From release 10.2.0.3 to 10.2.0.5

Hi Gurus!!
Currently I am working with the release 10.2.0.3 but I wanna change to the release 10.2.0.5 what I need to do? Wich patches need to apply??
It's the same licence or Do I need to pay another type of licence??
Thanks in advanced...

You need to download the 10.2.0.5 patch from Metalink (or whatever it's called now, MOS).
There isn't a separate charge for patches (above what you already pay for your support contract).
The instructions for applying the patch are contained in the patch file itself. Be sure to read and follow the instructions.

Similar Messages

  • I've upgraded the Discoverer from release 4 to 10.2.0.3

    Hi guys,
    I've upgraded the Discoverer from release 4 to 10.2.0.3 on two of my test systems.
    the difference between the two test system is that one is SSL enable and the other one is not.
    On the test system that is not SSL enabled users can access Discoverer via EBS fine but
    on the tests system that has SSL enabled users cant so now they have to go directly to
    the Discoverer link to access it. I've logged an SR with Oracle and they told me to edit the ssl.conf file
    for the Discoverer side which I did and I placed the file directories and the locations of the certificates in that ssl.conf.
    How can I get Discoverer to through EBS when SSL is enabled.
    Thanks

    Hi,
    Firstly, you need to check that the ICX: Discoverer Launcher system profile has the correct https url to launch Discoverer.
    Rod West

  • Upgrade Oracle Database From Release 11.1.0.6.0 to Release 11.2.0.1.0

    Dear Experts ,
    I need the procedure to do the upgrade Oracle DB From Release 11.1.0.6.0 to Release 11.2.0.1.0
    We have RAC Setup, OS windows 2003 R2 Server Service Pack 2
    I have 3 instance Epprod, Epval, Mnlptprod
    I am using the Same server as an application server as well.
    Server Specification
    E5540 @ 2.53GHz
    2.53 HGz, 15.9 GB of RAM
    Please your help highly appreciated

    Hi,
    Please refer the following links,which may help you in upgradation:
    http://www.oracle.com/technetwork/database/upgrade/best-practices-for-upgrading-11gr2-174946.pdf
    http://docs.oracle.com/cd/E14072_01/server.112/e10819/intro.htm#i1008321
    http://www.ludatou.com/?p=287
    http://www.oracledba.org/upgrade/Upgrade_11gR1_RAC_to_11gR2_RAC.htm

  • API for Work Order status from Released to Unreleased or any user defined s

    Dear All
    Is there any API for to change work order status from Released to Unreleased or any user defined status.
    Take care
    Aamir

    Hi Ben,
    As query is resolved, you should close the Thread after rewarding to the Concerned
    Thanks,
    Manish

  • EBS Upgrade from Release 11.5.10.2 to 12.1.3 - SLA Issues

    Hi,
    Before upgrading our EBS from Release 11.5.10.2 to 12.1.3, Patch 5233248 has been installed , and Concurrent Program "SLA Pre-Upgrade Program" has been registered and enabled correctly (See Note : 427639.1 )
    While running this Concurrent Program , on EBS 11.5.10.2, through "General Ledger Super User" Responsibility, the program ran several seconds.
    Parameters Used :
    Migrate all sets of books: Yes
    Start Date: 01-JAN-2010
    Are there Pre-Requisits while running this Concurrent Program ?
    Regards,

    Hi;
    Please see:
    R12.0 and R12.1: FAQ for the SLA Upgrade: SLA Pre-Upgrade, Post-Upgrade, and Hot Patch [ID 604893.1]
    Regard
    Helios

  • HOW TO UPGRADE FROM Release 10.2.0.1 TO 10.2.0.2

    Hi,
    HOW TO UPGRADE FROM Release 10.2.0.1 on Linux TO 10.2.0.2 ? Should we apply a patch ?
    Thank you.

    thank you. Of cours, I looked at metalink site for
    RDBMS patch familly, but I did not find any for
    upgrading from 10.2.0.1 TO 10.2.0.2
    Regards.
    Message was edited by:
    user522961What's your target OS ?
    Why are you specifically want this version?
    As you can see from Oracle download page, some OS come with 10.2.0.2 directly.
    http://www.oracle.com/technology/software/products/database/index.html
    Oracle Database 10g Release 2 (10.2.0.3) for Microsoft Windows Vista
    Oracle Database 10g Release 2 (10.2.0.1.0) for Microsoft Windows
    Oracle Database 10g Release 2 (10.2.0.1.0) for Microsoft Windows (x64)
    Oracle Database 10g Release 2 (10.2.0.1.0) for Microsoft Windows (64-bit Itanium)
    Oracle Database 10g Release 2 (10.2.0.1.0) for Linux x86
    Oracle Database 10g Release 2 (10.2.0.1.0) for Linux x86-64
    Oracle Database 10g Release 2 (10.2.0.1.0) for Linux Itanium
    Oracle Database 10g Release 2 (10.2.0.1.0) for Linux on Power
    Oracle Database 10g Release 2 (10.2.0.1.0) for AIX5L
    Oracle Database 10g Release 2 (10.2.0.1.0) for HP-UX PA-RISC
    Oracle Database 10g Release 2 (10.2.0.1.0) for HP-UX Itanium
    Oracle Database 10g Release 2 (10.2.0.2) for HP Tru64 UNIX
    Oracle Database 10g Release 2 (10.2.0.2) for HP OpenVMS Alpha
    Oracle Database 10g Release 2 (10.2.0.2) for OpenVMS Itanium
    Oracle Database 10g Release 2 (10.2.0.2) for Solaris Operating System (x86)
    Oracle Database 10g Release 2 (10.2.0.1.0) for Solaris Operating System (x86-64)
    Oracle Database 10g Release 2 (10.2.0.1.0) for Solaris Operating System (SPARC) (64-bit)
    Oracle Database 10g Release 2 (10.2.0.2) for z/Linux
    Oracle Database 10g Release 2 (10.2.0.2) for z/OS (OS/390)

  • Purchase Requisition Creation From Release

    Dear PM Gurus,
    For Manual material availability Check to work before release, the Purchase Requisition check is to be set to Immediately in SPRO-> Define Change Docs and Collective PR or Activating Pr from Now On from Maintenance Order. The issue is that I want to restrict the creation of Purchase Requisition to Release of Maintenance Order but what is happening is upon saving the Maintenance Order, the PRs for all non stock materials are created and I also want the manual availability check to work before release.
    Simplifying above details:
    I want Manual material availability check to work and PR generation from release both in my Maintenance Order to work..
    Regards..

    Hi DP Singh,
    I had seen the configuration settings that you are telling me but you see the Problem is:
    If in Define Change Docs, Collective Purc. Req. Indicator, Operation No. Interval, you define the Res/PReq Indicator as Immediately, then the Manual Material Availability Check would work accurately but upon saving the Order, System would generate the Purchase Requisition.
    and If in Define Change Docs, Collective Purc. Req. Indicator, Operation No. Interval, you define the Res/Preq Indicator as From Release, then the Manual Material Availability Check would not work as no material is as such MRP relevant till the time of releasing the Order but the Purchase Requisition would be created only when the Order is released.
    Now What I want is both the Manual Availability Check to work and Purchase Requisition Creation From Release, but this is not possible according to the Standard SAP System. A workaround could be that I configure the automatic material availability upon release and configure the Res/Preq indicator as From Release, that way the material availability would be checked when the order is released and Purchase Requisitions would also be created from Release but still the Manual Availability Check would not work.
    The Ideal Solution should have been configuring the Res/Purchase Requisition Indicator for all Non Stock Materials to be From Release and the Res/ Purchase Requisition Indicator for all Stock Materials to be Immediately. This way your manual availability Check would work for all Stock Materials and Purchase Requisition for all Non Stock materials would only be created upon Release. But this  But still this is an ideal solution not the actual solution for standard SAP does not give you the flexibility to do such a setting in customizing or using Enhancement.
    The Work Around Solution given by SAP is as follows: The system provides the following workaround:
    After you change the indicator for materials planning-relevance to
    "immediately" you can execute the availability check as required. You must
    not save the order or network.
    Regards,
    Muhammad  Usman Kahoot
    Edited by: Usman Kahoot on May 27, 2010 1:32 PM

  • How to users from releasing a contract that they have created

    Hi,
    can someone tell me how tp stop users from releasing a contract that they have created and or changed.  It should be released by a different user.
    I've been doing some investigation, and it looks as if function module EXIT_SAPLEBND_002 (SAP Enhancement M06E0004) might be the User-Exit that I may need. Does anyone know if this is correct?
    John

    Hi,
    You posted your query to wrong forum, should be posted to MM forum.
    Anyway probably your users have the authority of transaction code ME35K (Release) and authority object M_EINK_FRG (Release Code and Group (Purchasing)) to be able release contract that they created.
    Regards

  • Restricting a production order from releasing

    Hi,
    How can i restrict a production order from releasing if material is not available?
    Regards,
    samir
    Edited by: wadajkar on Jun 2, 2010 2:51 PM
    Edited by: wadajkar on Jun 2, 2010 2:51 PM

    Hi,
    In t code OPJK at material avialibility check section maintain '3' i.e. do not release if components are not avialable.
    Regards,
    Vishal

  • Capacity Requirement From Released Production Order

    Hi PP Gurus,
    Can i limit capacity requirement only from released production order ? I don't want to count requirement from production order that just created but not yet release.
    Regards,
    Arman Lie

    Dear Arman,
    As a standard practice the system creates the capacityrequirements once the production order is created.
    Check this,
    When a production order is created the following actions are carried out:
    ·        A routing is selected, its operations and sequences are transferred to the order
    ·        The bill of materials is exploded and the items in the bill of material are transferred to the order
    ·        Reservations are generated for bill of material items held in stock
    ·        The planned costs for the order are generated
    ·        The capacity requirements are generated for the work centers
    ·        Purchase requisitions are generated for non-stock items and externally-processed operations
    Regards
    Mangalraj.S

  • Hrms system from release 11i (11.5.10.2) to R12 (12.1.3) or higher

    ours is a public sector company and we want our company to upgrade our hrms system from release 11i (11.5.10.2) to R12 (12.1.3) or higher...
    As an MIS-IT department we have to demo the new functionality available for release 12 for hrms -
    Modules are :
    Core HR, SSHR,Payroll, OTL, PMS- performance management system, iLearning and iRec
    could any one out there clearly highlight what are the new features in the above modules and how we can capitalize on all the new functionality in our company.
    pls advise,,,,we are having some serious issues here in explaining our management.

    Jenny_Gomez wrote:
    ours is a public sector company and we want our company to upgrade our hrms system from release 11i (11.5.10.2) to R12 (12.1.3) or higher...
    As an MIS-IT department we have to demo the new functionality available for release 12 for hrms -
    Modules are :
    Core HR, SSHR,Payroll, OTL, PMS- performance management system, iLearning and iRec
    could any one out there clearly highlight what are the new features in the above modules and how we can capitalize on all the new functionality in our company.
    pls advise,,,,we are having some serious issues here in explaining our management.Please see the links referenced in this thread --> Document for differences between Financials of 11i and R12.
    https://blogs.oracle.com/stevenChan/entry/ebs_data_model_1213
    https://blogs.oracle.com/stevenChan/entry/ebs_seed_data_comparison_reports
    Thanks,
    Hussein

  • SAP OS kernel upgradation from release 700 to 710

    Dear Sir,
    We are upgrading kernel release 700 (185)  to 710 (160).
    In this we are getting an error of saposcol i.e saposcol is not started automatically when we run startsap.
    Currently we are running our application on Kernel release 700 patch level 185.
    Should we have to upgrade application pathes after to upgrade the kernel release 710 patch level 160 ?
    Is there any dependency in between SAP Application Patch and SAP Kernel Patch or we can run the application on current application patch level, kindly suggest
    Regards,
    Mushtaque

    Dear Mushtaque,
    I am not clear on your purpose for kernel upgrade from release 700 to 710. Your SAP_BASIS and SAP_ABA version showing as 710 or 700. If it is 700, there is no reason to change your kernel release. The latest patch is 201. You should go for this patch incase release 700.
    Also, as a post processing steps you need to run saproot.sh with root user after kernel upgrade.
    Also please find below link for saposcol options.
    http://help.sap.com/saphelp_46c/helpdata/en/c4/3a6c40505211d189550000e829fbbd/content.htm
    Regards
    Gautam

  • UCCX upgrade from from Release 7.0 to 8.5

    Planning to upgrade from Release 7.0 (1) SR04ES02_Build023 to Release 8.5.11003-32 (SU3). Does anyone have a simple step-by-step guide, powerpoint they can share? I understand first I have to apply a SR5?
    Any assistance would be greatly appreciated -

    Hi Lewton,
    You need to bring your current system to UCCX 7.0(1)_SR5 and than perform the upgrade to 8.5 version.
    Unified CCX 8.5(1) offers a direct solution for Cisco Unified CCX 7.0(1) SR5 or
    7.0(2) to upgrade to Unified CCX 8.5(1).
    Hope this helps.
    Anand
    Pls rate helpful posts !!

  • Reject a Collectivly PR' S from Release strategy

    Dear All,
    How to reject a Collectivly PR' S from Release strategy.
    Regards
    Aamir

    The line items may be approved collectively as a whole or individually, but, each line item must be rejected individually.
    http://help.sap.com/erp2005_ehp_03/helpdata/EN/75/ee14d755c811d189900000e8322d00/frameset.htm

  • Calling batch script from Release Management for Visual Studio 2013.

    Hi All,
    I need some guidance on executing\ calling a batch script from Release Management for Visual Studio 2013 as one of the activity during release and also let me know whether the tool provides the log of this kind of execution.
    Thanks in Advance,
    Manoj

    Hi Manoj,
    To run batch script during release process when use Release Management for Visual Studio Online, you can use Command Line Runner" tool which allow user to run comtom command line. You can check in by clicking Inventory tab then tools in Release Management
    client. You can check this
    page for more information about release manage tools to deploy an app. Thanks for your understanding.
    Best regards,
    We are trying to better understand customer views on social support experience, so your participation in this interview project would be greatly appreciated if you have time. Thanks for helping make community forums a great place.
    Click
    HERE to participate the survey.

  • Change the status of the request from Released to un released.

    Dear all
    Some requests were created with no target system and were released.
    these requests are to be transported to our Production System.
    Is there any other way to transport these requests?
    things I tried.
    1. I tried to find the files in Cofile and datafile but could not find in trans folder.
    2. tried to add the objects to new requests but facing problem while adding the key to the request.
    Regards
    Mahesh

    Hi,
    you have created the requests as local requests, it means you haven't mentioned Target system it will be treated as local requests so it wont create Cofiles and Datafiles.
    and you can use the option Transport of copies and check. actually u can't change the request from the Rleased to Unreleased.
    you have to create new request that's the only way if your not able to copy the objects to the new request or if the transport of copies wont work.
    -Srinivas.korva

Maybe you are looking for

  • If I have two iTunes accounts can I combine all purchases into one account ?

    I have two active iTunes accounts but I would like to combine my purchases into one is that possible.".?

  • WHY YOU SHOULD NOT USE SKYPE (and where to file co...

    Approximately two weeks ago, my account was blocked for no apparent reason. I contacted customer support and they didn't know why it was blocked, but told me to go through the account verification process. I asked to speak to someone on the phone to

  • Brazil - Withholding tax in A/R credit memos / notes

    Hi all, We have implemented a proto-type of SAP ERP in Brazil to check out the taxes and in particularly the withholding taxes (WHT). We now have a test customer and test vendor for which withholding taxes have been activated and as a result, a withh

  • Why can't I access the iTunes Store (iTunes 10.4.1)

    Every time I launch the latest version of iTunes and click on iTunes Store, I get the error message "We could not complete your iTunes Store request. You do not have permission to access the requested resource." In smaller print it says "There was an