For 1 process order all the materials to be clubed.

If aufnr is order no then for one order no i would like to club all the three materials.
In bdc how the code can be written???

Dear Srimedha,
First of all I assume Material Ledger is not active in your case.
Kindly understand what Srinivasa is trying to explain.
Your GR should always be with one standard price only. Inspection lot gets created after GR only and quality inspection starts there onwards.
You have got standard BOM and Routing for Good FG and there no seperate Master data exists for Defective one.
IF production is of bad quality that is a loss and you should not book that at a lower cost as the actual cost is the same in the both the case.
I would propose further to maintain split valuation for FG Good and Defective. If there is defective production transfer the same through 309 movement. This will provide tracing and proper explanation.
Explain to the client what they want is incorrect.
Regards,
Divraj Agarwal

Similar Messages

  • Is there any soln to display production line for process order in COOISPI?

    HI,
    When we run COOISPI for planned orders, the field  MDV01 "Production Line" populates correctly (based on the value in the production version associated with the planned order).  However, you run COOISPI for process orders, that same field is now blank.
    Any pointer on how to display MDV01 in case of Process order.
    Thanks in advance

    Thanks for your reply. my requirement is to populate the field value of production line in the CIOISPI report. I have production line assigned to production version. It does display if you see the results for Planned order but not for process order and the 'production line' field remains blank. More importantly i am trying to display the results for the same production version in case of process order,
    Can you plz provide me any pointers or the way we can have production line value if want to display COOISPI for process order.
    Regards,
    Nitin

  • Max stock level and reorder point for all the materials

    Dear experts,
    Is there any standard mm report that will give the details of max stock level and reorder point details for all the materials?
    Thanks in advance,
    Regards,
    Krish

    Your requirement can be pulled from table MARC. I dont think there is a standard report to meet your requirement. You can meet your requirement through SAP Query though.

  • Reg storage location for all the materials in the plant.

    Dear Gurus,
                       In my plant I would like to know the storage location for all the materials in the plant.can u guys suggest me the solution?

    If Stock is there in Each Storage Location then You can Run MMBE Report by Inputting Material & Plant. Then it will Show All the Storage Location Stocks for a Plant.
    Or you can Run MM60 Report Which will give you Detail Report.
    Else you Can Check in MMSC List of Extendable Storage Locations.
    Regards,
    Ashok

  • Need to checks if ASN has been received for all the materials in the

    Hi Experts,
    Can you please give me an idea
    I need checks if ASN has been received for all the materials in the Invoice.
    what filed do i need to check.
    Regd's
    Vardesh,

    Hi Jagadeeswari,
              If you need to check Workflow Trace check Transaction SWU9. This displays all the WOrkflow started on a particular time period we specify. Check Program RSWTTR01 and also table SWT_LOGCAT which could help you. The transaction i have specified displays all the Workflow that has been executed and whether it is been a success or a failure.
              Hope this would help you.
    Thanks,
    Prashanth

  • Material staging for process order

    Dear All,
    Can we use material staging for process orders.
    If possible pls brief the procedure.
    Subbu.

    Using warehouse management /WM) :
    - Create a control cycle for the component, using LPK1. Here you define if the supply will be specific for the order (when weighing takes place in the warehouse) or for released orders (normallu full packages of components and weighing is done at plant level). Reference to a supply area.
    - The resource used in the operation has a reference to the supply area.
    - Components have material master views in WM for the selected storage type
    Then, when releasing the orders run LP10 - LP12 to generate the Transfer requirements for the raw materials. These TR will be converted to Transfer Orders and Confirmed, so the stock will be moved to your supply area.
    Using Inventory Management, none of the above is required. You can use MF60 to move materials from General Storage Location to Shop Floor SLoc.
    Regards

  • Using 05 inspection type, all the materials moves to inspection lot

    Dear SAP Gurus,
    Using the 05-inspection type in material master for by product material, all the material goes to inspection lot.
    how to control the inpection lot movement, i have set a plan that the inspection will be carried through  a workcenter,but it moves all the materials to inspection lot.
    Since all the materials are moving to inspection lot, i have changed my inpsection type to 02 (goods issue), but the problem is,  i couldn't able to record the results for the created inspection lot.
    Kindly guide me and correct my process flow,
    Thanks in advance
    Thanks and Regards,
    R.Diwakar

    Dear Guru,
    Thanks for your response
    Sorry for not so clear ....
    My scenario is that, the user requires to have a inspection lot for their By-Product. during the production order, after manufacturing say 30000 material, for them the 30000 material should directly posted to the unrestricted usage and a sample maerial should go to inspection lot, where same will be inspected and transfered to unrestricted usage, through QA32.
    Based on their requirement, i have set the inspection type -05 in material master and a workcenter specifically created for the quality testing, so that a sample quantity can be produced and flows to the inpection lot,
    but it doesnt works,the produced materials are all going to inspection lot.
    Kindly guide me on this,
    Thanks in advance
    R.Diwakar

  • Issues during Component Batch Determination for Process Orders

    Hi,
    I am encountering a strange issue during component batch determination of process order.
    1. During creation of process order, when I execute batch determination, systems does determination based on strategies we have set and when I click on Copy it gives an error
    "Log cannot be saved: Object/subobject not specified"
    Message no. BL201
    *Diagnosis
    Log save cancelled because at least one log contains no object or subobject.
    Object and subobject are needed to classify application logs because there are several log types. Only a few logs are managed in main memory at runtime, so this classification is not needed.
    If the logs are to be saved in the database, object/subobject must be specified for later retrieval.
    Procedure for System Administration
    Object/sub object can be passed when a log is created (function module BAL_LOG_CREATE) and changed with BAL_LOG_CHANGE.
    The possible values for object and sub object must be configured in transaction SLG0.*
    If I save the order with CRTD status and come back again in change mode and do determination, It works fine.
    Again when the order is in REL status and do the determination, It gives the same error.
    This happens only for a specific plant, In other plants batch determination works in all scenarios.
    I checked for all plant related Config for batch determination and coudn't find any discrepancies.
    Please advise how to resolve this issue. Thanks in advance for your help
    Regards,
    Aheesh

    There Is no direct solution for your requirement just try this work around.
    While defining the batch determination search strategy for process order in COB1, there is one column Quantity proposal where you can attach the Routines (This is written in ABAB code )  make use of this, define New Routines with ABAB help to fulfill your requirement. Try this if found useful award full points.
    Regards,
    Ajay Nikte

  • Reverse Goods Receipt for Process Order

    Dear All,
    Please tell me how to reverse the Goods Receipt for Process Order for which already QM is cleared for that Particular Lot.
    But Confirmation is still yet Pending.
    I tried MIGO - Cancel - Material Document. But it is showing a message "Process Order already processed".
    Regards
    buss

    Hi,
    Use t code MB31
    Movement type 102
    Stock type = Unristricted use.
    Reverse by entering above information then you have to manually cancel the inspection lot.
    Regards,
    Vishal

  • Order type dependent parameters for process order

    Hello friends,
    In Order type dependent parameters for process order (T.C COR4), there is subscreen for Process data documentation.Inside it we have three options :a) Batch Record Required
                                                                        b) Order Record Required
                                                                        c) No Process Data Documentation Reqd.
    Through F1 help whatever information i have got regarding them, is not cleared.
    According to it, if i select Order Record Reqd, than first of all i will have to delete (archieve) the order record than only i can delete (archieve) the process order.The same is with Batch Record Required.
    So according to it if i want to delete the  process order than first i will have to delete order record.So guys may i know which order record firstly i have to delete?Than only the system status for process order will not have the status ORRQ (Order Record Reqd).
    And one more thing friends,if i select the third option No Process Data Documentation Reqd than which process data documentation system will not create?Or what will happen if  i select this third option?
    Thankingy you guys in advance.

    HI
    For process data documentaion pls check the following link:
    http://help.sap.com/saphelp_47x200/helpdata/en/89/a43ea8461e11d182b50000e829fbfe/frameset.htm
    Thanks

  • For process order matrix

    Hi All PP Gurus,
    Scenario from production client:
    Issue:
    For process order number 6300355; material code 15010163 the assay calculation is not correct.
    Process in use:
    Process order is created through tcode COR1 and Transaction code ZACOR2 is used for update of requirement quantity, i.e. assay calculation. The quantity calculated against batch no. 0001004480 is not correct. The correct value is 14.013.
    can u please help me regarding this issue?????

    your question looks to be very vague as you are giving order no/material no/ batch no which no member can view. explain more detail about your scenario and issue so that somebody may try to help. sorry for putting my view in direct manner.
    Thanks
    JK

  • Partal release for process order

    Hi,
    My scenario is like the below.
    I have one operation in my operation in my master recipe.So all the materials with the requirement quantity wll be assigned to that operation. Now I have created a order with 20 FG quantity.But I have RMPM according to FG quantity of 10 as per BOM.I want that the system will allow me to release the order partially for that 10 Fg quantity.
    Waiting for your kind reply.
    regards,
    kaushik

    Hi,
    Partial conversion is already considered but the issue with the same is explained below.
    Suppose you have an order for 50.the minimun lot size is 30.You have RM in stock for 35.Now according to you my planned order should be partially converted and the remaining planned order will be of 15 kg which is unconveratble.Now i can change the error msg of conversion of planned order lower than lot size maintained in production version.But this will violate the business requirement.
    I think the problem is clear with you now.
    regards,
    kaushik

  • Issue during CO43 for Process Orders

    Dear SAP Experts,
    I have a scenario where in Process Order is created in COR1, after that in COR2 i entered the qty then i did the confirmation for process order, now MIGO is done till now everything look fine with no errors.
    But now when i do CO43 for this Order in the result screen no data is displayed.
    Kindly advice.

    Hi All
    Try to check if the confirmation was really posted (KOB1 check production and consumption).
    Sometimes the production/consumption posting is waiting for correction in transaction COFC/COGI.
    If it´s OK, try to review your costing sheet for overhead.
    In CO43, go to Extras - Settings and review the rules. Maybe this order doesnot fits the rule to calculate overhead.
    Be sure you are not running again by mistake.
    Regards.

  • Progress confirmation for process order

    Hello to all,
    I want to use the progress confirmation functionality for process order. I know that it is possible for production orders, but I couldn't find respective transaction for process order. Do you know if it is possible to use progress confirmation for process orders.
    BR,
    Nikolay

    Thanks for your inputs, but they are not useful!
    COR6 - it cannot be used once the order is confirmed at phase level;
    COOISPI - it's a report
    COR6N -it is the standard transaction for process order confirmation
    I want to do so-called "unplanned milestone" for process orders, something similar to CO1F for production orders.
    BR,
    Nikolay

  • Batch determination for process orders

    Hi All,
    My requirement is complete batch batch is proposed in process order  batch determination even though the requirement is of less qty.
    For example the required qty. for component XYZ is 20 units but the available batch is of 40 units. Now requirement is that no batch splitting should happen & complete batch of 40 units is determined.
    This is required to do Material quantity calculation.
    regards,
    Mohit Goyal

    There Is no direct solution for your requirement just try this work around.
    While defining the batch determination search strategy for process order in COB1, there is one column Quantity proposal where you can attach the Routines (This is written in ABAB code )  make use of this, define New Routines with ABAB help to fulfill your requirement. Try this if found useful award full points.
    Regards,
    Ajay Nikte