Finish Date Calculation in Process Order

Hi all,
I have an unique problem. I am using Backword schduling and while creating a Process Order I give a Finish Date and Create the Order. But while Saving System Overwrites with a different finish Date. I have ckecked, nowhere In house Production Time is maintained in Material master for the Material. My question is from where the system is picking this new finsih Date?
Please give me the clue..
Regads

Hi,
Please check the scheduling Type when you ran MRP.
If you had used basic scheduling, then the times are picked-up from the material master. But you used Lead Time scheduling, then the times are picked from the routing.
Also, check the floats maintained in the material master.
Hope it resolves the issue.
Regards,
Kaushik

Similar Messages

  • Need to show data related to Process order request , BOM in a smart form

    Hi,
    I need to show data related to
    •     Process order request
    •     BoM
    Now in selection screen we are entering the followings.
    Manufacturing  Plant ,MRP Controller, Production scheduler, Order type , Order , Material, Sales order, WBS Element,Release,Scheduled start, Scheduled finish ,Selection profile.
    how to get 1> Process Order number,Produced Material,Material Description,Print date,Narcotics indicator , Quantity produced , Phase number , Phase description ,Resource description,Standard value  to show in a request form.
      2> Item category ,Component code,Component description , Component quantity ,Component Unit of measure ,BoM base quantity.
    Please help me how to get those values , what should be the aaproach , how to write the select quiry.
    Thanks

    Hi
    To get BOM details, do the following:
    1. Use the material number and goto Article to BOM link table (MAST) to get STLNR (BOM).
    2. With this STLNR, goto STPO table (where STLNR is the key field).  Here you will get all the BOM details like components (IDNRK), UoM (MEINS) etc....
    Hope this helps.
    THanks
    Vijay
    <b>PLZ REWARD POINTS IF HELPFUL</b>

  • Target cost calculation in Process Order based on Variance Calculation

    Hi all,
    I have a question on Target cost calculation in Process Order. My understanding is, the Target Costs gets calculated when the confirmation and GR is made for the Process Order.
    But if the confirmation/GR is not done, whether the target costs gets calculated for only the activity types after the Variance Calculation (KKS2).
    I have two scenarios. In one, the target costs got calculated for the activity types without the confirmation/GR after the Variance calculation.
    In another scenario, the target costs are not getting calculated for the activity types without the confirmation/GR if I try to do the variance calculation in KKS2.
    SO i want to know which scenario is correct?
    Can anyone answer this question?
    Thanks and Regards,
    Brijesh

    Hi,
    In general, the target costs are calculated once you deliver the order.
    Target costs for the components and the activities are updated only once you deliver the order and the target cost for the finished product gets updated when you do the variance calculation.
    Consider your scenario number 1 - you said the target costs got calculated for activity types without confirmation / GR after variance calculation.
    Now, if the order is not having any status like PDLV, DLV or TECO it will not calculate the variances in the first place.
    Your second scenario is correct - without GR the system does not calculate any target costs. Also it will not calculate any variances because the order status is still not DLV.
    Best Regards,
    Sameer

  • Production finish date is later than order finish date?

    In my company, most of the plan orders in MD04 have an exception message "64 Production finish date is later than order finish date". The plan strategy of the materials are 40. The plan orders are created from Scheduling Agreements or Independent Requirements.  We set 'Scheduling' as 2(lead time) in the MD01/MD02. The self-production time in material master data is 0. The schedule margin code is 000 which all the parameters are 0.
    For a example, we create a requirement on 2007.04.24. After MRP run, plan order generate. It's basic date will be 2007.04.24, but the production date IS 2007.04.25. All the plan order like that, the production date are always later than the basic date for one day.
    Could someone tell me why? and how to settle this problem?
    Thank you in advance!

    Hi,
    check scheduling parameters for planned orders and scheduling parameters
    for production orders.In that set the various indicators like
    adjust basic dates to order start date
    do not adjust basic dates to order start dates and try.
    Tcode opu3 / opu5
    Thanks,
    s.nandhakumar

  • Basic and scheduling  dates & time calculation in process order creation

    Hi guru's,
    i have one requirement, i need to calculate and display the basic and scheduled dates & times based on the given input i.e material , plant , process order type , quantity , UOM and scheduling type ( for corresponding scheduling type user will provide either start date or finish date ) using RFC. can  u plz provide any function module for this purpose or logic for calculating the same  , as i am working on version 4.7ee .
    Awaiting for a quick response.
    Regards,
    Madan

    Dear Rohan,
    1.Check the length of break timings defined in the resource that is assigned in the phase.
    2.Check in OPUZ whether for the process order type and plant combination whether scheduling is to include the break time also
    (whether the check box for scheduling with breaks) is included.
    Check and revert back.
    Regards
    Mangalraj.S

  • MRP Planned order finish Date calculation (Planned delivery + GR Proc.time)

    Dear Gurus,
    Currently in our system, when MRP runs, Planned orders are created and the order finish date is calculate based on Purchasing processing time OMEW + Planned Delivery time from Material Master + GR processing time from material Master.
    My business requirement is that,  system has to take only Planned Delivery time + GR Processing time and exculde Purchasing PRocessing time.
    I cant make it Purchasing Processing time as ZERO - because this is used for other Purchase orders and KPI will be affected for procurement department
    Now we are going to Automate the Purchase orders for Materials - if outline agreement exist.
    How to make system settings for a MRP run, the Planned order finish date - should consider only Planned delivery time from Material master + GR Processing Time ( it should exculed Purchasing PRocessing time). Is it posssible? if not by any user exit, ABAP coding should be done?
    gurus please advice!
    BADI : MD_PLDORD_CHANGE - is this can be used?
    Please advice
    Regards
    RS
    Edited by: RS on May 18, 2010 10:22 AM
    Edited by: RS on May 18, 2010 10:33 AM
    Edited by: RS on May 18, 2010 1:34 PM

    Let me check, if I can find a way to paste /afs/md04 (AFS Envirnoment) screen shot . But in the mean time following are the
    details
    IHPT  - 12 days
    GRPT - 0 days
    SMK  - 000 (Op Period, Float After Prod., Float Before Prod.,Release Per. - 0 days)
    Thanks,

  • Want last date of the month as default basic finish date for the Proc order

    For forward scheduling type in process order, irrespective of the start date i want last date of the month as my  basic finish date.
    Ex start date can be 01/10/2009 or 15/10/2009, but the basic finish date should be 31/10/2009.

    Hi Sam,
    sorry to say , its not possible in standard SAP.
    1) If, on order creation, a planned order exists for the production order/ process order, the basic dates are copied from the planned order.
    2)If no planned order exists on order creation, you must specify at least one basic date.
    The scheduling type determines the basic dates that you must specify. and it useses timings from routings for scheduling.
    so may be you need some work around.
    explain your requirement why do you want to fix it for the last day of month and other constraints, may be we can find some way.
    Regards
    Ritesh

  • PR delivery date calculation for TAB orders

    Hi All,
    1) The PR which is created via TAB item in the sales order - the delivery date for such PRs is equal to the delivery date in the sales order. This is happening only for TAB orders without BOM explosion in the sales order.
    2)In BOM exploded sales order - (meaning the parent item is entered in the sales order with item category TAP. ) -The sub components of this parent item is auto populate in the sales order. If any one of these sub components have item category TAB...then it creates a PR which has the delivery date equal to the "Planned delivery time" in the info record.
    Can anybody please explain why the PR default delivery date is different in the two cases explained above. Both are TAB items...the only difference is one is a stand alone TAB item and the other is via BOM explosion.
    Your help will be highly appreciated.
    Thanks
    Ashok

    Hi Sasy
    Delivery date calculation for MRP generated PR will follow the below settings
    1) Purchasing processing time in the Plant parameters in the customization and is calculated based on the Factory calendar days.
    2) Planned delivery time maintained in PIR and is calculated based on Normal calendar days
    3)GR Processing time Maintained in Material master record, calculated based on Factory calender.
    If you add up in the following sequence then you will get the exact delivery date.
    Purchasing Processing time + Plnd delivery time + GR processing time.
    Hope it will solve your  issue.
    Thanks / Karthik

  • Change of Basic Finish Date for a Maintenance Order

    Hi Experts,
    I have a requirement where I need to change the Basic Finish Date of an order. Currently in config for order type and plant combination, scheduling parameters are set as:
    Adjust to Basic Finish Dates
    Automatic Scheduling.
    If in an order, I remove the tick for Automatic Scheduling, I am able to change that but I am not supposed to do that.
    Can you suggest me how thisissue can be resolved. Remember, changing the Config is not an option.
    Regards...

    hi
    Since you have done the adjust basic dates ,kindly change the operation dates ,which will automatically change the dates specified in the operation dates
    regards
    thyagarajan

  • Changing basic finish date in Preventive maintenance orders

    Hi Experts,
    My requirement is to block PP work centre when maintenance schedule the equipment for preventive maintenance. I am making system condition as zero in generated preventive maintenance order but basic finish date is not changing in the order automatically. Can anybody please explain how to bring this? Finally my requirement is system should change basic finish date and time as time given in operation of task list.
    Thanks in advance.
    best regards,
    Srinivas M

    Hi Praveen,
    I have done all setting and tested but there is no change.
    My client requirement is like this - whenever maintenance plans are scheduled, for the scheduled dates, production capacity should not be considered by production. We could do this for breakdown orders but not happening for PM orders unless we change the finish date.
    The issue is to get the finish date automatically when scheduling maint.plans with respect to values given in operations. Please suggest how to get the  basic finish dates automatically.
    best regards,
    -Srinivas

  • Variance Calculation In Process order

    Dear All Gurus,
    We have produt cost by order.
    In process order variance calculation I am gatting variance  being calculated on Input v/s output costs.
    While settlement also same variance is being posted.
    I want variance to be calculated target v/s Actual
    Please advice
    Thanks in advance
    Bhushan

    I think in production order the variance is calculated between actual costs vs planned costs which is nothing but the input costs minus the gr coss of material produced at std costs.
    Is that happenning or not??

  • Actual Cost Calculation in Process Order

    Hi All,
    I updated Standard cost of a raw material through a cost estimate and also ran cost estimate of the FIN that is using this raw material but when I am creating a Process order, it is taking the cost of this particular raw material from the previous estimate not the recent one to calculate the target cost. Can any body help me with this.
    Thanks
    MKR

    Hi Ashok,
    My Valuation variants for the Costing Variant of Cost Estimate and Production order (Actual/Plan) cost calculation are in Sync to get the prices according to the price indicator in material master. But when it calculates cost for a production order, it is picking up cost from the previous period for that particular raw material. I have updated the standard cost by running the cost estimate but still its not working.
    Any lead on this. This will be really appreciated.
    Thanks
    MKR

  • Scheduled start and finish dates in the Work order.

    Hi Friends,
    I am facing peculiar issue that once the Work order has been released schedule start and finish dates should be derived from the control key and
    operation hours and work center capacity,infact in my case while releasing the Work order,these dates (scheduled start & finish) are not been
    populating in the Work order,(but SAP standard behavior is while releasing WO,the dates should be populated).
    though i have maintained proper configuration
    could you please light up some thing on it.
    Regards,
    Srinika

    Check Scheduling Parameters assignment to order type, Scheduling option in Control key.

  • Actual Over Head Calculation for process order

    hi!
    I have created a costing sheet for  over head, which will be based on labour activity cost.
    the base is labour cost for which I have given secondary cost element ( assigned in activity type for labour hours) in costing sheet and maintained over head rate for planned & actual. in credit of costing sheet for over head I have given secondary cost element with internal order.
    first question is : when internal order posting will happen? I am assuming , when production order settlement is done, over head cost has to be accrued to internal order. is my assumption is correct? because in line items of internal order , i couldn't see any thing.
    second question is : in process order, system is showing over head cost under planned cost, but it is showing ZERO in actual cost column. I have executed KGI2, system is not showing any senders or receivers. but when I executed KGI2 with dialog dipslay check box, system shows the calculations as per cost sheet correctly under condition value column.
    Please let me know where I missed ? how to get actual over heads in process order.
    in process order in cost analysis in the actual/target cost layout, system is showing the over head costs. but where as in "cost trend" layout, system is not showing over head cost.
    can any one help on above points.
    regards,
    ramesh b

    Hi
    Maintain the Overhead rate in KZM2 or KZZ2 as the case may be
    Then execute CO43... The moment overhead is charged to Process order, it would post credit to IO
    br, Ajay M

  • Lead Time calculation in process order

    Hi,
          I have a process order to be created of 112.6 L. i have only one phase  & one resource allocated. i have maintained my OH time as 1 H in my master recipe. now for resource i have maintained scheduling formula as ZRUNA = OH.
    After creating Process order the system calculates phase timing as 1:17:44. Can anyone pls let me know how did system calculate 17 min & 44 sec extra.
    Thanks & Regards,
    Rohan Somji

    Dear Rohan,
    1.Check the length of break timings defined in the resource that is assigned in the phase.
    2.Check in OPUZ whether for the process order type and plant combination whether scheduling is to include the break time also
    (whether the check box for scheduling with breaks) is included.
    Check and revert back.
    Regards
    Mangalraj.S

Maybe you are looking for