My client wants to have a fixed vendor for the Procurement of Consumables which doesnt have a Material Master. I dont have source list also. But i want to make a particular vendor fixed for my purchasing. Is there any options available in SAP to do that?
Please advice regarding this.
Thanks,
Saakithyan

Regular vendor - Specifies that the material is to be procured from this vendor at client level, i.e. for the entire corporate group. 
If you set this indicator, the regular vendor is suggested as the only source. 
If you wish to work with the source determination facility for purchasing documents, it makes sense not to set the indicator so that the system suggests all available sources, not just the regular vendor.

Similar Messages

  • Fixed vendor in source list not recognized by MRP

    Hi
    I have a source list (ME01) with a listed info record for a particular plant/purch.orgvendor/material combo.
    I have ticked the fixed vendor tick and flagged it as MRP relevant (MRP=1).
    When I run the MRP the purchase requisition is created but the vendor field in the purchase requistion is empty. Somehow the MRP does not recognize the source list settings. No fixed vendor is allocated to the purchase requisition.
    Validity period of source list is checked.
    I have checked the User exit LMEQR001, but nothing is implemented.
    Any suggestions?
    Thanks in advance,
    Lars
    Edited by: Lars Tornblom on Jan 15, 2011 5:10 PM

    Hello Lars,
    Please check the following settings in cutomization;
    SPRO>>Materials Management>>Purchasing>>Environment Data>>Define Default Values for Buyers.
    Select : Double Click:  Settings for Default Values.
    Now select the group and go to Source determination Tab.
    In tab under pre-setting of automatic source dtermination indicator.
    Tick the check boxes Create purchase requistion and create purchase order vendor unknown.
    Note: In ME01, if your vendor is external  then you have maiantain thye vendor in vendor fileld. If vendor is internal (say plant to plant transfer) then vendor needs to be maintained under ppl field.
    Br,
    Tushar

  • Fixed Vendor in Source List

    Hi, All,
    I want to know what's impact if i tick the vendor in the source list?
    1. is it impact for MRP run to assign the source to purchase requisition to generate purchase order?
    2. is it impct for costing run?
    3. can i create purchase order for this material with other different vendor?
    Is there any other impact other than above items?
    if i have no perfer in source list. is there any sequence for source list to dertermine vendor? item 1 is first?
    can i tick mutliple vendors for 'fixed'?
    Thank you in advance

    Hi,
    Hi, All,
    1. is it impact for MRP run to assign the source to purchase requisition to generate purchase order?
    If you have the source list,,, it will suggest the vendor to be considered for procurement. It depends on How the configureation( it allowed to change the vendor)
    2. is it impct for costing run?
    No
    3. can i create purchase order for this material with other different vendor?
    In Standard SAP it is possible,,, it will give warning messeage...again it depends on the config/settings
    Is there any other impact other than above items?
    no other impact
    REgards
    anand

  • Fixed Vendor in Source List not picking in MRP proposals

    Dear All
    For a matrial, we have maintained two Contracts as Sources in Sourcelist. Both sources are valid and MRP relevant(MRPindicator 1 in Source list)
    We then fixed the second Source ( fix indicator in second line in Source List)
    Then Run MRP. The expectation was that the second source will be picked as its fixed. But the MRP proposed Purchase Requstion and Planned orders are picking the first source only (non fixed one)
    Wanted to to clarify whether the fix source indicator does not have any relevance during MRP ? OR is it some other problem?
    Please let me know your thoughts on this.
    Regards
    Shyam

    Hello
    As already mentioned by Jürgen, the indicator 'Fixed source of supply' is not considered by MRP at all.
    See the following note which explains that in more detail:
    110074
    MRP: Source of supply, several valid source list records
    Therefore, please make sure that there is only one source list item relevant to MRP.
    BR
    Caetano

  • Create SA from PR - Vendor from source List

    Dear All,
    I am creating a SA from PR, where i have selected a vendor & info record. and now when i tried to create a SA wrt PR, system is asking for a Vendor and if i entered different vendor also its accepting & again asking for the Net price. Can i make such that during SA if I do against the PR system needs to pick the Vendor from the PR(Source of supply) & price from PIR ?
    regds,
    CB

    Dear Friend,
    In this case Better you maintain the source list for that vendor and material in Me01, and make FIX vendor
    if you do this system will not allow to the another vendor for particular date range
    Or
    Maintain the Quota arrangement for the it will select the vendors based on the quota rating
    Regards
    Pramod

  • Error when blocking a vendor in source list

    We are trying to block a vendor from the Source list (Tcode ME01), however this vendor was created in a different system and imported into our current system.
    The error message we receive states "Source list record created in a different system".  We are unable to save the change, so it is not a warning message, but an error.
    Any help would be appreciated.
    Thank you

    your source list records get created in a central system. if you delete an entry you create inconsistencies to your central system (and you may get this record back soon undeleted).
    Contact the guys who create the source list in this different system and let they maintain the block and distribute it to your system again with ALE.

  • Is it not possible to create a PR with Fixed vendor without an Info-record

    Hi,
    We have a requirement in which data necessary for PR(Purchase Requisition) creation ( replenishment orders ) comes from a legacy system and we use the BAPI -BAPI_REQUISITION_CREATE to create the PR's.
    The problem is when we try to create PR by using plant in the field fixed vendor present in Source of Supply tab, we are getting the error message, "Inforecord for Vendor xxx and material xxxx does not exist ". This message is due to the plant given in fixed vendor field and missing info records. And we always use only "plant" as fixed vendor.
    Is there any way to avoid the determination of info records based on fixed vendor?
    Thanks in Advance.
    Edited by: Dagny on Aug 28, 2009 3:01 PM
    Edited by: Dagny on Aug 28, 2009 4:30 PM
    Edited by: Dagny on Aug 31, 2009 11:09 AM

    Kurt Lang wrote:
    It is more than well known that Flash is not supported on the iPad or iPhone. Adobe officially threw in the towel even attempting to get a working player for mobile devices that one, doesn't chew up battery life; two, doesn't eat up so many system resources.
    The focus now is on Adobe AIR and HTML5. So don't expect to ever see Flash for the iPad.
    I don't understand the reply. This is the Power Mac forum. Is the real problem finding a PowerPC version of Flash and Adobe Reader? If so, Adobe dropped Flash support for PowerPC in February.
    http://lowendmac.com/ed/bashur/11db/powerpc-flash-support.html
    How evil is this? Well, Apple itself no longer supports PowerPC in its last two major OSs, 10.6 and 10.7. So the problem here is a very old Mac.
    There is an Adobe Reader for PowerPC.
    http://www.adobe.com/support/downloads/detail.jsp?ftpID=5245
    Adobe kept putting out PowerPC updates longer than Apple did!
    Also, Adobe Reader is available for iOS, if that was part of the original question.

  • Report to identify multiple vendors in source list?

    is there a standard t-code that may list multiple vendors (if they exist) for a range of source lists?  better to solve with abap query?
    (ex. say there are 1250 materials and want a list of source lists, with vendors or even one vendor if it only has one)
    thanks all
    Edited by: strat on Mar 27, 2008 10:41 PM

    Hi
    Try following report
    ME0M - Source List for Material
    Vishal...

  • Source list vendor

    Hi SAP Gurus,
    We have a problem with soruce list. In the source list there are two vendors maintained and one of them is marlked as fixed vendor, with MRP relevent 1 in the source list. we have two inforecords for the material from two different vendors. one of them is cheaper and that is why we marked this vendor as the fixed vendor in source list. Now when we run the MRP in MD04, the req gets generated but it does not pick either vendor from those two vendors. Why is it happening like this? Is there anything wrong? PLease let me know
    Thanks
    Anusha

    In MD04 show nº planning order or PO and  if the qty is same for tha requirement qty.
    Plase check your parameter MRP t-code MD41  in the fielde Planning mode:
    Planning mode
    Defines how procurement proposals from the last planning run are to be dealt with:
    The system reactivates unfirmed procurement proposals and, if necessary, adapts the quantity and date to the new planning situation. The BOM is re-exploded only for procurement proposals that are to be adapted.
    The system reactivates unfirmed procurement proposals and, if necessary, adapts the quantity and date to the new planning situation. The BOM is always re-exploded.
    The system regenerates unfirmed procurement proposals completely.
    Check too...your date last run MRP in MD06...this material is new or old?? if you already checked in ME03 ( Vendor List) , MEQ3 ( Quota) and Validity... the problem can be in the parameter of the MRP

  • Source List for Standard and Subcontracting Info Record

    Dear Sir and Madam,
    We have scenario where nart A could purchase with Standard PO or Subcontract PO.
    We  have following 2 Standard Info Record and 2 Subcontract Info Record.
    Standard InfoRec 1 for Nart A to Vendor 001 --Fixed Vendor
    Standard InfoRec 2 for Nart A to Vendor 002
    Subcontract InfoRec 1 for nart A to Vendor 003 - Fixed Vendor
    Subcontract InfoRec 2 for nart A to Vendor 004
    We have the problem here, how can we set the fixed vendor in Source List, for Standard PO using vendor 001 and Subcon using Vendor 003?
    Thank you very much,
    Regards,
    CW

    In source list only one vendor can be assigned.
    If u want to assign 2 or more vendor, try using Quota Arragement.
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/f4/7d267944af11d182b40000e829fbfe/frameset.htm
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/75/ee115f55c811d189900000e8322d00/frameset.htm

  • Why Fixed vendor is read without Souce List on MD14?

    Dear Gurus,
    Hi,
    I am trying not to assign Fixed Vendor at MD14.
    I created one Purchase Info Record for the material without source list.
    And operated as below;
    1. Execute MRP and Planned Order created
    2. Convert Planned Order to Purchase Requisition
    3. Then, Fixed Vendor is read automatically from Purchase Info Record.
    When there are several purchase info record, Fixed Vendor is not assigned.
    And also when PR is created via MRP, Fixed Vendor is not assigned from one Purchase Info Rec.
    -> How can I avoid automatic assignment of Fixed Vendor for PR on MD14??
        Are some customization wrong??
    AK

    hi,
    As mentioned in the note 157830, your system is working as designed.
    There are however two possibilities to solve this issue :
    1) In transaction ME15, flag for deletion all the related info-records,
       so that no fixed vendor is found when converting the Planned Order
       into Requisition.
    2) Rewiew note 157830 which gives a solution for de-activating
       the automatic soutce determination when converting a Planned Order
       into a Requisition (in MD04 and MD14)
    Hope the information helps you.
    Best Regards,
    Arminda Jack

  • Source List - MRP Run

    Hi all ,
    In our production server Source List is maintained for a material .
    The first line contains a vendor ( say Vendor1 ) with MRP relevant indicator 1
    2nd line contains another vendor (say vendor 2 ) with fixed indicator checked and MRP relevant indicator as 1 .
    1)For both vendor the date range is same
    2)No quota arrangement exists .
    But while MRP run for that material Vendor1 is automatically assigned instead of vendor 2 . (althoug vendor 2 is Fixed )
    What may be the reasons ?Please suggest .
    Regards,
    Anupam
    Edited by: Anupam Halder on Aug 10, 2009 8:23 PM

    Hi,
    System doe not take care of "fixed" indicator in source list during MRP run as per OSS note 668764:
    1. Question:
    The fixed indicator is set for a source list record. Is this source list record preferred for a planning run?
    Answer:
    Only the source list records, for which the indicator 'Source list usage in materials planning and control' is set, are taken into account during a planning run; the fixed indicator is of no importance here. See Note 206684 for more information.
    Please also check the mentioned OSS note (206684)
    Regards,
    Csaba

  • Source list Collective processing

    Hi All,
         I have a scenario where i need to do Collective generation of Source list for few vendors using tcode ME05..
        As i have not used this functionality earlier, can you tell me in detail how to execute this in system ...
          Thanks
        Regards..
        Akkshaya

    Hi
    you generate the source list for several materials by using ME05.
    1.Enter the materials for which source list to be generated
    2.Enter the plant
    3.Select all records for Material and Plant (System should consider only outline agreement items, only info records, or both be taken into account)
    4. Enter validity periods
    5. Select  Exixting records option based on requirement
    Execute 
    A list of the source records to be generated is displayed. Already-existing source list records whose validity periods are thus changed are also listed.
    Select the source list records you want to include in the source list.
    <b>Fixed or blocked Source list records:</b> You can mark a source list record as "fixed" or block it. A "fixed" source represents the preferred source of supply, whereas a "blocked" source is one from which you are not allowed to order.
    Select the desired source list record. Then choose Edit -> Fix, or Edit -> Block.
    Choose  save to store the selected source list records for the displayed material in the source list.
    Exception messages are displayed by the system. Press ENTER to continue the saving process.
    Regards
    Ramakrishna

  • Source List Details under PR in Project

    Dear All,
    When I am creating a PR thro' projects, I want system to propose me the list of suppliers with price details. Already i have maintained the source List & the same proposal is coming if I am creating the PR thro' MM in ME51n TCode. How to get the same proposal even when i am creating PR thro' Network in CJ20n ?
    regds,
    CB

    Hi, Thank You,
    I have 3 vendors in source list for mat A. And i have maintained 3 diff Info Records for these vendor & Mat Combination. Now I want to know who & all were supplying this material to me at what price ? Is this possible, If yes then how ? Looking for favorable replies
    regds,
    CB

  • How the source list is created automatically

    Hi all,
    Cud any one tell me is there any way to create the source list automatically. as per my knowledge we need to give the tick for the plants we want the source list should be made mandatory while creating the material master.
    How can be make the Source list field for the Purchasing view mandatory while creating the material master .

    Hi,
    You can have the system generate a source list for a material automatically. The system offers you the possibility of quickly entering or updating all source list records for a given source list.
    With this procedure, a source list record can be created for each info record and/or each outline agreement item for one or more materials.
    You can create the source list for several materials (collective procedure) or a single material (individual procedure).
    Prerequisites
    Before you create source list records, consider the following:
    For which materials/plants are the source list records to be generated?
    Are only outline agreement items, only info records, or both be taken into account? (Decision only in the case of the collective procedure.)
    What is the validity period of the source list records to be generated?
    Do source list records already exist for the materials for which you want to create source list records? If so, you must decide whether the old records:
    May not be changed
    Are to be deleted
    Are to be excluded from the validity period of the generated source list records
    Activities
    Collective Procedure
    With this procedure, you generate the source list for several materials.
    Choose Master data Source list Follow-on functions  Generate.
    Enter the necessary data.
    Create the source list.
    A list of the source records to be generated is displayed. Already-existing source list records whose validity periods are thus changed are also listed.
    Select the source list records you want to include in the source list.
    Fixed or blocked source list records: You can mark a source list record as "fixed" or block it. A "fixed" source represents the preferred source of supply, whereas a "blocked" source is one from which you are not allowed to order. Select the desired source list record. Then choose Edit  Fix, or Edit Block.
    Choose  to store the selected source list records for the displayed material in the source list.
    Exception messages are displayed by the system. Press ENTER to continue the saving process.
    Individual Procedure
    With this procedure, you generate the source list for a single material.
    Choose Master data  Source list  Maintain. The initial screen for the source list appears.
    Enter the material and plant number. Then press ENTER to display the overview screen.
    Choose Edit  Generate records.
    In the dialog box which appears, enter the validity period of the source list records to be created.
    First determine how existing source list records are to be treated if their validity periods overlap with the one specified. To do so, set the appropriate indicator in the dialog box. Press ENTER . The source list is created.
    Click  to save the source list.
    BR
    Diwakar
    reward if useful

Maybe you are looking for

  • Business Blueprint

    Hello I was reading an article on SAP and came across the word business blueprint.Is this something like your functional specifications or entirely different from that ? Googled the word and came across a few blueprints but I am unable to co-relate i

  • Parameter of BI-Report URL

    Hi, now I have a BI-report ID:   0TPLB_0CSALMC02_Q009_V01 I need to add this Report into the webgui of CRM-2007. For this purpose, in CRM 2007 we need to specify the paramters of the BI-report-URL. But I have no idea , how to know which parameter we

  • XML forms: attachment size

    Hello, we are working with XML forms to create news. Also we have the possibility to attach km document to this news. The attachments are displayed as a link on the end of the news. No my question. Is it possible to show the size of this attachment?

  • TS2121 why san i tunes not open nike web site

    I tried to get some kind of answer and have been asked ++++questions and now i just have 1 simple question why does i tunes not open so i can download my work outs to nike. I don't want to buy anything just some straight talk.

  • SFSY-FORMPAGES showing as * when it exceeds 9

    Hi All, I have a field in my smartform which shows the total no. of pages generated. I have put SFSY-FORMPAGES for this purpose. It displays correctly till the no. of pages are 9. When the total no. of pages become 10, its showing me * The space for