Finish date changed in Scheduling

Hello All
I am facing one problem in scheduling.
I have one production order 7734413.
Order is not released.
Always I am using back ward scheduling. I am working on  4.7 version
In production order Basic finish date is 07.11.2007 and basic start date is 28.10.2007.
In factory calendar Tuesday is holiday.
Now suppose I want to change finish date as 08.11.2007 and then I do scheduling.
Then system is proposing 09.11.2007 as finish date and start date as 31.10.2007.
That means after scheduling system is proposing one day ahead of finish date.
But if I enter finish date as any Wednesday then it is accepting the same as finish date.
Suppose I enter 14.11.2007 as finish date and if I do scheduling then system proposes 14.11.2007 as finish date. Here system is not proposing one day ahead of finish date.
Other details are as follows :
Schedule margin key
Opening period – 10 days
Float after production – 5 days
Float before production – 2 days
Main thing I facing problem in scheduling on all days except on Wednesday.
Please let me know the solution.

Hi
you an go through the following notes:
Basic finish date
Date on which the required quantity of the material is available (that is, the requirements date of the material).
If, on order creation, a planned order exists for the production order/ process order, the basic dates are copied from the planned order.
If no planned order exists on order creation, you must specify at least one basic date.
The scheduling type determines the basic dates that you must specify.
Dependencies
The order finish date is accurate to the day. However, for scheduling, production requires a completion date that also specifies the time. To ensure that the material to be manufactured is available on the order finish date, the completion date must be before 00:00 hours on the order finish date.
If, however, an in-house production time of 0 days is maintained in the material master, an exception is made to this rule. In this case, it is assumed that the material can be manufactured in a single workday. The completion date is then before 24:00 hours on the order finish date.
Example
The last operation of an order was completed on Thursday at 5 pm (17:00 hours). No float after production was maintained for the order.
If an in-house production time greater than 0 days is maintained in the material master record, the order finish date is Friday.
If an in-house production time of 0 days is maintained in the material master record, the order finish date is Thursday.
Regards
YMREDDY

Similar Messages

  • Production Order: warning when Basic finish date is before scheduled finish

    Hello experts,
    We will set in config OPU3 (scheduling parameters for prod order) Adjust dates = 2 Do not adjust basic dates, ... Essentially this will allow the shop floor controller to change scheduled date ie. production dates without affecting basic dates.
    With this setup the system may display in the header of an order the scheduling note "Basic finish date is before scheduled finish" as well as generate a scheduling log "Scheduled finish is after basic finish date" (message 36 mess class C7).
    These messages are not enough visible for our planners. I would like to find a way to generate a warning before save. I tried to add a record in OPJB: message class CO no. 533 "Scheduled date & is after the requirements date &" but this doesn't work.
    Note: I tried to add message class C7 no 36 in OPJB but got the error "Please enter a legal value".
    Have you been able to add message in table OPJB ? Is it a good idea or the only option is enhancement?
    Thanks for sharing your ideas.
    Francois P.
    Edited by: Francois Paquet on Sep 30, 2010 5:30 PM

    Hi Francois
    I'm trying to do the same (also for C7 035).
    Have you already found out how to do this?
    Arno

  • Basic start date and finish date changing in the past

    Hello Gurus,
    I set the scheduling parameters as " Do not adjust basic dates, dep rqmts to order start " and also assigned the priority to populate the basic finish date. System does calculate the finish date based on the priority and start date as current date but it does allow me to change both dates in past or future which should not happen.
    Please do note that I activated the defaulted date as current date as well. Even I removed this mark and did not work.
    Please let me know if there is any way to restrcit the changing it alteast in the past.
    Mahee

    This can be prevented using one the following ways depending upon your needs
    ---> Set the "start in past" field to appropriate value using transaction OPU7 for order type /Plant combination
    ---> Make the "Basic start date  and Basic end date" fields as "Display only" through the Field selection config for the order type.
    ---> Use the user exit on "SAVE" of the order to check for the same
    Regards
    Narasimhan

  • Purchase Ord delivery date changes SO schedule line date?

    Hi,
    I am purchasing a drop ship item as per sales order. The account assignment in the purchase order is the Sales order. 
    Why in some cases the schedule line date in the sales order changes when I change the delivery date in the purchase order? whereas in other cases it does not.
    Please help me out with this question.
    Sincerely.
    Puja

    Puja,
    The SO schedule line date should not change when you change the purchase order delivery date.
    However, if you change the PO del date, AND a user performs re-ATP against the sales order, OR if you are running backorder processing (rescheduling) of sales docs, then the SD item/schedule date may change to match the changed availability situation caused by the change of the delivery date of the PO.
    Look in the sales order in VA03, then Environment>changes.  Look to see if anyone or anything has 'touched' the SO item that is home to the schedule lines that were affected.
    Regards,
    DB49

  • Process Order Basic Finish Date and Scheduled Finish Date

    Folks,
    I have a requirement from the business to be able to update the Process Order Basic Finish Date and Scheduled Finish Date independently from each other.
    In other words, update the Basic Finish Date and the Scheduled Finish Date cannot change or update the Scheduled Finish Date and the Basic Finish Date cannot change.
    I believe the reason for this is to be able to use the Basic Date to maintain the ATP accurately and keep the Scheduled Date to mark when the order was originally due from the shop floor to be able to measure if orders are being completed on time or late.
    I have worked in tnx OPUZ and had some success with other issues with these dates but I can't seem to make them work independently from each other.
    Or does anyone have any ideas how to measure proces order performance to the production schedule?
    Thank you for your help,
    Greg

    Rajesha, thank you for your reply but it doesn't solve my problem.
    Let me restate my scenario:
    I start a process order and both the basic and scheduled finish dates are the same, June 1.
    At some point, shop floor tells me they will be late and cannot deliver until June 15.
    I need to update a date in the system so the ATP and the MRP planning runs have correct information for promising customers, I will update the Basic Finish date with June 15.
    I also need to keep the original June 1 date in order to measure the shop floor performance to the production schedule to measure how early or late the  order was delivered. How can I keep the original finish date or how can I measure if a process order is early or late??
    Thank you for your help,
    Greg

  • Changing basic finish date in Preventive maintenance orders

    Hi Experts,
    My requirement is to block PP work centre when maintenance schedule the equipment for preventive maintenance. I am making system condition as zero in generated preventive maintenance order but basic finish date is not changing in the order automatically. Can anybody please explain how to bring this? Finally my requirement is system should change basic finish date and time as time given in operation of task list.
    Thanks in advance.
    best regards,
    Srinivas M

    Hi Praveen,
    I have done all setting and tested but there is no change.
    My client requirement is like this - whenever maintenance plans are scheduled, for the scheduled dates, production capacity should not be considered by production. We could do this for breakdown orders but not happening for PM orders unless we change the finish date.
    The issue is to get the finish date automatically when scheduling maint.plans with respect to values given in operations. Please suggest how to get the  basic finish dates automatically.
    best regards,
    -Srinivas

  • PM Orders Basic & schedule finish date

    Hi Experts,
    I want the basic start & finished date similar to schedule start & finishe date  in any condition.For e.g. if i change the basic start & finished date the schedule start & finished date should become similar to basic start & finish date and vise versa.May I know how to do the customization setting.
    AR

    AR,
    This can be done through transaction OPU7.
    For the plant and order type combination, set the Adjust dates field to either"Adjust dates, Adjust dependent requirements to operation start" or "Adjust dates, Adjust dependent requirements to Order start".
    Regards
    Narasimhan

  • Scheduled start and Finish date .

    Hi Everyone,
    I am facing a problem in dates in creating a process order in Production .
    In the tcode COR1, when input the BASIC START DATE manually, the BASIC FINISH DATE ,scheduled start date and finished dates should get calculated automatically  as per standard SAP.
    The problem that I am facing is that , if I input the BASIC START DATE in future , the scheduled start date and finished dates are always coming as  the system date.
    whatever date I input in the BASIC START DATE  the scheduled start date and finished dates are always coming as  the system date.
    But this is not happening in quality and development server .
    Please help me if you have any solution
    Thanks
    Bijay

    Dear ,
    1.Scheduling parameter for new process order type and plant combination, to be defined at OPUZ . U can copy the settings at standard order type PI01.Here you should keep Backward Scheduling as Scheduling Type  and Keep the adjustment  Scheduling as Adjust to Basic Date , depenent requirement Date .
    Now  Order Basic finish date = Order Basic start date + float before prod + Lead Time of Operations (operation time from routing )+ float after prod.
    These floats are predefined in SMK  and assinged to material master .It comes through Planned Order after MRP run andcoped to Production Order .
    .2.Check and Define Scheduling Margine key in MRP -Carry All over all palnt paremtres (OPPQ)
    If you are MTS process , then Keep the Scheudling Type as Forward .Enter the Basic Start date and Scheduling Margine Days ( Opening periods , FBP, FAP) and then hit the Scheduling Indicator .It will calcuate all the dates based on the SMK and operation setup and propose you Basic Finish Date .
    So adjust the Flaots in SMK tab in process order , enter Basic Finish Date , Choose Bacward Scheduling to arraive Basic Start  or Go in reverse direction by choosing Forward scheduling .
    Hope its clear
    Regards
    JH

  • Calculation of start date with backward scheduling

    Dear all,
    I am facing an issue related to backward scheduling. I have requirement in which whenever backward scheduling is used, system should calculate from last activity to first for calculation of schedules which is fine. But when running scheduling i am giving finish date as input and system is always using start date as current date and not calculation last date from last. For example if i input finish date as 15 feb 2015, and there is only one activity of 15 days, system should count start date from 1 feb 2015. Please help me how i can achieve this, currently its always putting start date as current date.
    My current settings are--
    Project definition-  WBS Scheduling profile-  Backward scheduling
                                  scheduling scenario-  Free scheduling
    Network-      Planning type- basic dates
                        Scheduling type- Backward
    Please help.
    Thanks

    Dear all, this issue is resloved. Reason was that by default i am using forward scheduling for all project but in case of backward scheduling, user change schedule type at project definition and network. I was removing start date and putting finish date and running scheduling. Missing step from my side was i need to first copy date from top to down than run scheduling again.
    Thanks.

  • I use MS excel to Import activties,start,finsh date change to data date

    HI,
    I am working on a project using Primavera P6 V7,I use MS excel to Import activies in the primavera.I am facing a problem that when i import the excel sheet with columns(Activity ID,Activity name,Start,Duration,Finish),Acitity ID & Name import successfully where as Start and Finish Dates change with Data date.
    Can any one Please help me to tell the solution....

    You need to Import your activity relationships as well. Then, when you schedule (F9) your project, the logic will drive your dates.
    If you are just looking at producing a "pretty bar chart" (ie no logic, no scheduling capability), you will need to add a mandatory start date to each of your activities.

  • Production finish date differs from basic finish date in backward schedulin

    Hi, experts.
    When i do scheduling the planned order,
    production finish date differs from basic finish date in backward scheduling as below.
    Scheduling: Backward
    Basic finish date : 2010.01.22
    Basic start date : 2010.01.21
    Production finish date : 2010.01.23  09:00:00
    Production start date ; 2010.01.22 03:57:09
    *GR time : 0.
    *Scheduling Margin key : 0.
    I don't know why production finish date set in 2010.01.23 09:00. ( Basic finish date +1 day)
    Please reply me.
    Thanks.

    Dear Jong,
    1) what is the parameter used in MRP run, Basic scheduling or lead time scheduling
    2) you must find a exception Mssg for that plan order in MD04
    3) basic scheduling take the time from material master & lead time scheduling will take time
    from Routing
    Regards
    Madhu

  • Finish date is not correct

    Hi,
         I am facing a problem in Production order finishing date.
                  BasicDates          Scheduled           Confirmd
    Finish        01/14/2010  24:00   01/14/2010  16:30
    Start         11/05/2007  00:00   11/05/2007  15:52               00:00
    Release                           11/05/2007          10/19/2007
    I checked all the masters and found ok.
    Can you please help me analysisng this.
    Thanks

    Hi,
      Check in your work center whether factory calender has been assigned or not.
      If not assign factory calender 01.
      Regards,
      nandha

  • BAPI_PROCORD_CHANGE need to change GLTRS (scheduled finish date)

    Hello -
    I am writing a program where I need to change the scheduled finish date (field GLTRS) in a process order (transaction COR2).  I would like to use the bapi BAPI_PROCORD_CHANGE but it does not contain that field in the input structure. 
    Does anyone have any ideas how I can change that field without writing a BDC?  I am also curious to know why it was excluded from the bapi in the first place.
    Thanks!

    Hi Ferry,
    Thank you for your quick reply!
    That is very close to what I need, but it only updates GSTRS (scheduled start) and I need to update GLTRS (scheduled finish). 
    Can you think of any other suggestions?  I have also looked at BAPI_ALM_ORDER_MAINTAIN, but it doesn't have GSTRS as an input either, and doesn't seem to work for the order type I need.
    Thanks again,
    Susanna

  • Trying to update Project scheduled finish date - newbie help needed!

    Guys, I am super new to Oracle Projects, I have never used it before.  I've just learned a few things in the UI and read through the docs documenting the stored procs.  My question is simple (hopefully)   In the UI I choose a responsibility, then under "Projects : Delivery" I choose "Search Projects", I enter the Project ID in the field and click Go, I am able to see all the project details and the Tasks.  No problem there!  What I would like to do through the Update_Project API is to change the "Scheduled Finish Date" of the Project.
    I have the following information that I have managed to scrape up:
    Project_id, Responsibility_id, User_id, Resp_Appl_Id
    I retrieved the project id using:
             Select project_id,name from pa_projects_all
              where name = 'My Project';
    So first I call set_global_info with the appropriate parameters, then this:
        -- SET GLOBAL VALUES
         pa_interface_utils_pub.set_global_info(
         p_api_version_number => 1.0,
         p_responsibility_id => fnd_profile.value('57203'),
         p_user_id => fnd_profile.value('1013415'),
         p_msg_count => l_msg_count,
         p_msg_data => l_msg_data,
         p_return_status => l_return_status);
         l_project_in.pa_project_id := 4608;
         l_project_in.scheduled_finish_date := to_date('2008-02-27', 'YYYY-MM-DD');
      --UPDATE_PROJECT
              pa_project_pub.UPDATE_project(
                        l_api_version_number,
                        p_commit => l_commit,
                        p_init_msg_list => l_init_msg_list,
                        p_msg_count => l_msg_count,
                        p_msg_data => l_msg_data,
                        p_return_status => l_return_status,
                        p_workflow_started => l_workflow_started,
                        p_pm_product_code => null,
                        p_project_in => l_project_in,
                        p_project_out => l_project_out,
                        p_key_members => l_key_members,
                        p_class_categories => l_class_categories,
                        p_tasks_in => l_tasks_in,
                        p_tasks_out => l_tasks_out);
    What I am getting is the message "error :Project ID is invalid" and the status is "E"
    I'm not sure why it is invalid as it is the exact Project ID from the projects table.  The only thing I can think of is that the p_pm_product_code is set to null but I am not sure where this value comes from and why it even matters.  I checked the documents and it says it refers to some external system.  Why does the external system code matter if I am changing data within Oracle Projects?

    Hello,
    Looks like you are not setting the Initialization values correctly. Oracle Project APIs are Org specific and require proper initialization before being called for them to work.
    Few things i noticed from the code is :
    1.  The following is being used to set the User ID and Responsibility ID  :
         p_responsibility_id => fnd_profile.value('57203'),
         p_user_id => fnd_profile.value('1013415'),
    I think the call should be like this. This should be used only if you are going to call the API through a concurrent program from the submit request window (Oracle Apps environment). fnd_profile.value will get the responsibility id and the used id of the user running the program and assign it to the variables.
         p_responsibility_id => fnd_profile.value('RESP_ID'),
         p_user_id => fnd_profile.value('USER_ID'),
    Or If you are directly passing the IDs hardcoded then, This can be used if you are running the script from a Non-Oracle Applications environment, for example from SQL*Plus.
         p_responsibility_id => 57203
         p_user_id => 1013415
    2. I notice that you are not passing P_OPERATING_UNIT_ID parameter in the call to pa_interface_utils_pub.set_global_info. This is fine if you are not using MOAC  and you have set MO: Operating Unit profile for the responsibility being passed.  If you are using MOAC or are not sure, then it is always a good practice to explicitly  pass the P_OPERATING_UNIT_ID parameter in the call to pa_interface_utils_pub.set_global_info.
    Note :  DO NOT use fnd_profile.value('ORG_ID') to set the P_OPERATING_UNIT_ID parameter. In a MOAC environment this may not work.
    3. Always ensure you check the return status of the pa_interface_utils_pub.set_global_info for success before calling the Project APIs. This will save you a lot of frustration when testing.
    4. You might find the following note useful
    Project API Overview and Reference (Doc ID 1424156.1)
    Regards,
    Raghavan Gopalakrishnan

  • Scheduled finish date for process orders not updating in BW

    We are having problems with the scheduled finish date (GLTRS) for process orders. When the process order is already released, changes done in R/3 on the scheduled finish date will not result to a delta hence data in BW is not updated. Table AFKO, where data is coming from, is always updated with the changes though. 2LIS_04_P_MATNR is used in extracting the data.
    Has anyone experienced the same problem? We are looking for possible ways on how to have a delta whenever there are changes on the process order even after it is already released.
    Any help would be greatly appreciated...

    Hi Donna,
    If I've understood your problem correctly, you can increase the load frequency as Sriee has pointed out.
    If you want latest data frequently and if you are on BI 7.0 then you can look at Real Time Data Acquisition(RDA)
    Regards,
    Tom.

Maybe you are looking for

  • Performance Issue when setting connection information

    I am writing a Winforms application using VB.NET I have developed a method that sets the Crystal Reports Connection. This method first grabs the connection string from the config file creates a Crystal Reports ConnectionInfo object. The following cod

  • Channel & HD Wishlist for 2012

    I'd like to see both ESPN deportes and Cartoon Network added in HD.

  • Feature proposal: Optional keywords

    Use case: I tag some of the shots with the name of persons visible in the shot. I organize all these names under a (Persons) keyword in the Keyword list. I want these keywords / names to be included when sending the shots as files to others, but not

  • Where is the extract filter in photoshop cs5?

    Where is the extract filter in photoshop cs5?  Thanks

  • Safari is duplicating my Bookmarks over and over again

    I am running Safari 4.0.2 0n a Powerbook G4 1.67 GHz OSX 10.5.2. I was having problems with sync and MobilMe support was helping but have now gone quiet since the Safari problems continued even though they asked me to send them my Bookmarks file. The