FM to find week start and end date on the basis of a given date

Hi Everyone,
I have a requirement in which I require the week start and end date  of any given date.
For eg: The given date is Wednesday 24.03.2010, I need a function module to calculate the week start date ie. Monday 22.03.2010 and week end date ie. Sunday 28.03.2010 on the basis of that date.
Any input to this query would be helpful.
Thanks,
Nimisha Agarwal
Edited by: Nimisha Agarwal on Jul 7, 2010 7:47 AM

HI nimisha,
many posts r there for this .
Kindly check  before posting
anyways this FM will serve u  r purpose.
GET_WEEK_INFO_BASED_ON_DATE

Similar Messages

  • Get week start and end dates

    I'm currently coding a calendar where I want to diplay all
    event for the current week.
    Can anyone tell me how to get the dates to use in the query?
    Thanks

    When I run this:
    <cfscript>
    Offset = (DayOfWeek(Now()) - 1) * -1;
    Date1 = dateadd("d", offset, now());
    Date2 = dateadd("d", 7, Date1);
    </cfscript>
    <cfdump var="#date1# and #date2#">
    I get this:
    {ts '2009-01-18 10:58:34'} and {ts '2009-01-25 10:58:34'}
    Looks like I should have only added 6 days for date2, but
    that's minor. How did you manage to get 2009-02-01?

  • Report execution start and end date/time

    Hi All,
    How can one find execution start and end date/times for all reports? Basically I am looking to see what reports were run on a day, when and how long it took for each to complete.
    Thank you.
    Denis

    Hi,
    The "eul5_batch_reports" holds the data about the scheduled report and if you don't have any so you will not have any data.
    Take a look at "EUL5_QPP_STATS"
    for example:
    select
    qpp.qs_doc_name,
    qpp.qs_doc_details,
    fu.user_name Ran_by,
    qpp.qs_created_date Start_run,
    qpp.qs_doc_owner Doc_owner,
    qpp.qs_num_rows rows_fetch,
    qpp.qs_est_elap_time estimated_time,
    qpp.qs_act_elap_time Run_time,
    qpp.qs_act_cpu_time Cpu_time
    from eul_us.EUL5_QPP_STATS qpp,
    fnd_user fu
    where substr(qpp.qs_created_by,2,10)=fu.user_id
    order by qs_created_date

  • Getting the start  and end dates of the week

    Hi,
    I was stuck with a problem in getting the start date and end date of the week,i know the month ,week and year also,with these three values how can i get the start and end dates of a week.please help me
    Thanks

    There is no simple way. It has to be a math calculation.
    There are several ways you can get the dates. First you have to know what day is January 1st and what day is december 31st for a particular year. Second you have to check whether the given year is a leap year or not. Based on the abvove information you should be able to find out what day is a particular date.
    Hope this helps to get you started.
    - Venkat Dhurjati.

  • Adding a summary column in a table which contains the start and end dates in the week

    Hi,
    I've got a DIMENSION DATE table and want to add in another column which shows the start and end date of the week.
    See below, the new column is WEEKOFYEARTEXT.
    Does anybody know how i may generate this column using SQL and using the existing columns?
    Umar Javed

    See:  http://www.sqlusa.com/bestpractices/datetimeconversion/
    DECLARE @Year INT = '2015';
    WITH cteDays AS (SELECT DayOfYear=Dateadd(dd, number,
    CONVERT(DATE, CONVERT(char(4),@Year)+'0101'))
    FROM master.dbo.spt_values WHERE type='P'),
    CTE AS (SELECT DayOfYear, WeekOfYear=DATEPART(week,DayOfYear)
    FROM cteDays WHERE YEAR(DayOfYear)= @YEAR)
    SELECT WeekOfYear, StartOfWeek=MIN(DayOfYear), EndOfWeek=MAX(DayOfYear)
    FROM CTE GROUP BY WeekOfYear ORDER BY WeekOfYear;
    WeekOfYear StartOfWeek EndOfWeek
    1 2015-01-01 2015-01-03
    2 2015-01-04 2015-01-10
    3 2015-01-11 2015-01-17
    4 2015-01-18 2015-01-24
    5 2015-01-25 2015-01-31
    6 2015-02-01 2015-02-07
    7 2015-02-08 2015-02-14
    8 2015-02-15 2015-02-21
    Kalman Toth Database & OLAP Architect
    SQL Server 2014 Database Design
    New Book / Kindle: Beginner Database Design & SQL Programming Using Microsoft SQL Server 2014

  • How to find the start and ending dates of a quarter of a particular fiscal

    Hi Experts,
    I need a function mudule which returns starting and ending date s of a particular quarter of a particular fiscal year .
    For Example: if pass 1 quarter and 2002 or 2 quarter 2002 it has to give me the star and end dates of that particular quarter na d fiscal year.
    Please help me which is urgent for me.

    Hi Kishan thanks for reply.
    But given function module the 2nd one is full but it is giving me the calender year dates but i need fiscal yea dates.
    fro example: if i pass 1 st quarte and 2006 it is to give me the 1st-april to 30-jun2006.
    And need this quater starting date and ending date for as per USA fiscal year calender.
    If u get any idea plz let me know.
    thanks.
    Dashmantha.

  • Contract Start and End Dates in Sales Order

    Hi
    I have a situation where a service item is bundled with a deliverable item. The order is as follows
    Line Item    Mat                                                                 Qty            Higher Level Item               
    10              Item No.1 (Physical Item)                                  1             
    20              Item No.2 (Service Item)                                    1               10
    For the deliverable item 10 , Revenue is recognized immediately. For the Service item no.20 , revenue needs to be recognized over a period of 1 Year (It is a 1 year service contract).
    The whole order is created via BAPI from an external 3rd party order capture system.
    In order to do revenue recognition properly for service items , SAP I believe has 2 options
    1. Based on Billing plan dates
    2. Based on contract start dates
    Since order with both the line items need to produce 1 invoice, I cannot use billing plan . The only other option is to use contract start and end dates. I have enabled contract data at the sales order level. So when I enter the contract start and end dates manually at the line item level and set the item category to recognize revenue based on contract start and end dates based on time-based revenue recognition it is working fine.
    But I need a way to automate the population of contract start and end dates at the line item level. My ABAP guy is not able to find a user exit that can change the XVEDA or any VEDA structure in any of the user exits.
    I guess the SAP SD gurus out there would have definitely dealt with a situation of product bundling (Service and non-service items in the same sales order with one billing document , but seperate revenue recognition for service and non-service items)
    Please help.
    Thnx
    Siva

    Hi Siva,
    Kindly let me know what criteria you want to give for automatic population of start date of contract...
    Standard SAP comes with a few baseline dates for contract start date and we can control this from customization itself. 
    01     Today's date
    02     Contract start date
    04     Acceptance date
    05     Installation date
    06     Date contract signed
    07     Billing date/Invoice date
    08     CntrctStDate+contract duration
    09     Contract end date
    If you have some criteria which is not covered here, then let me know and i will try to provide some help then.
    Thanks
    Kapil Sharma

  • BT Broadband Contract Start and End Date

    Where can I find my contract start and end date online ?

    conrad wrote:
    You can, by starting a new order for BB and entering phone no + post code - no need for email address - you then go to choose a package page which shows your current package  details at the top of the page
    Obviously you don't need to go any further than that page
    Conrad, thank you for your suggestion. I gave your suggestion a try but initially got a technical error and then appeared to be getting closer and closer to completing an order without the required information coming up so I chickened out. This also was fraught with difficulty as the cancel button seemed ineffective.
    I think I may have to use imjolly suggestions.

  • Reduce Working Days by Emp Start and End Dates

    I'm banging my head trying to get this working. The set-up:
    DimResources table with various employee information including a Start and End Date.
    A Calendar table with FullDate, Year, Quarter....WorkingDays (1 for working and 0 for non-working) and WorkingDayNumber (working days increased by 1, weekends are not).
    Page View report with page view filters for Business, Role, Month, Week, Year.
    In the calculation the denominator is total working days for the period * 8. Works great. Further reduced by any submitted time off. Again, so far so good. The part I'm having trouble with is trying to further reduce total working days by
    the number of days the person wasn't available in a month, defined by the person's start or end date.
    The calculated field works great when only 1 person is selected. As soon as more than 1 person is selected or the slicer is cleared, an error is thrown.
    Any ideas on what is wrong or better ways to accomplish what's needed?
    TotalWorkingDays2CF=CALCULATE
     SUM(Calendar[WorkingDays]),
                    FILTER(Calendar,Calendar[WorkingDays]=1),
                    Calendar, DATESBETWEEN(Calendar[FullDate],SUM(DimResources[Start Date]),SUM(DimResources[End Date]))
    Error:
    <detail>
      <ErrorCode>rsErrorExecutingCommand</ErrorCode>
      <Message>Query couldn't run for dataset 'Tablix41DataSet'.</Message>
      <ProductName>Power View</ProductName>
      <ProductVersion>11.0.2150.3</ProductVersion>
      <MoreInfo>MdxScript(Model) (10, 27) Calculation error in measure 'Calendar'[TotalWorkingDays2CF]: An invalid numeric representation of a date value was encountered.</MoreInfo>
    </detail>
    Dennis DeRobertis

    ok, but this is not a running total but just a sub-total/grand-total
    so what you can do is the following:
    create two measures - first calculate the workdays per ressourcen and second use SUMX() to get the sub-/grand-total if multiple employees are selected (e.g. subgroups, groups,division, etc)
    WorkdaysRessource:=CALCULATE(
    COUNTROWS('Date'),
    FILTER('Date',
    'Date'[Date] >= CALCULATE(MIN('DimResources'[Start Date]))
    && 'Date'[Date] <= CALCULATE(MIN('DimResources'[End Date])))
    Workdays:=CALCULATE:=SUMX(
    'DimResources',
    [WorkdaysRessource]
    hth,
    gerhard
    Gerhard Brueckl
    blogging @ http://blog.gbrueckl.at
    working @ http://www.pmOne.com

  • [CF10] CFINPUT custom validation start and end dates

    Hello, everyone,
    Another developer that I am working with is working with a form that has start and end dates.  He'd like to be able to use custom JavaScript validation to make sure that not only are the dates in proper format (that part of the JS is working fine), but that it will also check to make sure that the start date will always be prior to (or equal to) the end date, and will throw an alert if the end date is before the start date.
    I've Googled for this, and am finding informative suggestions on just making sure the date is in the right format, or falls within a certain range, but nothing on how to make sure that one date is before (or less than) another.
    I'm guessing that data binding might be a part of it.  Can anyone suggest how to set these fields so that each has a validateat="onblur" that will check both values?
    Also, as a related issue, he has the CF datepicker working as far as entering the dates, but since the field doesn't get/lose focus on this, how do we trigger the function?
    V/r,
    ^_^

    i had tried this a few times but I kept getting an invalid numer to character error. Maybe my syntax was off. Let me try again.
    I must have had syntax errors. I tried it again, the way you typed it out and it worked. Before I was using '/' instead of '-' to separate the date fields.
    Thanks again!!

  • Start and End Dates check

    Hi,
    I have a requirement to find the list of persons who have overlapping dates.
    Each person can have many start and End Dates, but only one row that has a NULL end date, the active record. If the start and end dates are overlapped, like in the example below, the second row should have a start date of 24-DEC-2006 and not 22-DEC-2006. Is it possible to list those persons who have overlapping dates/gap in the dates.
    Empl_ID Start Date End Date
    12345 01-JAN-2006 23-DEC-2006
    12345 22-DEC-2006 13-JAN-2007
    12345 14-JAN-2007 NULL
    Any help is greatly appreciated.
    Thanks!

    Hi Patrick
    I like where you are coming from. I hope you don't mind but I have extended your idea slightly to add in a PARTITION BY clause to make sure we look at records for the same person. Also, if we LAG to get a previous record shouldn't we LAG the END_DATE and compare it with the current START_DATE?
    LAG(END_DATE,1) OVER (PARTITION BY EMPL_ID ORDER BY START_DATE)
    Doing this, then the results would look like this:
    Empl_ID Start Date End Date Lag Date
    12345 01-JAN-2006 23-DEC-2006 NULL
    12345 22-DEC-2006 13-JAN-2007 23-DEC-2006
    12345 14-JAN-2007 NULL 13-JAN-2007
    This would give the SIGN an issue because in the first record the LAG would be NULL and in the last record the END_DATE would be NULL. So it looks like some manipulation of NULLs has to take place as well which I will deal with later.
    SIGN((LAG(END_DATE,1) OVER (PARTITION BY EMPL_ID ORDER BY START_DATE)) - START_DATE)
    Anytime the difference between the Lag Date and the Start Date is positive this means this is an overlap which means we do need to look for any variance where the SIGN is 1.
    Using the other function, we could use LEAD like this:
    LEAD(START_DATE,1) OVER (PARTITION BY EMPL_ID ORDER BY START_DATE)
    Doing this, then the results would look like this:
    Empl_ID Start Date End Date Lead Date
    12345 01-JAN-2006 23-DEC-2006 22-DEC-2006
    12345 22-DEC-2006 13-JAN-2007 14-JAN-2007
    12345 14-JAN-2007 NULL NULL
    which when combined with SIGN becomes: SIGN((LEAD(START_DATE,1) OVER (PARTITION BY EMPL_ID ORDER BY START_DATE)) - END_DATE)
    This time you would be looking for the SIGN to be -1
    Personally, I think I would prefer the LEAD function because a) there would always be a START_DATE, and b) we could replace all of the possible NULLs with the SYSDATE to get a final calculation like this:
    SIGN(NVL(LEAD(START_DATE,1) OVER (PARTITION BY EMPL_ID ORDER BY START_DATE),TRUNC(SYSDATE)) - NVL(END_DATE, TRUNC(SYSDATE)))
    Based on the current date being 17-NOV-2009, you would now get this result:
    Empl_ID Start Date End Date Lead Date
    12345 01-JAN-2006 23-DEC-2006 22-DEC-2006
    12345 22-DEC-2006 13-JAN-2007 14-JAN-2007
    12345 14-JAN-2007 17-NOV-2009 17-NOV-2009
    Best wishes
    Michael

  • SAP CRM Tables and Fields for Contract start and End dates

    Hi Experts,
    Please Provide me SAP CRM Tables and Field names for the below.
    SAP CRM Contracts start date and End date
    SAP CRM Conditions(PROO, K007 etc....) records start and End Date.
    Thanks and Regards,
    Teja

    correction
    10 Replies Latest reply: 24 May, 2013 8:38 AM by nishant Vasudev  
    Tweet
    SAP CRM Tables and Fields for Contract start and End dates
    This question has been Answered.
    Teja Dhar 12 Oct, 2009 8:03 PM  
    Currently Being Moderated
    Hi Experts,
    Please Provide me SAP CRM Tables and Field names for the below.
    SAP CRM Contracts start date and End date
    SAP CRM Conditions(PROO, K007 etc....) records start and End Date.
    Thanks and Regards,
    Teja
    Correct Answer by Sreekantha Gorla  on Oct 22, 2009 8:22 PM
    Hi,
    dates will be stores in the table 'SCAPPTSEG'.
    I double checked it. This table stores all the date types of one order transactions...
    The relationship is as follows..
    CRMD_ORDERADM_H- guid = crmd_link-guid_hi
    crmd_link-guid_set = SCAPPTSEG-APPL_GUID.
    Thanks and regards,
    Sreekanth
    <:footer>See the answer in context
    6281 Views
    Topics: Customer Relationship Management
    Reply
    Average User Rating
    0
    (0 ratings)
    My Rating:
      Rating Saved!
    Comment on your rating
      Re: SAP CRM Tables and Fields for Contract start and End dates
    Robert Jesionowski 14 Oct, 2009 2:23 PM (in response to Teja Dhar)  
    Currently Being Moderated
        Hi, 
    you should try with FM: CRM_DATES_READ_SINGLE_OB or CRM_DATES_READ_DB.
    There is something in table SCAPPT and SCGENAPPT.
    Regards, R
    Report Abuse
    Like (0)
    Reply
      Re: SAP CRM Tables and Fields for Contract start and End dates
    Teja Dhar 22 Oct, 2009 5:30 PM (in response to Robert Jesionowski)  
    Currently Being Moderated
        Hi Robert, 
    I am not able to find contract start date and End dates in the tables SCAPPT and SCGENAPPT.
    Can you suggest some relevant tables.
    Best Regards,
    Teja
    Report Abuse
    Like (0)
    Reply
      Re: SAP CRM Tables and Fields for Contract start and End dates
    Sreekantha Gorla 22 Oct, 2009 2:35 PM (in response to Teja Dhar)  
    Currently Being Moderated
        Hi, 
    Table SCAPPTSEG stores the contract start and end dates.
    Thanks,
    Sreekanth
    Report Abuse
    Like (0)
    Reply
      Re: SAP CRM Tables and Fields for Contract start and End dates
    Teja Dhar 22 Oct, 2009 5:32 PM (in response to Sreekantha Gorla)  
    Currently Being Moderated
        Hi Sreekanth, 
    I am not able to find contract start date and End dates in the table SCAPPTSEG.This is for appointments.
    Can you suggest some relevant tables.
    Best Regards,
    Teja
    Report Abuse
    Like (0)
    Reply
    Correct AnswerRe: SAP CRM Tables and Fields for Contract start and End dates
    Sreekantha Gorla 22 Oct, 2009 8:22 PM (in response to Teja Dhar)  
    Currently Being Moderated
        Hi, 
    dates will be stores in the table 'SCAPPTSEG'.
    I double checked it. This table stores all the date types of one order transactions...
    The relationship is as follows..
    CRMD_ORDERADM_H- guid = crmd_link-guid_hi
    crmd_link-guid_set = SCAPPTSEG-APPL_GUID.
    Thanks and regards,
    Sreekanth
    Report Abuse
    Like (0)
    Reply
      Re: SAP CRM Tables and Fields for Contract start and End dates
    Wim Olieman 23 Oct, 2009 9:12 AM (in response to Sreekantha Gorla)  
    Currently Being Moderated
        Hi, 
    I can tell you where the pricing records are saved, replicated from ECC.
    The data from ECC table Axxx (e.g. A304) is replicated to CRM table
    CNCCRMPRSAPxxx (e.g. CNCCRMPRSAP304).
    Here you can find fields TIMESTAMP_TO and TIMESTAMP_FROM.
    About the dates: what Sreekantha Gorla stated, about table 'SCAPPTSEG' is correct.
    What might help is to execute program "CRM_ORDER_READ". Here you can find
    the relevant entries also.
    regards,
    Wim
    Report Abuse
    Like (0)
    Reply
      Re: SAP CRM Tables and Fields for Contract start and End dates
    Teja Dhar 23 Oct, 2009 4:59 PM (in response to Teja Dhar)  
    Currently Being Moderated
        Hi Experts, 
    Thanks a lot for your support.My problem got resolved.
    Best Regards,
    Teja
    Report Abuse
    Like (0)
    Reply
      Re: SAP CRM Tables and Fields for Contract start and End dates
    rajesh gadamsetty 27 Nov, 2009 12:29 PM (in response to Teja Dhar)  
    Currently Being Moderated
        Hi Teja 
    Please let me know how you got the dates. i got the same requirement
    Report Abuse
    Like (0)
    Reply
    Correction on above mail.
    Hi Sanjay,
    Can you please help me to find the contract st art date and end date fetching from the table as below
    ITEM DATES:
    Select guid_set from table CRMD_LINK where guid_hi              =  CRMD_ORDER_I-GUID AND
                                                                              OBJTYPE_HI     =  '06'
                                                                              OBJTYPE_SET  =  '30'.
    Select * from SCAPPTSEG where APPL_GUID = guid_set.
    as from the table scapptseg has some unusal fields which fields to select to get the start date and end date and on what condition and isuppose we need to convert als the same
    pls suggest further on same
    regards
    Arora

  • Update Contract Start and End dates via BAPI_SALESORDER_CREATEFROMDAT2

    Hi Experts.
    We are successfully using BAPI_SALESORDER_CREATEFROMDAT2 to create sales order.
    Only problem is that the contract start and end date do not get updated.
    We are passing that in ORDER_HEADER_in-CT_VALID_F and ORDER_HEADER_IN-CT_VALID_T.
    After debugging, I found that there is one more table SALES_CONTRACT_IN in SD_SALESDOCUMENT_CREATE. Updating the values in that table works.
    But the problem is this table is not available in BAPI_SALESORDER_CREATEFROMDAT2. How to update Contract start and end dates from this FM ?
    I could not find anything in the search of this forums. So I guess this is not an issue and I am doing something wrong. Can someone suggest to me please?
    Thanks in adv.
    Aishi

    Are you creating a contract or a sales order?

  • Report for Validity Start and End Date in PO

    Dear All
    Is there any report where I can get PO validity start and end date which user input in addtional data header tab of PO?
    Regards
    Satish Kumar

    Hi,
    Yes, It is available standard report using T-code ME2N - Purchasing Document (PO) Per Document Number, enter the T-code and provide the following input data's are as follows.
    Scope of List                 :  ALV ( for Ms-Excel format report)
    Plant                               :   __________ to __________ (if required)
    Document Date              : ____________ to ___________ (if Required)
    Execute the report shown by default in excel format and if required PO validity start and end data, you have to select Change Layout button and open new window options screen right side field option as Validity Per.Start, Validity Period End, Commutative number field data's are selected and click <--- arrow button and then click bottom tick marked button. Now, the report shown your requirement.
    Hope, it is useful for you,
    Regards,
    K.Rajendran

  • SNP Planned order start and end dates are not calculated correctly

    Hello SNP Guru's
    The SNP planned orders generated after the Heuristics run, have a start and end date based on the Activity Duration (Fixed), while the resource consumption is based on the Bucket Consumption (Variable), which is correct.
    The Activity Duration (Fixed) is based on the BOM Base Quantity. So if the Activity Duration = 1 day, and if the order quantity is more than a day, the start and end dates, still shows as 1 day. So no matter what is the order quantity, the start and end dates is always = 1 day.
    Does anyone have any experience in implementing any code to change the start and end dates on SNP Planned Order?
    Seems like it should work as standard.
    Am i missing something?
    Thanks,
    Mangesh

    Dear Mangesh,
    SNP is a infinite planning tool. If you have defined fixed duration to be 1 DAY in the activity, no matter how many quantity you input for your planned order, the order will last for one day. If the resourced is overloaded, you then run capacity levelling to
    banlance the capacity. What your expected beahavior happens in PPDS planning.
    Claire

Maybe you are looking for

  • Down Payment clearing in f-54

    Hi Sap Gurus, We use f-48 to enter down payments, and f-54 to clear these down payments. We are also deducting tds while making down payments to the taxable vendors as per income tax rules. In case of Invoices posted using fb60 every thing is going f

  • Unspecified error using odt in Visual Studio 2003

    Hello all We have Windows XP SP2. We have installed ODT version 10.1.0.4.00 on our workstation. We have MS Visual Studio 2003. We have the Oracle client 10.1.0.2.0. We also have Oracle data access product 10.1.0.4.0. When I try to access Tools - conn

  • Import CALS table as Indesign Table

    Hi All, InDesign CS3. Im working on NLM-DTD, When im importing the xml file into indesign template, i have checked the option "Import CALS table as Indesign table". So it is transfered to table format, after finished the pagination, i want to export

  • (( Hello -ENABLE REPORT PRINTING - OPTION NOT SHOWING  ))

    2010-07-28 Hello, I am trying to print a report in APEX 4.0 using the free account APEX.ORACLE.COM . I learning how to do this using the tutorial at: http://st-curriculum.oracle.com/obe/db/apex/r40/apexstart/apexstart_b/apexstart_b_ll.htm In the tuto

  • Variable Type Problem !

    i want to get a variable data type. how can i do it? th evariable might be a class object. how should i get it. please help me.