Fulfillment situation of materials in MRP screen

How to find/check the fulfillment situation of materials in the MRP screen ?
Is there any BAPI function module to find it ?

I would start by checking the function modules that start with MD_.  Specifically check out MD_STOCK_REQUIREMENTS_LIST_API
Regards,
Rich Heilman

Similar Messages

  • In Material Master Screen,functionally what is Mixed MRP in the MRP Screen.

    In Material Master Screen,functionally what is Mixed MRP in the MRP Screen.Pls explain its functionality

    THis indicator will define whether the material is available for the following....
    Subassembly planning with final assembly
    Gross requirements planning
    Subassembly planning without final assembly

  • I have Photoshop cs6 Ext on an ASUS laptop. How can I increase the font size of the contents of the FILTER Panel situated on bottom left of screen. The font size is extreamly small and almost unreadable. I have changed display parameters, not the resoluti

    I have Photoshop cs6 Ext on an ASUS laptop. How can I increase the font size of the contents of the FILTER Panel situated on bottom left of screen. The font size is extreamly small and almost unreadable. I have changed display parameters, not the resolution, to no avail.
    David.

    Paragraph breaks are good for readability. ;-)
    Have you noticed any difference between your MacBook and others at the Apple store? Wondering whether this is a configurable setting at the system level, i.e., DPI.
    You can default Firefox to a larger zoom level to avoid having to zoom every page. You'll still be able to adjust the size for individual sites as needed. It sounds as though you are aware of these add-ons:
    * Default FullZoom Level: https://addons.mozilla.org/firefox/addon/default-fullzoom-level/
    * NoSquint: https://addons.mozilla.org/firefox/addon/nosquint/
    There are some discussions about changing coming in Firefox 22 (I think) to address higher density displays like the Retina display. So perhaps there will be a built-in setting to address this in the future.

  • How to assign materials to MRP Area

    Dear All,
    How to assign materials to MRP Area
    Thanking you
    Regards
    Prashant

    Hi
    Go to SPRO
    Production Planning>>>> Master Data>>> MRP AREAS>>>Define MRP Areas, Create New MRP AREA
    Then come to Material Master ( MM02)
    Go to MRP1 view
    In this Tab, Go to MRP AREAS BUTTON
    Here you can assign the MRP AREA to that material
    For any other info, Plz revert
    Regards
    BRSR

  • Customize the MRP Screens

    Dear All,
    Please let me know whether we can customize the MRP Screens or control the flow of MRP screens. I have created a userdefined form for creating a Work Order using UDO. I wanted to know if we can include this screen in MRP wizard.
    Regards,
    Noor hussain

    Noor,
    I guess that it could be possible to get the output of the MRP wizard to a UDT, but to get that i guess u need to use the UI screen values, Please try it and check,
    And to add work orders from the wizard i guess in the button click event of the MRP wizard u can try to add the work orders.
    But i am a bit skeptical on how the above would work. 
    Hope it helps,
    Vasu Natari.

  • Single PR for multiple materials thru MRP

    Hi,
    Is there any setting to achieve a single PR, for multiple materials thru MRP?
    Regards,
    Sattuj

    Hi,
    I don't think it is possible to create single PR for Multiple materials through MRP.
    Depending upon the Lot size, Individual/collective Indicator in MRP 4 view, you can club the requirements for the same material and have a single PR.
    Hope this helps..
    Regards,
    Siva

  • MRP Screen Default values

    Dear All,
    Can we make MRP screen Parameters Default.
    If Yes How?
    Please let me know.
    Thanks
    Regards
    RAghu

    Dear Raghu,
    Not in front of SAP
    But in MD01 or MD02, Just input required parameters you want then go to header tab
    Settings > Save
    Now every time same parameters will appear
    Regards
    Madhu

  • Calling MRP screen of material by using report

    The requirement is that when I click material on report, MRP view (From MM02 transaction code) will be opened for that material.

    Hi,
    Use this :
    set parameter id 'MAT' field <material code>.
    call transaction 'MM02' and skip first screen.
    Hope this will help you
    Regards,
    Moon

  • LTP excludes materials with MRP indicator of storage location

    Hi All,
    SAP Note 208017 explains the reason for LTP not taking into account the MRP
    indicator of a storage location for a material. Has anyone tried a work around for this issue?
    <b>We basically are looking for a snapshot of operative MRP a week back from current date</b> and I thought LTP can be used, but it plans at the plant stock level. Since we have service inventory managed at storage location level and its exculded in operative MRP, we cant have consistent results with LTP being used for my purpose.
    Any inputs appreciated
    Thanks

    Hi,
    1. I dont think we should use the LTP Forthe purpose of your requriement
    2. Since i think you will be runing the MRP at certain frequency say daily,weekly etc
    3. LTP is a strong functionality for the forward planning , which means for a medium or long term in the forward direction
    4. For the purpose of snap shot we shouldnot use this ...
    may be pp gurus in the forum will be giving  us some reply which you are looking for
    reg
    dskumar

  • In Material Master Screen,functionally what is Requirement Group in the MRP

    In Material Master Screen,functionally what is Requirement Group in the MRP Screen.Pls explain its functionality

    Hi,
    The safety time / actual range of coverage ensures that the planned warehouse stock covers the requirements of a defined number of days. It therefore serves as a time float and thus works alongside the safety stock, which acts as quantity float.
    The system simulates bringing the requirements forward by the specified number of days and the planning for the receipts, created for these requirements in the planning run, is also brought forward by this number of days.
    Prerequisites
    ·   You have set the Safety Time indicator in the material master record (MRP 2 View) to define whether the safety time is only to apply to independent requirements or to all requirements.
    ·    In the material master record (MRP 2 View), in the Safety Time/Actual Range of Coverage field, you have entered the number of workdays by which the requirements are to be brought forward.
    ·    If, in addition to this actual range of coverage, you also want to define a different number of workdays in certain periods or a safety time less than one day then, in Customizing for MRP in the activity Define Period Profile for Safety Time/Actual Range of Coverage you can define a period profile and assign it to the material in the material master record.
    Regards,
    Vijay

  • Deleted materials shows in mrp list

    Hi,
    I have two requirement
    1. How can we remove all deleted materials from MRP list.
    The deleted material does not display in planning file entry.
    2. Is there any report to see the MRP LIST with Exception message (Not MD05,MD06, MD46)
    Please guide me
    Regards,
    Sanajy

    Hi,
    After you have marked a material for deletion you also need to take it out from planning (MRP type "ND").
    If a MRP list exists for such a material, you need to erase it specifically, since MRP will not do it automatically.
    Regards,
    Mario

  • MD07 - MRP: Why shows me materials without exception messages?

    Hi Everyone!
    I need MD07 to shows me only materials with exception messages. I have 700 materials with MRP and the materials without messages are messing my analysis. Is that possible?
    Thanks in advance!!
    Ignacio

    Venkadesh,
    Thank you very much for your answer. When I go to Plant Parameters there's no Exception Messages setting under any of the 6 sections (Environment, Master Data, Planned Orders Reporting, Planning Run or Performance).
    Could you please put some light on this I feel Alone in the Dark, je. I'm using R3 4.6C
    Thanks in advance.
    Ignacio

  • Mrp not taking materials in to consideration.

    Hello,
          I am running MRP for the first time for the plant. when i run MRP its not picking all the materials in the plant.  I am using NETCH planning. but when i run MRP for each material its working good. why is this happening.  what should I do

    Hi Deepu,
    I think problem is due to planning file entry is not maintain for all the Materials.
    MRP is carrid out during MD02 that means Planing and Planning File entry both are activated, but problem might be is Materials are created before MRP that's why auto maintanance of entry in planning file is not activate for those materials.
    So what you have to do is maintain planing file entry either by using MD20 or by schduled job using T.Code OMD0.
    Regards,
    Dhaval

  • How do i display Materials by an MRP Controller?

    I tried using MD07,MD05,MD06 and i think MD16 all this displays the materials by the specific MRP controller but you cannot export from these displays.
    MMD7 is not configured to work in our system because there are no values set up for the MRP profile and this is a compulsory field that must be entered for this report to run.
    Is there any way to run a report of Materials by MRP controller?Also i need report that'll give me access to export the displayed report in an excel format.
    Please help...thanks

    When they changed Oracle versions, did you have to create a new data source in ColdFusion Administrator?  If so, there is a setting under "Advanced Settings" to enable CLOB support, and that probably didn't get turned on.
    -Carl V.

  • Reg....MRP Run Materials

    Dear Friends
    i have 300 finished materials now i updated forecast for 50 materials in MD61 and i am going to run MRP in MD01.
    How can i get  MRP run  list only for these 50 materials
    pl guide me
    Thanks
    selva

    Dear Selva,
    1.Is your requirement to get the MRP list for the 50 materials after MRP run or else to run MRP only for the 50 materials for
    which demand exists?
    2.If your intention is to run MRP only for the 50 materials means you can activate MRP run user exit(M61X0001) and run MRP
    based on MRP controller.
    3.If your requirement is to get the MRP list for the 50 materials,you can check this report MDLD or else from MD06.
    Regards
    Mangalraj.S

Maybe you are looking for