Hi Gurus
Cannot find FI-FM datasource in business content. We have BC SP09 installed.
The datasources relates to Cube:0FIFM_C01.
Can anyone shed any light.
Thanks.

Hi,
The data source  0FI_FM_1 is avialbale in R/3 source system for following releases.
Please check your R/3 release and Plugin for R/3 system.
Type of DataSource
Transactional data
Application Component
Funds Management (0FI_FM)
Available from OLTP Release:
4.5B
Available from PlugIn Release:
2000.1
Check below link for further information.
http://help.sap.com/saphelp_nw70/helpdata/en/71/d3143cb1b8be00e10000000a114084/frameset.htm
Regards,
Nitin

Similar Messages

  • Budget vs Actual data Datasource in Funds Management

    We are not able to find the correct datasource for Budget (Vs) Actual in Funds Management in R/3. We have activated most of the existing datasources and checked but could not find any data for the Value Type 'Actual'. Where can we find this?
    Thanks

    Hi,
    Look at this datasource
    0PU_IS_PS_44 Fund Assigned and Fund Consumed - R/3 Table FMAVCT
    Did you check
    0PU_IS_PS_33 - CO Line Items in Funds Management
    value type 70 - Actual and commitment.You should put restriction on 0FM_ACTDETL - Commitments and Actuals Detailing in Funds Management with values like ( 140 Invoice,110 -Transfer posting, and 160 Actual transfer)
    Regards,
    Saran

  • CASH FLOW REPORT FROM FUNDS MANAGEMENT

    Hi All
      I am in the mid of BW implementation for FI and FM reports.
    As part of this i have to create CASH FLOW report..
    Currently the user using a SAP report from , Funds Management, FMEM which points to the structure IFMEISB , Cash Budget Management.
    Is there any datasource is available in FM to access this structure?
    Otherwise any body knows what are tables in FM has to be extracted for this puropes..
    Regards
    Mano

    Hi
    You can check the Financials business contect.
    Funds management
    http://help.sap.com/saphelp_nw04/helpdata/en/71/d3143cb1b8be00e10000000a114084/frameset.htm
    Have a look at these data sources:
    http://help.sap.com/saphelp_nw04/helpdata/en/b5/12163c240a9440e10000000a114084/content.htm
    http://help.sap.com/saphelp_nw04/helpdata/en/d3/29ae399c1a6651e10000000a114084/content.htm
    Data sources for funds management
    http://help.sap.com/saphelp_bw33/helpdata/en/ba/c8ad3928a07c50e10000000a114084/frameset.htm
    Regards
    Naveen
    PS: Assigning point to the helpful answers is the way of saying thanks in SDN

  • Funds Management Budgets and Hierarchies

    Hi Folks
    We use funds management budgets in our R3 system and import them into an FM cube using 0FI_FM_1. When I run reports including budgets the Hierarchy for Funds Centre cumulates values in  subordinate nodes. The problem is that  the extractor brings in the budgets at each level as a result of the way the budget is stored in R/3. Previously I knew the lowest level that budgets were stored at and targeted just that data but now the budgets may be stored at varying levels.
    I either need to build an DataSource on R3 that provides the "Distributable" budget at whatever level it is stored or do I make the Key figure non cumulative.
    Anyone had an similar experiences or solutions with hierarchies

    hi
      Eli Klovski
      how to use this budget period  in FM
    I had read help
    http://help.sap.com/erp2005_ehp_04/helpdata/en/03/f1968109244986b0c3719d2670af08/content
    but that when i to define new ledget but no total table PSGLFLEXT can use (Had Activate PSM-GEN-BUDEGT_period 1 and 2)
    and if i want to define 12 AVC ,but how to control on month?
    can you help me ?

  • Funds management data sources not available in RSA5

    Dear all,
    We have got requiremnt for implemtation of Funds management.
    i have searched SDN for the same. my question is the data sources 0FI_FM_1 , 0FI_FM_2, 0FI_FM_31 ,0FI_FM_32 ....are availabel from help.
    But in the system (RSA% )when i wanted to see these data sources then i cant find them.
    what is the reason for that and how to go about it.
    Regards
    venu

    Hi Venu,
    The datasources u mentioned are now replaced with new datasources.
    Please got through the thread for further information.
    Datasource not present in RSA5 after appln component hierarchy activation
    Hope it helps
    Regards,
    Javed

  • Business Content for Funds Management and Purchase Orders

    Dear all
    Our controlling department asks me to have SAP Funds Management and Purchase Order reporting in BW and thus BO. SAP standard report FMRP_RFFMAV01X shows pretty much what they would like to see: Distributable Budget by Funds Center and how it got spent by the Purchase Orders.
    I tried to find what SAP BI content can offer. I found for example DSO 0BBP_PO in the "Enterprise Buyer" BI content, but this only shows purchase orders. On the other hand, cube 0PU_C02 shows funds line items, but nowhere a reference to the Purchase orders.
    Could anyone advise if there is something in the BI content combining FM and PO?
    thanks a million for your help
    Josef

    Hi Josef,
    The Functional cosultants in the Team should be able to answer this as to how the integration has been done and the respective tables.
    In case there is no STD datasources then you can build a view of Generic Datasource based on the Tables Recommended by the FC Team.
    Also check how Fundcentre is mapped in MM module,like it may be same as Profit centre or Plant.
    In that case get both the data in BW and build a MP/IS and report for both the KPIs...Amount Alloted and Amount Spent ,if drill down is require then show the POs.
    rgds
    SVU

  • Sap bw step by step implementation guide for funds management module

    Hi Guys,
    I am new to sap bw and my client is planning for sap bw implementation for sap funds management module.
    please provide any step by step guide and any seggestions would be appreciated.
    please provide me the standard info cubes and datasources and objects.
    Regards,
    Mahesh

    Hi Mahesh
    Please check if below application components are available, If you dont see them then you can implement it to get the relevant Fund Management Extractors
    (IS-PS) (0IS_PU_FM) &(PSM-FM) (0PSM_FM)
    You can find the information from help.sap (google it)
    Thanks
    Abhishek Shanbhogue

  • System error in Funds Management update

    Dear you,
    Have anyone seen the following when updating FM from FI document:
    "System error:Funds management update (FMRI, CHECK_WE_RE)"
    Any ideas what to do?
    Thanks
    Sonja

    Hi there,
    The update problem occurs both if we try to post with FB50L or if I try to make a transfer of FI postings in FM. This all happens in the new installation where we plan to use new GL and FM.
    This note you gave did not ring a bell for me
    The error message is FI057. But we have not yet found a suitable note.
    Therefore any ideas are still welcomed.

  • Funds management cube getting data from 4 ods, data not seen in cube

    Hello all,
    I am working on funds management cubes (0PU_C02 and 0PU_C03). These two cubes get data from like 7 or 8 ODS. Can someone tell me which are the ODS which feed to respective cubes. I have the mappings done but i am getting very confused.
    In the ods 0PU_O44 there is RLDNR for Ledger and I can see that data in ODS but when i run load to cube I dont see the ledger data (its direct mapping there are no routines or rules).
    Is there any sequence with wihic we have to load the data?
    Thanks
    Message was edited by: Raj M

    Hi Raj,
    I was going thru the forums who has knowledge in Public sector when i came accross ur forum.Can i get your email id..i have some questions to ask regarding student administration.
    thanks.

  • |Funds Management - relating to PR/PO

    I am getting another error in Funds Management:
    Posting date must be used for update of value type 000100 update profile 50
    Message no. FI_E008
    Diagnosis
    FM areas with assignment to the update profile must have all their value types defined as 'posting date' on the ledger level when activating to period-based encumbrance tracking (PBET) on the ledger level.
    Procedure
    Find all the FM areas using the update profile in transaction 'OF37'.
    Use transaction OF36 to ensure that all value types in the FM area(s) are using 'posting date' for the ledger that is being activated to PBET.

    Hi,
    It's what the system says. You have to ensure, that you don't overwrite profile 0100 in OF36 with other date, than posting date.
    Regards,
    Eli

  • Funds Management cut over of Open PR and PO

    Hi,
    In case of cutover, we are using following link to update FM account assignment in open PR/PO.
    SPRO>Funds Management Government>Actual and Commitment Update/Integration>Internal Data Transfer to Funds Management>Supplementary Account Assignment-->Select Documents
    and
    SPRO>Funds Management Government>Actual and Commitment Update/Integration>Internal Data Transfer to Funds Management>Supplementary Account Assignment-->Convert Worklist
    1) But in this case, for open PO of which GR is not done FMRP_RW_BUDCON report is not updated after doing above mentioned process. when I make GR, commitment get updated in FMRP_RW_BUDCON report. This does not show actual status of budget consumption as budget consumption is shown at the time of GR only.
    2) If GR is already done for PO and after doing above mentioned process, if GR get reversed then Negetive commitment shows in FMRP_RW_BUDCON report and after deletion of that respected PO, commitment of PO gets zero. But negetive GR commitment remains open which leads to wrong status of budget consumption. e.g. GR of Rs 5000 is reversed. Then report shows two documents as -5000 for GR reversed and 5000 for PO commitment getting open. IF I reversed this PO then PO commitment of 5000 become zero. but GR reversing amount -5000 still remains open. So it shows less consumption of budget by Rs.5000.
    Do I am missing any process. Suggest.

    Hi,
    Firstly, after you convert the open commitments, you'll need to run FMAVCREINIT to reconstruct AVC. FMRP_RW_BUDCON will then reflect the converted commitments.
    Secondly, based on your posting, it seems that you do not want PO commitments (VT 51) to be counted as budget consumption. You can achieve this in the ledger 9H configuration:
    Public sector management > Funds management government > BCS > Availability control > Settings for availability control ledger > Define filter settings for commitment/actual values. You will want to exclude both value type 50 and 51 from ledger 9H. After you change the setting, you will need to run FMAVCREINIT again.
    Hope this helps.
    Regards,
    Ming

  • Error while Activating Activate Global Funds Management Functions (PSM-FM)

    Hi,
    I am getting the below error while activating Activate Global Funds Management Functions (PSM-FM) in Funds Management.
    Aktivierung des Haushaltsmanagements ist nicht erlaubt
    Message no. ZZ003
    Kindly help me in fix this issue....
    Thanks
    Kishore

    Hi,
    Thanks for your reply. But can you clarify me why we need to delete the row Z_LEAVE in SE11 for FMISPS table. Because here ABAPER is objecting to do this as they feel there may be some impact if we delete this.
    Kindly clarify me
    Thanks
    Kishore

  • Error while settlement of WBS - Funds Management

    Hi,
    We have maintain derivation rule as - WBS to Fund Center. This Fund center is DUMMY because we need not want to control WBS through Funds Management.
    There is always one Cost center in each WBS. while settling this WBS we are getting error as -
    Asset ABC 000127000000 0000: no subnumber with FM assignment DUMMY / /
    Message no. AW851
    ABC - Company code
    000127000000 - asset number
    DUMMY - Fund center
    suggest.

    alex ice wrote:
    Hi, 1 change FC in AS02 to dummy if it applicable.
    > 2 Check note 618269 it applicable.
    > 3 remove FC from asset master data
    Hi Alex, how are u!?
    I've got the same issue than Harsh Vaidya in my system ...
    Ive already read this notes: [618269|https://service.sap.com/sap/support/notes/618269] (no apply to me, because Joint Venture Accounting isn't active), [844262|https://service.sap.com/sap/support/notes/844262], [1473357|https://service.sap.com/sap/support/notes/1473357], [446029|https://service.sap.com/sap/support/notes/446029] and [440396|https://service.sap.com/sap/support/notes/440396]
    All very interesting notes :P
    But... I couldn't find the solution
    I try to TRACE from FMDERIVE too, but when I go to KO88, FMDERIVE's trace doesn't track anything.
    Any help to throw some more light on this thread, would be very useful.
    Thanks a lot!
    Regards from Argentine.

  • After Funds Management activation we got error in travel managment

    Hi All,
      After activating funds management in the system, while creating a travel request we got the following error. Anyone can help on this, for idenifying the problem.
    In the travel request portal we are getting this error :
    " com.sap.tc.webdynpro.modelimpl.dynamicrfc.WDDynamicRFCExecuteException:      No expense type for estimated costs has been defined. Cannot save   , error key: RFC_ERROR_SYSTEM_FAILURE     and          No expense type for estimated costs has been defined. Cannot save   , error key: RFC_ERROR_SYSTEM_FAILURE "
    regards,
    Sabari Prabhu.

    Hi
    I have a question, I udnerstand in (Create one expense type "Estimated Costs") but my question is in using transaction
    When you start using the trip transaction and select a travel request the system send you to the TP04 transaction... now
    with this new function, I have to use the transaction PR05 its right? becouse the TP04 ask the VORS expense type, and sap says to dont delete record
    Please could you tell me with wich transaction you start to create a travel request? I have the same problem of the screen but Im not sure to use the TP04 transaction wit this solution
    Thanks a lot

  • Status of PO becomes F in fund management

    Hi,
    recently we have upgrade SAP from ECC6 to EHP4 and found some of the PO's Status becomes F in fund management, so we are not able to make service entry sheet and payment as system asking for further budget though actually POs value has not reduced fully.
    Plz help to remove the status F from FM so that it can be able to make payment.
    P K Sahoo

    Hi, try to reconstract PO(I don't remember tcode, but you can find it in spro like M*4N)

Maybe you are looking for

  • E71-Memory Card in use ERROR!

    hi, After transfering data to memory card through data cable from my pc and disconnecting it in the way it has to be done, the following error occurs:- *When tried to access memory card it shows an error msg saying memory card in use. The only way is

  • How do we know, when the service contract is last modified ?

    How do we know, when the service contract is last modified and by whom ? thanks siva Edited by: sivapara on Nov 24, 2008 3:14 PM

  • Library in forms 6i

    i'm using a library (pll) in a form the library is in my local disk, i want to use the form in several clients, the question is do i have to copy de pll in each client or there is an alternative. tia

  • CHANGES IN KONV TABLE on VA02 ADDRESS CHANGE

    hi SAP experts , can any one say when the sales order is changed in the T code. va02 ( just changed the address ) the condition table is changing its values  like vat is getting zero . can any one please say the reason behind it . here i have attache

  • Unzip Password protected EasyDMS71SP02P_1-20006126.ZIP file