Dear Experts,
I want to transfer my scarp qnty stock of finished  materia code ABC base unit EA stock into selling scarp material code XYZ base unit KG by mb1b 309 movemnt type but i get error Stok Differnce unit EA and KG
.Then in this case which scenario i used to transfer my finshed scrap ABC stock into scarp material code XYZ.
PLEASE GUIDE ME how i map this scenarion
Example-
production order ABC - 10 EA ,
After confermation 8 qnty OK
2 EA Qnty is scrap
Now i transfer this 2 EA stock into this  scrap material code XYZ KG but due to difference in base unit it not transfer in mb1b by movement type 309.

Hi,
Scrap in the production order is resultant of raw materials used.
Why is that you are getting finished material as scrap. In this case this scrap is from production or from storage?
Let us know  the process you are following and what are the materials you are using for the purpose of production.
In general, when scrap is reported in production...it should be treated as a By product and its qty should be received from production.
Or You can upload this scrap qty using MI10 (this is like physical inventory but wihtout any doc. reference).
So as and when, scrap qty is accumualted....upate the stock qty using MI10.

Similar Messages

  • Material to material stock transfer

    Is it possible to do material to material stock transfer when the material that is being transfered to recieving material is in Quality?. I am getting error in doing so. Please advice.
    Thanks,
    Sam

    Hi sameer,
    309 Transfer posting material to material
    The quantity is posted from unrestricted-use stock of the issuing material into unrestricted-use stock in the receiving material
    Prerequisite: both materials have the same stockkeeping unit.
    it is not possible to post material to material stock trasfer in quality
    Vishal...

  • Transfer material stock into another material

    hi
    I want to transfer the stock of one material into a new material,
    Is it possible? if yes then how? and is there any financial effect.
    thanks
    Pankaj Garg

    Hi Garg ,
    Transfer posting is done through MB1B T.Code which requires the necessary movement tyep
    Transferring the material stock into another Material uses the mvt type 309
    The quantity is posted from unrestricted-use stock of the issuing material into unrestricted-use stock in the receiving material
    Prerequisite: both materials have the same stockkeeping unit.
    Possible special stock indicators: E, O, Q, V, W 
    Hope this helps you out
    If found useful award accordingly
    Thanks & Regards
    Pavan

  • Conversion of 2 different material codes into 1 material code for STO?

    Hello All,
    A pleasant day to you all.
    I have a business scenario and I would want to get opinions on the feasibility of implementing it.
    The scenraio is that the country have a new tax regulation (they call it BOI) so that when a material or product is created on a certain machine, the tax is reduced. Therefore, if there is an exactly the same product that is created from different machines, it will incur different taxes.
    So, since the business has 2 company codes (i.e. Company A and Company B), the scenario would be company A will be creating 2 different material codes for this so they can track BOI products from non BOI products. But Company B on the other hand, would like to use the same material code to reduce complication. With this, Company A will then produce and do transactions using 2 different material codes then when PO STO is created (to transfer stock to Company B), Company B would like that those material codes from Company A would somehow (be automatically) converted into 1 material code on Company B's side. Is this possible? If so, how can we do that? what are the required set up to do this?
    Thank you very much. Your response and opinioin would be greatly appreciated.
    Best regards,
    Lee

    Hello Jürgen L.
    Thank you very much for your kind attention and reply.
    So with this, it's really not possible to do that requirement? There's really no way?
    Thank you very much.
    Best regards,
    Lee

  • Transfer of Material Class characteristics into Batch

    Hello,
    Is there a way to transfer the material specific class characteristics ( maintained in material class 001) into Batch, while creating a new batch?
    For e.g. for Material A, i have Material Class Characteristic = COLOR, with a value RED.
    So if i create a new Batch for Material A, the COLOR characteristic in Batch should get defaulted to RED, instead of manually entering.
    Pl let us know, if this is possible.
    Regards,
    Mangesh
    P.S: I know there is Default check at the characteristic value level, but that doesn't help, as each material will have different value.

    Dear,
    You can use function module exit EXIT_SAPLV01Z_014  SAP enhancement SAPLV1ZN when assigning characteristic values to batches with EXTENDED_CLASSIFYING parameter. You use this to classify user-defined characteristics in the background when creating a new batch using the central function module VB_CREATE_BATCH during activated batch classification.
    Refer IMG>Batch Mngmt>Characteristics Value Assignment>...using function module
    Please try and come back.
    Regards,
    R.brahmankar
    Edited by: R Brahmankar on Oct 11, 2010 4:39 PM

  • Transfer posting of material

    Hello All,
    Is it possible to Transfer all unrestricted materials in a warehouse (in a particular storage type) to blocked?
    thanks in advance
    regards,
    ranjit

    Hi Ranjit,
    Using MB1B transaction code and movement type 344 you can move unrestricted stock into blocked stock.
    The outcome of this transaction would a material document number.
    Later create a transfer order using Transaction Code LT06 and cofirm the same.
    Kindly revert back in case your are struck any where.
    Regards
    Krishna
    Note - Reward me if my solution has solved your issue

  • Transferência de material de consumo entre centros com ICMS - MB1B 833/835

    Boa tarde amigos, meu problema está na transferência de material de consumo entre centros utilizando a transação MB1B, mov 833 e 835, quando há incidência de ICMS:
    Para informação, ao fazer uma transferência para material de industrialização (MBEW-MTUSE, utilização do material = 1), o sistema funciona corretamente, pois o tipo de condição ICM3 no IVA de saída (mov 833) e o tipo de condição ICM1 no IVA de entrada (mov 831) são u201Cdedutíveisu201D, desta forma a contabilização fecha corretamente.
    Na transferência de material de consumo (MBEW-MTUSE, utilização do material = 2), não consigo fechar o processo devido o erro u201CM7050 -> Saldo não nulo: 157,09-   Débito: 0,00   Crédito: 157,09u201D. Esse erro acontece devido ao tipo de condição de imposto ICM2 que é usado no IVA de consumo na entrada (835), pois este é u201Cnão dedutívelu201D.
    Como se trata de transferência de material de consumo, o ICMS não pode ser recuperado, então entendo que se fosse possível ter uma saída com ICMS u201Cnão dedutívelu201D o problema estaria resolvido, alguém tem esse cenário e/ou tem alguma dica que possa me ajudar via configuração ou desenvolvimento?
    Estamos na SAP EC 6.0 com TAXBRJ.
    Att
    Antonio Amorim
    Complex IT

    Antonio,
       Observe que, no recebimento de mercadorias colocadas em trânsito, não existe valorização de estoque, pois isso já foi feito no momento da saída.
       Por esse motivo, não devem ser ativas no tax code de MM condições de imposto que estejam atribuídas a chaves de conta definidas como "não dedutível" na transação OBCN.
       No caso, a chave NVV é desse tipo e não deve ser utilizada, pois invariavelmente incorrerá no erro descrito.
       Mesmo que seja feita uma transferência para consumo no destino, não deverá ser feito o lançamento na conta de custo do material, pois não existem lançamentos desse tipo na MBSU.
    Abraços

  • Scrap of material in subcontract and Excess material issue

    Hi,
             I want to know is there any setting such that ,  for mfg. a finish good material,  some qty. of raw material is scrap   the qty which is scrap i have add as negative qty in BOM  and  but after making the GR for Finish material , all positive qty. are consume by deduction of qty which i have mention as negative but scrap is not done automatically,  i am doing scrap sepearetely  so it is possible  whenevr i make the GR for finish good material then ,  the material for which i have maiatain as negative should get automatically scrap,  as the raw maetria are consum using 543 materials,
    second thing  the negative  qty of material i have mention in BOM of finish good  but insted of maiatining -ve qty in BOM  is it possible   to add the excess qty in PO  as -Ve qty  because  when we select the finish  material in Subcontract PO  all BOM components appear in PO   but there there is no option to add some addition material in PO.
      can we make the above settings
      regards,
        zafar

    Hi,
      Thanks for your reply.
      Just want to know one more think, as in subcontract  we are issue the material as per BOm,  as suppose, total qty of one raw material required is 4500,  which is to be consume for making the finish good but due to std. packing of raw material i want to issue the qty 5000,  but while making the GR  only 4500 should be consume and the reamining 500  should be shown as in vendor stock  after getting material back  we will take that as 542 movement.
      regards,
        zafar

  • Error during creation of transfer orders for material

    Hi,
            We are doing a transfer of stock from one storage with WM to a storage without WM.
    But system does not finish the process automatically displaing the following error message:
    "Error during creation of transfer orders for material document 49000XXXX"
    System cannot find source storage bin
    Thanks in advance for the help
    Regard
    Enzo

    your picking strategy does not find the bin where the material is.
    So you need to check what value you have entered for picking in WM view of material master.
    then you have to check where your material is (storage type and bin)
    then you need to check customizing to where what storage types are included in the picking strategy that is tight to the material master entry.

  • Split Valuation Material Cost Estimate into COPA

    Hi all,
    Is there any way how we can transfer the split valuation material cost estimate into COPA?
    I checked the actual line items, there is no "valuation type / batch" characteristics there.
    Is this the main cause?
    Please kindly suggest on the best way to solve this issue
    Thank you very much
    Regards, Erwin

    Hi, Ajay
    Does this mean that, even though i manage to create the valuation type as characteristic in COPA, i won't be able to get 2 different cost estimate based on valuation type into COPA?
    Hm, then, are there any solutions which can be done to solve this issue?
    The client needs a COPA report which can show the breakdown of the sold materials cost estimates
    As usual, thank you very much for your help
    Regards, Erwin

  • Stock transfer of Imported Material

    Dear Experts ,
    I wanted to do stock transfer of import material from one plant to another under the same company code.
    I want to transfer the cenvat credit on taken on CVD & other cess to the receiving plant .
    How should I go about it.
    Kindly guide .
    Thanks

    Hi,
    1) create PO for stock transfer.
    2) maintain material of stock transfer in j1id , with accessible value.
    3) create goods issue 351 mov type.
    4) go to J1is , refernce documnet will be goods issue number , type matd and customer id receiving plant
        after entering in to it put percentage for BED , SED , cess and also give accessible value.
    5) save j1is
    6) post excise invoice (j1iv with refernce of J1is doc), this number will automatically comes in goods issue document under excise invoice tab.
    7) take print of excise, will go with goods issue
    8)then in receiving plant do GRN , excise invoice will be post excise in goods issue plantdo, enter duties for creadit.
    do same process as of excise creadit.

  • Material to Material stock transfer betn Handling Unit to nonhandling Unit

    Hi Experts,
    Pls explain step by step procedure to Material to Material stock transfer betn Handling Unit to nonhandling Unit.

    Hi,
    You have several options. In case you use the Stock Transport order scenario, you simple pick and pack in the HU managed SLOC and PGI. You PGR in the non HU managed SLOC. HU's are not taken into consideration. If you would use inbound deliveries, you can have the HU's copied from the inbound to the outbound delivery but still you dont do anything with the HU in the non-HU SLOC.
    You can also use tcode VLMOVE, if your HU managed SLOC is not connected to a WM. You do a 311 posting which creates a posting change delivery. After PGI the HU is moved from SLOC 1 to SLOC 2.
    MdZ

  • How to transfer Shelf Expired Material from QC Pending Location

    Dear Sap Experts,
    Scenario
    Currently the stock is lying in Quality Pending Location with Inspection Lot
    Against Inspection lot, MIC recorded;
    But system not allowing Usage Decision because shelf life is expired
    Now the Questions are
    1. How to make Usage Decision or
    2. How to Transfer "Shelf Expired Material" from QC Pending Location without changing Expiry Date.

    Dear ramana
    Please try with QA07 with intial run in days as 1and also the reason code
    If the materials are not batch managed the material will be transfered to Block or if it is batch managed it will make restricted.
    Please try and let me know
    Regards
    gajesh

  • Is it possible that we generate material requirement in MRP at company code level?

    We want to generate material requirement in MRP at company code level, what is the possibility or any work around.
    Thanx in Advance.

    Hi Mirza
    This is not possible on the standard system. The highest planning level on MRP is the plant.
    It has been discussed on the following thread, where BAdI MD_CHANGE_MRP_DATA was proposed as a solution, however, the logic to be implemented on this BAdI is very complex:
    MRP Run considering Stocks for Multiple Plants and Requirement maintained for Plant Cluster
    If you want to know more about the BAdIs available on MRP check the following document:
    BAdIs for MRP
    Another alternative is to use flexible planning to plant at company code level, then disaggregate the planning to the plants and transfer the result to demand management and MRP.
    See the following thread for details:
    Flexible planning | SCN
    BR
    Caetano

  • Error during creation of transfer orders for mateRIA

    hi gurus,
    I am getting an error while moving material from sl0c2 to sloc1 which is connected to wh by mvmt 321. the document is getting posted and the stock is coming to sloc1,but the error is
    "Error during creation of transfer orders for mateRIAL.how to correct the error.
    regards
    murugan

    Hi,
    The material is maintained at the Warehouse level, hence warehouse transactions have to be completed, by creating a transfer order and the confirmation of the same will create a transfer posting from SL1 to SL2 in the system. This is trigerred automatically depending on the sytem configuration.
    Regards,
    raghu

Maybe you are looking for

  • Duplicate photos in catalog......

    Hi I've  been engaged in a project to clean-up my Photoshop Elements catalog for  several months now...   so far, without success.   What spurred me to  do this was getting into a situation where I had (literally) thousands  of duplicate photos in my

  • ACS 4.2.1.15 patch 4 installation

    Hi everybody, I'm having a problem when I try to install the patch 4 in a Windows ACS 4.2.1.  When I began the installation process, after I confirm that version 4.2.1 is installed, the installation window disapear and never receive a message from th

  • Billing Relevance - Indicator C

    When is this indicator C- Relevant for order rel bill status according to target quantity used?

  • Hyperlink **** - urgent!

    Hi there I've got what I hope is a tiny problem that is currently causing me a massive headache - 2 out of 3 hyperlinks on my welcome page for a small conference website I've published (its currently just a welcome/splash page) don't work in Internet

  • Differentiate file uploaded from explorer view in SharePoint

    Hello, I am working on event receiver which on item adding updates few fields of document in library if those are not empty. The code is working fine in new file, drag and drop but in explorer view, I am not getting afterproperties values except two