Follow-up material

Hi,
I need to search the material X for wich in field 'follow-up material' of material master data, I inserted the code Y.
Is there a transaction , standard report or search help in mm03 that can help me?
Regrds
Sabrina Paolini

Hi,
It can be searched with SE16 => MARC => filed to select NFMAT it might help you...
Regards,
Ninad Kshirsagar

Similar Messages

  • Multi level follow up material in BOM

    Dear All,
    Our client have a requirement for multi lvel follow up material in BOM.
    for example
    BOM for Finish Good made of A.
    if material A is depleted then used material B
    if material B is depleted then used material C
    if A and B have stock used A(higher priority)
    I tried to used follow up material in MRP4 and BOM but it can not be used for multi level like this case.
    Is there any solution for this?
    Best regards,
    Fred

    Hi anyway I tested the BOM master data like this
    F/G 1 Master Box
    |--- A 10 PCS  Alt Group Z1  Priority 1 Usage 100% Strategy 2 (100% Check)
    |--- B 10 PCS  Alt Group Z1  Priority 2 Usage 100% Strategy 2 (100% Check)
    |--- C 10 PCS  Alt Group Z1  Priority 3 Usage 100% Strategy 2 (100% Check)
    Stock A is depleted
    Stock B enough
    stock C enough
    Expected result F/G only used B 10 PCS
    Actual result is
    F/G 1 Master Box
    |-- A 10 PCS
    |-- B 10 PCS
    |-- C 10 PCS
    Do ou have ides how should the percentage in BOm is maintain?
    Best regards,
    Fred

  • What will happen if don't set follow-up material in material mas view MRP4

    Client get the information that some materials will not manifacture until one date. After this date, client want this material can't create BOM or PO anymore.
    I gave solution for set delete flag for this material so that when create BOM or PO error happens.
    But client want to use discontinue material in material master view MRP4, so that he can enter the last date when this material is out of use.
    Will discontinue material in material master view MRP4 can meet this requirement? enter discontinuation indicator and date then after this date will not create BOM or PO.

    As per my understanding discontinuation is related only to MRP (how system handles requirements).
    http://help.sap.com/erp2005_ehp_04/helpdata/EN/b1/c044d1439a11d189410000e829fbbd/frameset.htm
    If you want to disallow the creation of BOM / PrdOrd / etc, you have to apply to the suggested material status control or to your own solution (marking the material for deletion), etc.
    n my opinion discontinuation makes sense if the real situation is also discontinuation (you have a real follow-up material). In this case you can use it to manage the requirements properly.
    Edited by: Csaba Szommer on Sep 2, 2010 1:37 PM

  • Process Order is not picking the follow-up material

    Hi Gurus,
    We have changed a BOM by discontinuing a component and giving a follow-up material with the valid from dates as 18/5/09.  and then MRP is run on that nignt  ( mrp job set to run daily in the back ground). and on 19/05/09 a Process Order is created from the planned orders genereated by the MRP run.
    now, we found that the new componenet (follow-up) is not copied into the process order, but the old compomemt (discontinued) is removed. 
    MRP parameters are correctly defined (Planning mode is set to 2) .  Please let me know if we are missing anything.
    Thanks,
    N

    Hi
    Pl ensure that the Following requirements have been met before you can use the discontinuation functionality:
    1) Both materials must be planned using MRP.
    2) The base unit of measure of the follow-up material must be the same as the base unit of measure of the discontinued material.
    3) You must enter discontinuation data for the discontinued item and follow-up data for the follow-up item.
    and Also refer the SAP link for Complete Details
    http://help.sap.com/saphelp_45b/helpdata/en/b1/c044d1439a11d189410000e829fbbd/content.htm
    Regards
    Brahmaji

  • Full BOM component qty when follow-up material is effected.

    Dear Experts,
             How to ensure discontinuation / follow-up is implemented on FULL BOM's
             component qty, and not partial.
              Example : A requires 3B, and B is follow-up with C upon discontinuation.
                             Planned order of A should only contain 3B or 3C, not mixture eg. 1B
                             and 2C etc.
              How can the control be implemented ?

    Dear Pradeep, Rajesha & all,
          Assume BOM of "A" indicates component B qty 10 is follow-up with component C qty 10.
          Material B (say, balance 1 qty) is received into Store Y (MRP Relevant). Thus to exclude material B from MRP, we have to manually transfer stock to store X (Not MRP Relevant).
          This would mean, we have to perform manual tracking such that this store transfer is done, to force SAP to direct to material C, so that we either accept 10B or 10C in planned order and nothing else.
         Not forgetting, I could have another follow-up in another bom such that 1B = 1C. Thus, the material 1B I transfered to store X (Not MRP relevant) can actually be use in this case.
    <b>    Thus, from BOM explosion, is there a way to control discontontinuation to follow-up, based on full component qty specified in BOM ?</b>
    <u><b>My Setting as follows :</b></u>
    <b>(1)</b> Material Master of "B" : MRP4 specify (a) Discontinuation Indicator "1", (b) effective-out date, (c) Follow-up material "C"
    <b>(2)</b> In Bom of "A" (parent of "B") :
    - Item "B", indicate discontinuation group "A1"
    - Create item "C" and indicate follow-up group "A1" and qty to be follow-up upon B discontinuation.
    Thank you for your guidance !

  • Same discontinue and follow up material?

    I have used before this function having a follow up material with indicator 1 and effective-out date. However, this time I have 3 materials A, B, C.
    The logic I want to use is the following but I'm not sure if SAP supports this:
    A = discontinue material and B = Follow-up material. Using indicator 1
    B = discontinue material and C = Follow -up material. Using indicator 1.
    So far, SAP is not allowing me to have B as discontinue and follow-up material at the same time. Any insights?
    Thanks for your help.

    Hi Lee,
    If you try to set the discontinuation for a follow-up material, then error message "Message no. 61224 -Multi Level Discontinuation not suported" will be generated when you try to run MRP. Refer Note 398238 - Error message 61224 for parts provided
    For more information on Discontinuation data, refer Concept of Discontinuation Data - Material Master and BOM
    Thanks & Regards,
    Ramagiri

  • Alternative item with follow-up material

    Hi,
    I have a finished product X for that component A-1 pc and B-1 pc is required.
    Now A cannot be used in next year thatu2019s why my client wants 1) to issue 2 pcs of A instead of A-1pc and B-1 pc until the stock of A is available. 2) If the stock for A is not available then only it goes for B.
    1) I have used alternative item grp with priority: 1, strategy : 2, usage probability 200% for A and priority: 2, strategy : 1, usage probability 0%  for B
    System issues 2 pc of A only
    2) Also maintained follow up material as B so if there is any shortage for A then system is looking for B.
    Problem is with the above setting the follow up material and alternative item is not working together.  System issues only 1 pc of A if I maintained B as follow up material. If I maintain only alternate item then it issues 2 pc of A but at the same time it will not check B if any shortage occur.
    Pls help.

    Hi,
    [Kindly check this link |http://help.sap.com/saphelp_47x200/helpdata/en/a0/1016bd4c8311d189520000e829fbbd/frameset.htm] which has information of the below.
    Alternative item group
    You can only define discontinuation data for a stock item or variable-size item that is not assigned to an alternative item group.
    Once you have maintained discontinuation data for an item, you can no longer assign the item to an alternative item group.
    reg
    dsk

  • Discontinuation indicator and follow up material.

    Hi,
    I am facing the strange issue for which i need your expertise. The requirement is like:
    1. "X" material is discontinued and "Y" is as follow-up in two plants A & B. Discontinaution group and follow-up group has also been assigned in the BOM.
    2. Now The client want to reverse the settings . means "Y" should be discontinued and "X" should be follow-up in both plants A & B.
    Now I have removed the discontinuation indicator and follow up material from "X" in both plants. But when I am going to discontinue the "Y" material and putting " X" as a follow-up material, The system is giving the message "The specified follow-up material results in recursiveness
    Message no. M3609
    Diagnosis
    You have entered a follow-up material. However, the BOM explosion for the follow-up material leads to the discontinued material, resulting in unpermissible recursiveness.
    Procedure
    Enter another follow-up material or cancel the entry.
    Please suggest me where I am missing in my settings and what is the reason for this message.
    Regards
    Deepak Sharma

    Dear ,
    Check the following  :
    1.Validity of the Bill Of Material or any deletion flag is set in the present BOM.
    2.Please check the following SAP notes :
    Note 161742 - Consulting note: BOM recursion/low-level code 999
    Note 839879 - Trace 'BOM is recursive'
    Note 139517 - Recursiveness for follow-up materials
    Note 42891 - Recursiveness check
    Hope this will help you to figure it out
    Regards
    JH

  • Discontinued part and follow up material

    Dear Guru,
    How to use discontinued and follow up material with effective date. I am using MTS Scenario.
    Please help.
    Regards,
    Sanjay Sahoo

    Hi Sanjay,
    refer to the below link, it should answer your query:
    Re: Discontinuation Indicator - Need Guidance
    In addition to the above details:
    In material master for the material which is being discontinued, in MRP-4 view you need to maintain discontinuation indicator, effective-out date & Follow-up material.
    If you need any additional info, revert.
    If helpful award points
    Regards,
    Vivek

  • Cost-Roll take follow-up material upon discontinuation effective-out date ?

    Dear Expert,
    If we use discontinuation/follow-up material, during Cost-Roll (CK11N), SAP will take default cost from discontinued material even if follow-up material is effective. 
    <b>How to make SAP take cost of follow-up material after/on effective-out date ?</b>
    <b>Example :</b>
    Parent "A" contains component "B" qty 3, to be follow-up with component "C" upon discontinuation of "B" on effective-out dated 1st Nov'07, and like-wise to take std cost of "B' before 1st Nov'07 cost-roll.
    Thus, when I roll cost in December, I hope SAP would calculate for std cost of A to include std cost of "C" (for cost-roll after 1st Nov'07).
    <b>Setting :</b>
    <u>Material Master of "B" MRP4 view :</u>
    - Discontinuation Indicator = 1
    - Effective-out date = 1st Nov'07
    - Follow-up Material = "C"
    <u>BOM of Parent "A" :</u>
    - Component "B" indicate discontinuation group "A1"
    - Add component "C" and indicate follow-up group "A1".
    <b>Thanks for your guidance !</b>

    Hello,
    We are having the same issue: is a BOM for costing the only way to handle this ? Controlling dept. here fear they wouldn't be maintained as accurately as the production ones (and they are right). We were also thinking to set the phased out materials (B in your example) as cost irrelevant when you add to new material in the BOM...and start costing the father (A in your example) directly with the new component. I would appreciate a lot to hear other examples of dealing with this issue if anybody has.
    Thanks a lot,
    Olivier

  • Production Order with follow-up material unble to save due to error CKBK009

    Dear Expert,
    When we apply discontintion/follow-up material setting, production order is not able to save. <b>Error message "CKBK009 - No price could be determine for material....."</b>.
    <b><u>SAP Help indicates :</u></b>
    "No price could be determined for material .......... Message no. CKBK009
    <b>Diagnosis :</b>
    The system could not determine a price for valuation view 0, because no valuation 
    strategy succeeded from valuation variant 006.
    <b>System Response :</b>
    Since the input quantity is zero for this material item, the costing result is not   
    affected by this error at the pricing stage.
    The standard system defines this message as an error message. However, you
    can use user-defined error management to specify that the message is a warning
    or an information message, or that it is not issed at all.
    <b>However, in Controlling's User-Defined Error Management, CKBK009 is already  warning only.
    What other setting is needed ?</b>
    Thanks for helping !

    Dear all,
            Manage to solve the problem via Note 1008643, per following.
           <b> THANK YOU for all your guidance & Have a nice day !</b>
    <u><b>NOTE 1008643 :</b></u>Symptom
    In a production order error message CKBK-009 is raised during cost calculation.
    This message cannot be modified into a warning or information message.
    Other terms
    CKBK009, CO01, CO02, CO03
    Reason and Prerequisites
    System design
    Solution
    Please make a new entry in TA OPR8 with the following characteristics:
    ErrorManagID    ApplicationArea   MsgNo  MinMsgType    MaxMsgType
    PPCO            CKBK              009
    Then run TA OPR4_PPCO to modify the message type for CKBK009.

  • Significance of Follow-Up Material in MARC with Interchangeability

    Dear All,
            We have a field 'Follow-Up Material' (NFMAT) in the MARC table in R/3. Can we use this field in our APO Interchangeability.
    (ie.) Maintain the replaced product in this field and use it as Predecessor product in our super session chains (in APO).
    Please clarify.
    Thanks,
    Siva.

    Hi anyway I tested the BOM master data like this
    F/G 1 Master Box
    |--- A 10 PCS  Alt Group Z1  Priority 1 Usage 100% Strategy 2 (100% Check)
    |--- B 10 PCS  Alt Group Z1  Priority 2 Usage 100% Strategy 2 (100% Check)
    |--- C 10 PCS  Alt Group Z1  Priority 3 Usage 100% Strategy 2 (100% Check)
    Stock A is depleted
    Stock B enough
    stock C enough
    Expected result F/G only used B 10 PCS
    Actual result is
    F/G 1 Master Box
    |-- A 10 PCS
    |-- B 10 PCS
    |-- C 10 PCS
    Do ou have ides how should the percentage in BOm is maintain?
    Best regards,
    Fred

  • Error Follow up Material

    Hi all,
    I'm facing this problem:
    I have indicated in the material master data that a material is substituded by another one (follow up material type 1).
    When I create and release the production order the new material is diplayed correctly (the old with quantity 0 and the new one with quantity 1).
    But, when I read the PP master data there is an error : i see in the components the old with quantity 1 and the new with quantity 0).
    The validity date indicated in material master data is 01.01.2011 so in the past. All data seem correct.
    I'm using configurable material and I created the sales order bom with CU51 transaction. So the Production Order reads Sales Order BOM.
    May you help me?
    Thanks.
    MG

    HI, in my system I don't use the availability check.
    I inserted the role PP in my production order type without check but, when i run the Availability check into the production order the follow up material is wrong. I have no error message but the quantity proposed is 1 for the old material and 0 for the follow up. This is the error.
    MG

  • Multiple follow up material

    Hi,
      I hav eone requirement  we have material X  for this in material master follow up material is Y  now user want that for the material Y  they want to add anothere follow up material z  so is it possible  how it works,  now when  I am trying to add material Z as follow up material to Y   system is giving error Message no. MM031
    regards,
    zafar

    Standard system does not support the use of chain of follow-up materials (multilevel follow-up materials).
    There are several checks in FM MARC_NFMAT - you receive one of them when the before mentioned FM calls FM MG_NFMAT_CHECK and it returns with 'X" in variable 'FLAG1'.
    (I receive message M3609 which is triggered from the same FM)
    Edited by: Csaba Szommer on May 11, 2011 8:56 AM

  • The follow up material results in recurssiveness

    HI,
    I have two BOMs one is plant specific production bom
    & the other is group BOM which is engineering/design bom
         Production Bom(plant specific)     
    parent     MO     
    child 1     m1     
    child 2     m2     
         Enginering/desing bom(indepent of plant)     
    parent     MO     
    child 1     m1     
    child 2     m2     
         m3     
    So in material master  of m3  iam trying to discontinue with  discontinuation indicator 1 with follow up material MO
    The sytem is issuing the "the specified followup material results in recurssiveness"
    why the system is throwing this message though m3 is not present in the production bom (which is plant specific)

    Praveen,
    Are you trying to say that if you maintain the material BOM for M0 with M3 as component and a follow up material as M0 again..?
    It will definitely a recursive bom.
    Or is it that you are maintaining a material M3 with follow up material as M0, where the M0 bom has components as m1 and m2 and you are getting this error in this case?
    Please explain clearly..