8t.
Please let me know the importance of specifying Factory calender while defining the Sales Orgination.
Thanks & Regards,
Smithun.Hi
Factory calendar specify the work days at the customer's site .These calendars are used to determine when a delivery must take place in order for it to reach the customer's site on a work day when it can be received. We also use the factory calendar in consolidated invoicing. That is, if we specify that only one day a week is a working day for our customer ,the billing documents are only to be created for that one day each week, causing delivery documents to be consolidated into one billing document.
You maintain the factory calendar in IMG in T code SCAL and assign the factory calendar with plant and also sales org in Img while defining the plant in the Enterprise structure .If you donu2019t maintain it and make the standard order you will get an error-"Factory calendar missing or error in factory calendar".
Factory Calendar decides the holidays for the plant.
Sales order flow to production order and based on the factory calendar material availability will be confirmed to the customer.
Production planning/Scheduling will happen based on Factory Calendar
Regards
Raja
Maybe you are looking for
-
Delivering Error and Scheduling Error
I just wanna schedule a report, when I'v configured schedule, and click 'submit', the following error displayed: 'java.sql.SQLException: ORA-02289: sequence does not exist ' Same error occurred when I wanna deliver it to a printer which is already co
-
Collapsible panel problem in IE
Hi , I have a collapsible panel in a site I'm working on.the collapsible panel on display is closed. whe I open the page in IE8 it looks fine but once I click on the panel to open the content is show as it should and after a sec it drops down to the
-
Hi guys! I´m back with another question. When I try too recieve my my signal in the waveform chart a get an error It says: "Error 1073807253 occured at VISA Read in Basic Serial Write and Read.vi Possible reason(s): VISA: (HEX 0xBFFF006B) A framing e
-
HT201365 If my phone is stolen, how do I find it with find my find a phone activated?
If my IPhone is stolen how do I find it with my find a phone activated?
-
Can some help me to understand the oracle DB architecture. I'm in learning stage.