Forecasting: Different customer forecasts under one material

I am currently provided with customer forecasts which are used in planning and I input on our SAP system using T.Code MD61 create or MD62 change.
Right now, if two different customers give forecasts for the same Item code they are added together in the forecast.
e.g.
Customer
Item Code
Jan-14
Feb-14
Customer 1&2
Item1
7000
7000
Right now there seems to be no way to keep forecasts for different customers on different lines once one line is active.
How can I set the forecast to look like below?
Customer
Item Code
Jan-14
Feb-14
Customer 1
Item1
5000
5000
Customer 2
Item1
2000
2000

Hi GM,
Post this discussion under SAP ERP Manufacturing - Production Planning (SAP PP)
In MD61 demand is maintained against the material not againt the customer. If you want to maintain the demand and identify the demand specific to customer then use strategy 50 for the FERT material. In that case entire demand eg 7000 can be mantained in MD61. Sales order can be created seperately for customer 1 5000 qty and customer 2 2000 qty. On MD04 screen you can see the customer specfic demand qty which you can convert partially to poduction as required. Incase of strategy 50 once sales order is created then only convertable planned order against the sales order demand gets created upon MRP run. Production will be order based.
Thanks & Regards,
Ramagiri

Similar Messages

  • Different Document types under one company code

    Hi All,
    I am working on a project where i have to implement SAP PS in 3 Company codes.
    I have a requirement that Different number ranges should be used in different codes for creating PRs.
    In OPTT,order category 20 is used with NB,here i can change 1 Document type.Is it possible in std SAP to create different Order cat for 20 and then we can link diff document types for diff order cat of type 20.
    Regards
    Muzamil

    Hi,
    The assignment of the PR document type in Account assignment is only one is possible you cant assign multiple document type here.
    The Automatic PR raised from the PS is only one assignment is possible,so you can inform your MM consultant to create the seperate document type say ex ZNB-- PR for the Project which is common for all the three company code & assign this with the PR assignment in account assignmet filed.
    Regards,
    Raj

  • What's the best way to sample multiple AI's with different sampling rates under one task?

    I'm using a PCI-6221 card and CVI 7.1.
    I have a tri-axis vibration sensor and two other pressure transducers.
    I want to take 10k samples from each vibration axis at 80 kHz. This is
    possible by configuring the scan rate of the "vibration task" to 240
    kHz. (The card maximum is 250 kHz).
    I want to take 1k samples from each pressure transducer at 250 kHz. This happens very infrequently.
    Each measurement is required by a separate task.
    I thought I could do this by setting up three finite tasks (1
    vibration, 2 pressure), but DAQmx won't let me run more than one AI
    task at a time. I've read other posts here, and I realize I have to
    add/remove physical channels on-demand.
    What is the best way to optimize this setup so that I'm not hogging up system resources?
    Should I do the following?
    1. Stop the task
    2. Remove the vibration channels from the task
    3. Add in a pressure channel
    4. Configure the pressure channel
    5. Start the task
    6. Take the pressure samples
    7. Stop the task
    8. Remove the pressure channel from the task
    9. Add in the vibration channels
    10. Configure the vibration channels
    11. Start the task
    Also, the vibration portion is running in finite mode, but I'm looping
    it. Should I switch it to continuous and run the "DAQmxReadAnalogF64"
    to sample the latest 10k samples. (If the task is continuous, would I
    pull the latest 10k samples, or would I pull some old buffered samples
    instead?)
    Thank you,
    Nobody

    Hello Nobody,
    If you configure your task timing to acquire a finite number of
    samples, then you can only read the number of samples that you
    specified in your configuration.  Once you try to read more
    samples, you will receive the error you are seeing.
    If you configure your task timing for continuous acquisition,k then you
    can read samples indefinitely.  Any given DAQmx Read will read the
    oldest unread samples in the buffer.
    If you are going to be switching between different tasks, you will definitely need to stop one before you start the other one.
    I hope this helps!
    Eric
    DE For Life!

  • Move AR Customer Sites into different Customer Account under same customer

    We are going to upgrade the ERP AR from 11.5.10 to 12.1.3.
    We would like to rearrange the customer account and customer site.
    For example,
    There is one customer Name "ABC" and customer site "DS01", "DS02", "OM01", "OM02" in 11.5.10.
    Target to rearrange the customer site into 2 customer account as follow,
    Customer "ABC"
    Account : "Account 1"
    Site: "DS01", "DS02"
    Customer "ABC"
    Account: "Account 2"
    Site: "OM01", "OM02"
    However, there is existing transaction link to those site already.
    Please advise if it is possible to split some AR customer sites into two account by data patch or by upgrade.
    Thanks!

    During upgrade, how are you migrating the data into R12 from 11i

  • Two services under one roadmap

    Dear All,
    Here we have a requirement that  to bring two or more standard ESS Services and one custom service under one roadmap
    Is it possible?
    thanks in advance
    sera

    Hi Sampath,
    thanks for your reply,
    here the requirement is we wanted to integrate four servicces under one roadmap
    for eg:
              1. complete timesheet application  (ESS Application)
              2. apply for leave                          (ESS Application)
              3. Custom Application  1                 (ESS Application WD based)
              4. Custom Application 2                (ESS Application WD based)
    The requirement is that all should be in one roadmap, that is this all should be done one after the other.
    Is it possible that the employee will also be able to skip applications.
    kindly show some light
    sera

  • Create Forecast from one location porduct to other location product

    Hi All,
    I have a business scenario trying to design process in APO -DP.Two Plants in R/3 (1001 and 1002).
    Plant-1001, produce  material A using raw material B.
    Plant -1002,  Produce C  and sale to plant 1001. Physically material B and C are same but in R/3  material  B and C  are different numbers.
    I am trying to design this scenario in APO- DP  like whenever Plant 1001 run forecast for material A, it should generate forecast for material B(raw mat in 1001) and material C (finish product in 1002).
    I tired to understand if APO-DP BOM functionality can be used but in this case system asked me maintain material C in plant 1001, which i am trying to avoid.
    This seems to be common business scenarion. I'll appreciate any quick advice or help to understand how to map it in APO-DP.
    OR
    Is there anyway to transfer forecast from one location product to another different loaction product.
    Thanks
    Kumar

    Hi Kumar,
    1) Your scenario seems like realignment of location products.
    2) You can achieve this using realignment planning in APO DP
    3) The transaction to do this is /SAPAPO/RLGCOPY
    4) Here, the history of one location product will get copied or maintained to transfer
    to another location product
    5) You can select one or more key figure data to get copied to your new
    location products from the existing history.
    Regards
    R. Senthil Mareeswaran.

  • System calculates the year forecast in one colume.

    hi
    i have query of planning book. i wanna  see the total year forecast in the end of the colum that is how much i forecasted, under this table we have some months which tells like jan, feb, march,..till one year.below i have given example how the client want to see the his total forecast into one colume/field.(u03A3 Fiscal 2011). actually we are not maintaing any key figure for this one or we are not maintining any auxallary kf. the clinet want to see the total one year forecast in one colume. it should be updated automatically.
    M 07.10     M 08.10     M 09.10     M 10.10     M 11.10     M 12.10     u03A3 Fiscal 2010
    250     300     350     400     450     500     2250          
    like above example the system needs to display the total forecast in the kf of it and the total budge display of its kf. how i can map.

    Hi ,
    You need to first create appropriate fiscal variant . A detailed SDN forum thread is available as below:
    What is the significance of columns while creating Fiscal Year Variant?
    Then you need to use this FY variant appropriately in the planning bucket profile.
    In the data view then, you need to configure the visisble from field appropriately so that you willl see complete finance year's periods.
    If you have aleready configured Ro totals, then you will see the FY totals,
    Practically, if say, we are in middle of fianance year, then next FY planning also we need to do . This we can do in another data view, with appropriate planning buckets profile.
    I hope this will help.
    Please check and confirm.
    Regards
    Datta

  • I have two separate itune accounts under two different email accounts and would like to combine them under one account.  Is this possible and if so, how do I do it?

    I have two separate itune accounts under two different email accounts and would like to combine them under one account.  Is this possible and if so, how do I do it?

    If you go to Settings > iTunes & AppStore , you can sign out from your account, and sign in with the one you've used to purchase apps.This will not remove any apps you already have on it.
    Then you can go to AppStore and download apps you've purchased (either via "Purchased" button in "Updates", or simply search for them and download them.
    That way you can have multiple accounts' apps on your iPad. When updating, you will be prompted for the credentials for account you've purchased given App with.

  • HT1918 Hi - I think I have different apple devices recorded under different apple IDs. Now I would like to consolidate all the devices under one Apple-ID.  I have tried to do this going through the manage accoung like, but it timed out - could somebody he

    Hi - I think I have different apple devices recorded under different apple IDs. Now I would like to consolidate all the devices under one Apple-ID.  I have tried to do this going through the manage accoung like, but it timed out - could somebody help, pls

    Purchases of multple Apple ID accounts cannot be merged as noted here >  Frequently asked questions about Apple ID

  • Material Code with Different profit Centers in One Plant

    Hi Experts,
    There is one requirement in my project that given in detailed below please:
    Material code                     Plant                       Profit Center
    MSR009                            2011                       2011
                                                                            2012
                                                                            2013
    one material code, one plant and 3 profit center,. the material should trigger with different profit center from sales order to revenue booking..
    So is it possible to map that configuration in SAP, if yes please guide me
    Thanks and regards
    Madhu

    Hi,
    Profit centre is trigured through
    Material master
    Company code + Cost element
    When you create sales order it id derived form material master if you maintained in material master
    Else at the time of invoice creation and account posting it is derived from company code + cost element combination(Which is mentianed in OKB9 by FICO people)
    kapil

  • HT204053 How do you get everything on an iPhone under one iTunes account to a different iTunes account?

    How do you get everything on an iPhone under one iTunes account to a different iTunes account?

    You cannot

  • HT2905 I have multiple album titles of the same name with different artists. How can I get them to go under one album title again?

    I have multiple album titles of the same name with different artists. How can I get them to go under one album title again?

    In iTunes(on a Mac or PC) just tap on 'Albums' rather than 'Artists' and you'll see them all together.
    You may find that there are songs mislabelled. In which case right tap on the Album or Artist and tap 'Get Info', then change to the correct name and the songs will join the rest of the songs for that Artist or Album.
    Then resync with your iPhone and all will be well.

  • How can i upload two different logos for 2 sub sites [which falls under one super site ] in share point 2013 ?

    hello,
    How can i upload two different logos for 2 sub sites [which falls under one super site ] in share point 2013 ?
    thanks,
    Jay

    Hi,
    I understand that it applied first logo to all other sub sites.
    Please make sure that you change the logos in the subsites.
    If we change the logo in the root site, the logos in the subsites will be changed at the same time.
    However, we can change the logo in the subsites separately.
    We can go to a subsite, click the Site Sitting-> Look and Feel-> Title, description, and logo->Insert Logo->select a picture, then it will has a different logo than the root site.
    Then go to the other subsite, click the Site Sitting-> Look and Feel-> Title, description, and logo->Insert Logo-> select another picture, then it will has a different logo that the first subsite.
    Best Regards,
    Linda Li
    Linda Li
    TechNet Community Support

  • HT204053 Can I have 2 different countries billing address under one Apple ID? I mean 2 countries credit card for payments at the same time under unique Apple ID.

    Can I have 2 different countries billing address under one Apple ID? I mean 2 countries credit card info for payments at the same time under one Apple ID.
    I do travel very often to overseas. I'm having problem with few apps that can not be updated when I'm using another countries store. I do have 2 countries billing address. So when there is an update I need to switch my county & billing address for few selected apps. I was wondering if I have option to add both countries as my billing address that would be great under same Apple ID. Is this option available?

    You can only have one credit card and billing address on your account at any one time.

  • How to create a Platinum,Gold and Silver Customer and how to set different price for a single material based on customer?

    Hi All,
    How to create a Platinum,Gold and Silver Customer and how to set different price for a single material based on customer?
    Assume Material is Pen.
    While creating Sales Order in VA01 how to bring different price for the same material for Platinum,Gold and Silver Customers.
    Kindly help me out.
    Thanks,
    Renjith Jose

    A good place to start is http://www.javaworld.com/javaworld/javatips/jw-javatip34.html
    Also, do a search in this forum on HttpURLConnection. That class allows you to use POST method to send form data to a web server.
    "Hidden" variables are only hidden in HTML. The HTTP that gets POSTed to the web server doesn't distinguish between hidden and not hidden. That is, the content you would write to the HttpURLConnection.getOutputStream() would be something like:
    hidden=1&submit=ok(Of course, the variable names would depend on what the web server was expecting from the form.)
    Also, be sure to set the Content-Type request parameter to "application/x-www-form-urlencoded"

Maybe you are looking for

  • How do I delete songs & podcast from iPhone using iTunes on new MacBook Pro

    I have recently bought a new MacBook Pro after years of using PC. First thing I have to say is that I love it. I've had a couple of problems here-and-there but these have been teething issues which these discussion boards have mostly helped me resolv

  • Need some hints for evaluating data from Central Performance History

    Hi Experts, I am pretty new to all the BI-stuff and hopefully someone can provide some hints. I got the requirement to read data (CPU usage/peaks) from central performance history of "system a" into "bi system" to generate overviews/charts/etc Now I

  • Can't extract pages from PDF in 9 Pro, but coworker can in 8.

    I have a PDF that I need to extract 3 consecutive pages from, but extract pages is greyed out.  However, my co-worker was able to extract them with no problem using Adobe Acrobat 8.  Any ideas why she can, but I can't?

  • MORE D2G screen issues...

    Ok, so I am having quite a few of the same problems listed in the 'screen issue' threads for the Droid 2, and D2G. The phantom finger on the screen, back/home buttons sometimes don't work, unable to scroll a web page without it zooming in, and when i

  • Photosmart 7510 wont print black

    Help!!! on my last tax forms for my business and I can't get the black to work even with a new cartridge!!!  screen shows a full black but when i print a report for the ink it shows nothing!!!  i have to have my printer fast!!!