Hi all,
I have the BOM with material Mat1 as a component. The base unit of measure of Mat1 is KG.
Is it possible to replace Mat1 with Mat 2 material in MRP once the Mat1 warehouse stock is depleted.
The base unit of measure of Mat 2 is KGK.
The required quantity of MAT1 should be recalculated from KG to KGK accordanly unit ratio.
Please, expain, where does it maintain?
Thanks,
Peter

Hello Peter,
You can use follow-up setting (set Mat2 as follow-up of Mat1 in MRP 4 view of material master if this follow-up scenario is valid for all BOM) with discontinuation indicator '1', w/o effective-out date. In this case Mat1's stock will run out (no PldOrd, PR, etc) will be created, and from the date, when Mat1's stock runs out, MRP will calculate with Mat2.
As I told you, according to my best knowledge, you cannot realize this with different base unit of measures. (you have to change the buom of one of the related material masters or create a new material master if you cannot cope with buom-change).
Follow-up group scenario can also be used but I guess different buoms will be a problem in that case as well.
Maybe there are better solution but I'm not aware of it...
BR
Csaba

Similar Messages

  • Transfer material with different stockkeeping unit

    Guys,
    My user having problem with material transfer (material-to-material) from KG to MT. This error occured during material transfer
    "Stockkeeping units KG and MT differ"
    They still need to transfer this material without creating any new material number (OuM in KG) since all their plant using the same material number (OuM in KG).
    What is the best practice in SAP to solve this problem?

    for material 1 post goods issue to cost center with 201 movement .
    for material 2 post goods issue reversal to costcenter with 202 movement.
    if the prices in the material master are not the same, you may get a balance at the cost center.
    If you want to have the value flow,  then you need to create a production order, to consume material 1 and receive material 2.

  • Base unit of measurement while saving production order

    Hi
    While saving production order I am getting following problems:
    "Material has no base unit of measure"
    Whereas UOM is there, I also can see that as soon as I  enter qty while creating the order. System automatically prompts the UOM.
    I also donot find any problem in MRP run, planned order creation etc
    So what can be the problem?
    Edited by: BNR on Nov 24, 2008 5:22 AM

    Dear,
    It may be data base problem as you are getting this problem fequently so please check with Basis person.
    Have you defined the any production unit in both material master WS view & in routing or any other alternative unit of measurement please check?
    Regards,
    R.Brahmankar

  • Change base unit of measure

    Hi,
    Its me again. I need to change the base unit of measure of a material but a task listw as created via QP01. I tried to delete this via QP02 but i still cannot change the base unit of measure. Is there any way except for deleting the task list via CA98?
    Thanks.
    Elen

    Ellen,
    Unfortunately the answer to your question is no..You have to use a transaction like CA98 or QSR6 to delete the Inspection plan from Database. Please take necessary authorisation and delete this plan.
    Alternately set this material to with deletion flag and client & plant level status, so that you cannnot use this material any longer. Now create a new material with correct Base unit of measure and use this material.
    Regards,
    Prasobh

  • Base unit of measure is cahnging after creation of material master

    Hi
    I have created a material with material type Raw material with BUM  "Ton" , after save the material, when iam checking the material with display mode, the BUM is changed into "EA",i dont know where the sustem picks the BUM as "EA", kindly suggest where i have to do the configuration settings.
    Thanks

    Hi,
    Have you created the New Material referencing from another material.
    Please check the following links for details. It should be able to answer your queries.
    [Re: can't able to change into alternate UOM]
    [Re: variable order unit]
    [Re: Base Unit of Measure]
    Hope it helps,
    Best regards
    Amit Bakshi
    Edited by: AMIT BAKSHI on Aug 4, 2011 12:44 PM

  • Changing Base Unit Of Measure (Material Master)

    Hi
    1. How to check this? (Any successful changes in material master only took place when there is no open document from SD, PP, MM & FI for that material. )
    2. Base unit of measurement cannot be changed.  The reason being material movement history is there in table - MSEG mainly which otherwise create inconsistency in reporting.  -
    Is this line applicable for current period or previous period in current year or previous period previous year???
    3. There are no existing purchase requisitions, purchase orders, or scheduling agreements for the material. -
    is this means open / pending purchase orders  or the the PO's created in system with respect to material where the GR and IR is already done
    4. You can change the base unit of measure if there is no stock of the material during current and previous period----
    is this means the term " previous preiod" is previous period in the current finacial year   or its applicable for the previous preiod in previous financial year
    5. Post the stock in the previous period to the current period  - -
    how can we do this???
    Vijay

    See this OSS note : especially the last sentence:
    From OSS note 138767
    Within the material master record maintenance, you want to change the base unit of measure (base unit). During the change, the system performs extensive checks in order to avoid inconsistencies in the applications which use the material master.
    In particular, the following checks are performed:
    The base unit must not be defined as an alternative unit of measure for the material
    No International Article Number must be assigned to the base unit
    No proportion/product units must be defined for the material
    No configurable material must be assigned
    The material must not be used as a configurable material
    Stock must neither exist for the previous period nor for the current period
    No physical inventory must be active
    No reservations or dependent requirements must exist for which the deletion indicator is not set
    No planned orders must exist
    No purchase requisitions, purchase orders or scheduling agreements must exist for which the deletion indicator is not set
    No WM transfer requirements, no WM quants or no WM posting change notices must exist
    The material must not be a bill of material
    The material must not be contained in a bill of material
    The material must not be used as a production resource/tool
    The material must not be used in task lists
    No standard cost estimate must exist for the current or future period
    No production orders must exist
    No planned independent requirements must exist
    No run schedule headers must exist
    If the base unit has dimensions, no serial number profile must be assigned
    No sales and distribution documents must exist which have status Not processed or Partially processed.
    Solution
    If necessary, all reasons mentioned above must be eliminated by archiving the objects listed
    1) SAP checks this for you. A new button will appear in MM02 and after you click this button to check the error log, you will see which documents exist.
    2) I have not seen that an existing movement will restrict the change of a BUoM.
    3) No purchase requisitions, purchase orders or scheduling agreements must exist for which the deletion indicator is not set
           it is not caring about GR done or IR done. it telling you that the deletion indicator has to be active. As a deletion indicator can be reset easily, you probably have to archive the documents
    4) the previous period is the period before the current period.
       today we have February, hence the previous period is January.
    5) first make sure your current stock is higher than the stock of the previous period. if it is lower, then you have to create inventory in current period first e.g. with 202 movement with current date.
    Then you issue the previous period stock with 201 movement and previous period date (make sure periods are open in OB52 and MMRV allows posting to previous period).
    Finally you issue the left stock in the current period with 201 and current date.
    Now previous period and current period stock is zero. After the change of the base unit you have to get the stock back into the system
    Edited by: Jürgen L. on Feb 2, 2010 3:58 PM

  • Putaway Strategy I, not allowing second material with different batch

    Hi all,
    Can someone please help me to understand where is the problem
    My config is
    Strg Typ 401
    Putaway Strategy I
    Capacity check - 4
    Mixed storage: X
    Addition to existing stock: X
    Storage section check -active
    Storage bin created for the storage section in the storage type 401
    Maximum capacity maintained in Storage bin
    In material master WM view 1- maintained capacity.
    When system is correctly finding Bin for First material / Batch combination
    But when I am trying to create TO for same material with different batch it does not find storage bin - even the storage bin capacity is still remaining
    Also it is not accepting second material in same bin.
    The only requirement to have startegy I is that same materials can be placed in same Bins (sorry but dont need fixed bin)
    Thanks

    Hi Hiren,
    You are correct I forgot to mention that in my earlier reply. Actually with out storage unit you can store only one quant in a Bin. So it can add stock to the same quant if we use addition to existing sock feature. If the material batch combination changes it cannot use the same quant, so it wont be able to add the stock to existing quant. If a new quant is to be stored in the same BIN it has to be storage unit managed. To in nutshell multi material multi batch your scenario can be achieved with storage unit managed storage type.
    For storage unit setup you can refer below link.
    Storage Unit Management - Warehouse Management System (WMS) - SAP Library
    If you find this useful please close the tread.
    Regards
    Abhishek

  • Base unit of measure is different from Idoc to purchase order toSAP System.

    Hi Gurs,
    vendor send a purchase order for confirmation through EDI, the base unit of measure in the Idoc is PA( Parcel). For this same material the unit of measure in R/3 system is PC.( Piece). I got a error on this.I checked in CUNI, In Unit of measurement ST (PC) is already assigned to  unit PCE in EDI. But i dont want to change the  Conversion.I need this also and I want to create a new conversion ST(PC) is assign to PA( Parcel).
    Please help in this.
    Is it possible to maitainthe ISO-code PA into table Units of Measurement of Dimension?
    Edited by: Vadivel Karalam on Nov 1, 2010 1:13 PM

    Hi,
    You are getting the error because as part of the std ( For ALE/EDI) the unit of measurement that is maintained is PC whereas if you look at another unit of measure that you have mentioned, the std doesn't define anything under the ALE/EDI setup.
    Because of that all the conversions are coming with PC. So pls goto general settings and check unit of measure menu. There for each of your units, there is a section for ALE/EDI, set up the relevant UoM and the issue should get resolved.
    Hope it helps.

  • BOM Unit Different from Base Unit of Measure

    Dear PP Experts,
    I have following Scenario in some of wires which are .
    Base Unit of Measure - Coil
    Conversion Factor
    1 Coil - 100 Metres (Already Maintained in mm01)
    Suppose, one manufacuring item consist of 0.5 Metre of Wire. We want to use Metre in BOM, how can we use it.
    Please help, full points if helped.
    Ishu

    Dear,
    In material master you maintin alternate unit as meter in plant data/storage 1 as unit of issue This will default this unit in BOM item
    In the BOM, in the component enter the above material code and enter the qty as 0.5. system will default meter as the unit of measure in BOM.
    Please come back if required
    Edited by: Rajesha Vittal on Feb 16, 2008 8:35 AM

  • Material Master MATMAS IDOC and base unit of measurement

    Hi
    We are using SAP standard material master IDOC type MATMAS05 to trigger IDOC. Our material master is having base unit of measure as "G". We are not using ISO unit of measurement. But Material master IDOC, segment E1MARM is populating base unit of meaurement (MEINS) as "GRM".
    Any idea why IDOC is picking ISO unit of measurement instead of material master base unit of measurement.
    Any idea how to send base unit of measurememt as "G" instead of "GRM" in DOC segment.
    Thanks
    Nilesh

    There are ISO codes for country keys, currency keys, units of measure and shipping instructions. According to SAP design guidelines, you should use ISO codes for an IDoc if they are available. When you set up the IDoc, the SAP codes have to be replaced by ISO codes.
    http://help.sap.com/printdocu/core/Print46c/en/data/pdf/BCMIDALEPRO/BCMIDALEPRO.pdf

  • Changing Base Unit Of Measure in Material Master

    Dear All,
                  We need to change the base unit of measure of certain materials who have been assigned inspection plan. We have deleted the material from Inspection Plan and later even the plan. But still the system not allowing to change the BASE UNIT OF MEASURE. The error thrown by the system is : Material is assigned to inspection Plan.
    Please guide in this regard as changing the material for us will be a very cumbersome act.
    Regards

    Hi Rohan,
    Please check 'display errors' in MM02 when you are trying to change the BUoM. It will say what prevents you from doing that.
    Please check:
    http://www.sap-img.com/materials/change-base-unit-of-measure.htm
    BR
    Csaba

  • Same  Material with different itemcatagory groups

    We have 3rd party manufacturers that make product for company and sometimes they send the finished product back to company and other times they will drop ship it to one of our customers.
    this scenario we need to have the same material with different itemcatagory groups
    i tried to create same material with different storage locations, but it's possible but the thing is when i change the item catagory group for the material , the same is applicable for 2nd same material, my requirement is i need 2 different itemcatagory for the same material,  hope u understand my requirement
    i will be expecting your possible replys.
    Thanks & Regards
    Venkat.Dhanemkula

    Hi Venkat..
    Please explain it more clear manner..
    With whatever i have understand, i think you scenerio is manual 3rd party order processing.
    In that case the material that you normally deliver yourself but occasionally need to order from a third-party vendor, you can overwrite the item category during sales order processing.
    Keep only one material and specify the item category group NORM in the material master.
    If, as an exception, you use a third-party material, change the entry TAN to TAS in the ItCa field when processing the sales document. The item is then processed as third-party item.
    hope it helps you.
    Regards
    Harry

  • Tcode MB1B (Transfer Postings) material with different Valuation class

    Hi,
    is it possible to avoide tcoce MB1B for material with different valuation class?
    Materia1 (001000) has valuation class: 3000
    Materia2 (300000) has valuation class: 7900
    I don't want allowed MB1B with Material1 (3000) to Material2 (7900).
    Thanks.
    regards, Dieter

    Hi,
    Yes, It is possible to avoide tcoce MB1B for material with different valuation class.
    Regards
    Md.MahaboobKhan

  • Base unit of measure can not be changed since EAN is already assigned.

    Hi,
    We would like to change the UOM from EA to SET .In order to tag MM # as BOM Header and ZCEN (Serial number profile)but the error massage appears as below print screensystem is not allowing to do so ,throwing following error message:
    "Base unit of measure can not be changed since EAN is already assigned."
    Could you help to resolve the same.
    Thanks,
    Amit

    Hi,
    Thats correct you must be getting Error message M3 341 ,
    EAN international article number is tied with material number in basic data view with EAN Category and seperate number range
    EAN is a standardized unit that uniquely identifies a material relating to a unit of measure or type of packaging.
    The International Article Number (EAN) is assigned by the manufacturer of the material. In this case, the EAN identifies the
    manufacturer uniquely. A company can assign EANs using "in-store" numbering techniques known only to the company.
    If you still want to change UOM you need to first remove the EAN assigned..please explore further if you have internal number range
    for EAN or external ..etc
    Thanks
    Diwakar

  • Item category N: Only base unit of measure EA allowed,Message no. CO344

    Dear all
    I am facing  the following  issue,
    Item category N: Only base unit of measure EA allowed
    Message no. CO344
    Diagnosis
    You have entered a unit of measure for a component of the item category N which does not correspond to the base unit of measure maintained in the material master record.
    Procedure
    Use the base unit of measure maintained in the material master record.
    Please give  the solution  for how do handle that issue.
    Thanks&Regards
    K.Muthukamatchi

    Hi
        My requirement is: The item category N should allow me to use alternate UOM.
      When i checked with Item category L, the system allows me to use alternate UOM. I need the same to work for Itm category N also.
    Through  forums, i found that, in standard SAP, system will not allow to use alternate UOM for Item catedory N.
    Is there any config settings to be done for my requirement?
    Kindly do the needful.
    Thanks & Regards,
    K.Muthukamachi

Maybe you are looking for

  • Deleting a photo from Photoshop Elements 11 editor

    I deleted a photo from Photoshop Elements 11 organizer. How do I delete it in Photoshop Editor?

  • Change report process theme v6.0.2

    Wnen we generate a project report, the process is defaulted to "business analyst". How do I change this to be colorBPM? I assume there is a properties file or css for the report generation somewhere but am not sure of the location.

  • O.T. For All Font Fans - Mac Only

    FontDoc produces out a Rich Text document containing samples of all your fonts. Save it or print it for future reference. http://www.versiontracker.com/dyn/moreinfo/macosx/24912

  • Visual Composer Query

    I have already created a system and am able to successfully pull data from the sql database source. However, I have a query that I want to plug in to restrict the recordset. Can somebody tell me how I can do this? Thanks in advance.

  • I like the new Peripherals community

    https://discussions.apple.com/community/peripherals Alas, I don't see a separate sub-community called Keyboards.   Yes some with Bluetooth wireless keyboards might post in Bluetooth, but Bluetooth can mean anything Bluetooth to many.    And Apple doe