Good afternoon experts,
Is there any posibility to change the fields that appear in the "Mass Change" option in transacctions FBL1N, FBL3N .....?
Thank you a lot.
Kind regards,
Daniel

Hello,
Please, READ the SAP Note  640908. It describes how you can change other fields in these transactions.
REgards,
REnan

Similar Messages

  • How to grayed out fields in Pop screen in FBL1n while doing mass change

    Dear All,
    I want encorporate user specific screen with some edit fileds  with validations and some grayed out fields in pop screen
    in FBL1N Transaction while mass change option.
    Can you tell how can achive if any BADI or enhance pont or BTE or any exit .
    Regards
    Amar

    Hi amar,
    try with transaction variant
    with transaction variant we can hide or grey out fields
    bye
    T Bharat Bhushan

  • Changing  "Mass change" options in FBL1N

    Hi All,
    With reference t.code FBL1N, followinng by menu Environment/Mass change/New values,
    I wonder if is possible add other fields in the pop-up "New values" to get some mass changes.
    Thanks
    Gandalf

    What are you interested in changing?
    Rob

  • Ztable field level Mass Change

    Dear All,
    According to our client business scenario we have created one Ztable to capture day to day activities.
    Daily minimum 3000 records are getting saved. after some time user will change the single field value with some conditions. at a time he can change 10000 records also..now im using the syntax UPDATE ZTABLE FROM INTERNALTABLE.its working ...but i feel it may fail when no of  records got increased.
    so suggest me some options...if any one have idea about Mass change object creation for ztable please guide me to create
    Thanks & Regards
    Raj

    If you are changing too much data without a "commit work", then the redo buffers will be full at some point, leading to a short dump.
    To be on the safe side update the database table in blocks of say 10,000 records and send a "commit work" after each block. The optimal block size varies depending on row length and system parameter settings. Just try around a bit.
    Thomas

  • Fast change option in Sales order-Additiinal field required

    Dear al
    We want to add schedule line category field in Fast change option in Sales order as we have a requriment of changing schedule line category for more than 20 lines in sales order...After sales order is created ,we go and change the schedule line category ...
    Tried using MASS transaction but this doesn't have Schedule line category field.(VBEP table)
    Table name-VBEP
    Field name-ETTYP
    In VA05 also there is no option to change schedule line category mass update...
    Should we have to do in screen painter only for adding this field...
    Please confirm
    Regards
    Sudha

    Hi Sudha
    It would be better if you tell with which Ztable you have updated the data and how. It would be better if you share what you have done
    Regards
    Srinath

  • Mass change of certain fields thru list of equipments IE

    Hi,
    Instead of writing LSMW, i am looking for mass change option for list of equipments available thru IE05 under Go To----> Carry out a mass change.
    Its giving me a error message :
    Objekt PM_MASS_TECH_OBJECTS is not maintained
    Message no. BL010
    Diagnosis
    An application log entry is to be made for object PM_MASS_TECH_OBJECTS. This object is, however, not maintained as an application log object.
    Objects and subobjects of the application log are created using transaction SLG0.
    System Response
    The program had to be cancelled.
    Procedure
    Inform the system administrator.
    I went thru the forum link: Mass Change of Functional Locations - error message "Objekt PM_MASS..... and read the note 1166820.
    Please tel me the steps to do in order to include Object    : PM_MASS_TECH_OBJECTS
    Object Text: Mass Change of Equipments and Functional locations
    in table as per the note...
    Please provide some detailed steps..
    Authorization is no issue as i have profile: SAP_ALL
    Thanks
    Murad..

    Hi All,
    i'm trying to change a filed value as null. i.e. a value is maintained in pp work centre field for functional location.  i want to delete this value to keep this field as blank. By using this mass change functionality i'm not able to do so. can any body hep me out to this problem.
    Raj

  • Mass Change of TEXT field

    Hi
    I wanted to carry out Mass change of Text field in 2000 Financial documents, Can anyone give the best way to do the same?
    Thanks

    Hi,
    Execute the FBL3N report by selecting the Documents using Dynamic selection mention
    a) Document no's
    b) Fiscal year
    mention company code and execute the report and use mass change option to make changes.
    The following accounts may not appear in the listing
    a) Recon accounts in case these are not line item managed.
    b) If any of the documents have been archived.
    If you are on ECC6.0 or higher then you can use the report FAGLL03 report this would list the line items in the documents even if the Recon accounts are not line item managed.
    You can also record a SECATT/LSMW to do this for you in case you want different text for each of the line item.
    Regards
    K.R

  • Mass change of PAYMENT TERMS on Vendor Invoices

    Hi Can someone advise me how i can update paymetn terms on vendor line items en masse ?
    When i select the line items i require,  then CTRLShiftF9 - the field for payment terms does not seem to be available for me to add new values in .....
    Is there another way for this to be done, - or is there a way that i can add in this field
    Thanks for your advice
    Tony

    Hi Tony,
    You can use the transaction FBL1N.
    Select the entries you want to change and do a Mass change.
    The field PAYMENT TERMS is not available (I think whith an oss note that it is possible to ad this field to the mass change option) but you can fill in the fields Days/discount in Mass change.
    Paul

  • Mass change of payment in customer line item for all open line item.

    Hello,
    We have updated the new payment as per the new agreement with customer in customer master. We want this new payment term should also be updated in all the open invoices which are not cleared. Is there are way we can do the mass change in Payment term as the open line item in the customer where line item are more than 50. Please let me know the transaction code for the mass change of payment term in Customer account balances.
    Thanks and Regards,
    Rajesh Kumar Mantri

    Hi
    you can find the way to change the payment terms
    first check weather the payment term field is having change option in your document change rules in the line item for you customers.
    Financial Accounting (New)Financial Accounting Global Settings (New)DocumentRules for Changing DocumentsDocument Change Rules, Line Item
    if the payment term BSEG-ZTERM(payment term) is there for your customer and having deselcted check box for changing document you cannot change payment term for your company code.
    This can done client level or company code level.
    if the payterm  can be changed you do changes to payment terms mass level.
    Thanks
    ANJI

  • Mass Change FBL3n

    Dear Guys
    I want to use the MASS CHANGE option available in T-CODE FBL3N (G/L Account Line ITEM Display)  to change Material. But there is no field of material is avialable there.
    How can I use MASS CHANGE option to change to Material Fields in FBL3N
    OR
    Is there any option to use any EXIT or SCREEN ENHANCEMENT to add a new field there.
    Thnx

    Hi
    In your id try the transaction and then go to SU53, system would show you any missing authorizations. Consult your basis accordingly. I suspect mass change would require specific authorization
    Thank You,

  • FI-GL- FI Document mass change

    Hello friends,
    We are on ECC6 and having requirement from user to have field "VALUT - Value Date" in "Mass Change" option of FBL3n.
    Can any one give me solution to add VALUT field in mass change screen.
    Thanks,
    Parag
    +9120 9823053472

    you need to make sure the field can be changed in FB02.
    I presume you have a program for your mass change, however you need to check you config. There is config at line item and header level over the fields that you can change.
    There have been numerous threads explaining how this is done if you dont know, use the search facility.
    If useful assign points.

  • Sales Order Material and its MOQ mass change

    *The issue is related to our Spare parts Ordering process in our company.*
    We have a concept of having 65 days of back orders. Hence there will be
    lot many open orders in the system.
    The Material code will be changed from (for eg) M01 to M02. Hence forth the Material (M01) ordered will
    automatically changed to M02 through Material determination logic. But
    for the 65 days back orders, it is very difficult to change the
    material one by one in sales order. There may be more than 100 orders
    for a material. Even if the MASS change option in Transaction VA05
    doesn't address because of the following reasons;
    1. The changed new material (M02) may have new price with new validity
    periods, whereas the back orders will have old pricing dates. Its
    difficult to change individually in the open orders.
    2. Some materials may have partially delivered.
    Similar to ECM changes, there will be MOQ changes which also needs to
    be changed individually the order quantity in the old Open orders.
    For example,
    Initially the MOQ for a material in 10. Order inflow has happened based
    on this MOQ.
    Now if the MOQ is changed to 20, future orders are addressed. But for
    the 65 day back orders, we need to manually open the individual sales
    order and change the order quantity.
    Hence we require a mass change option for the open orders as below:
    1. For Material Changes (M01 to M02), I will give the list of orders and
    the line items and Qty for M01. The program should reject the existing
    line item for M01. An additional line item should be created with M02.
    Also the pricing date should be changed.
    2. For MOQ changes, I will give the list of orders and the line items
    and Qty. The program should reject the existing line item for those
    materials. An additional line item should be created with new Qty.
    If the material is partially delivered, the the existing qty should be
    updated to the extent it is delivered and the remaining qty should be
    updated with new material or New MOQ.

    You can use BAPI_SALESORDER_CHANGE.
    1. Get the SO detail using BAPISDORDER_GETDETAILEDLIST.
    2. MODIFY the ORDER_CFGS_* internal tables and  update.
            CALL FUNCTION 'BAPISDORDER_GETDETAILEDLIST'
              TABLES
                order_cfgs_value   = gt_char
                order_cfgs_ref       = gt_char_ref
                order_cfgs_inst      = gt_char_ins.
            MODIFY gt_cfgs_*.
            CALL FUNCTION 'BAPI_SALESORDER_CHANGE'
             TABLES
                order_cfgs_value   = gt_char
                order_cfgs_ref       = gt_char_ref
                order_cfgs_inst      = gt_char_ins.
    Refer SAP note 549563.

  • Mass change to activate the old line item display

    hi
    I want to know that is there any program like RFSEPA01 to activate the old line items display. There is no mass change option in this program.
    I am searching for a program which can change on mass level as i am working on many company codes.
    Thanks

    Hi,
    Standard SAP delivers this program only, If you want multiple options for company codes, ask your ABAPer to copy this program so that he can create a Z program.
    Rgds
    Murali. N

  • Mass change in collective BOM's

    Hello Experts,
    I want to change the quantity of a single material in several BOM's already created in the system, there are atlest 2000 BOM's having the same qty of that material which i want to change.
    I had a look to the MASS change option in the system but i was not able to resolve my problem.
    Please Help.
    Regards
    Prashant

    Hi,
    Please try transaction CS20.
    If resloved then let me know.
    Regards,
    Jigar

  • Fast change option for changing scheduling agreements

    Dear Experts,
    We need to have more fields in fast change option for scheduling agreements. How can we get it. please suggest

    Hello Antony,
    I want to add more fields in SA fast change.. it is not possible. if we click on more fields. but in PO it is possible. is there any way to do it in SA.