Hi to All,
My name is Samad Farooq, Currently we are using the SAP version 4.6C. We are using Funds Mamangement.
How can we change the superior center for the fund center, if it contains budget (object ) on it. For eg. Cost Center is 214010001 and it has superior center 214. Now 214 also has a budget, how can we change the superior center 214 for the cost center 214010001. This Cost Center also has a actual posting on it.
Thanking You All in Advance.
Samad Farooq Dandiya

Hi, there is no standard solution for this case

Similar Messages

  • CHanges to Funds Center HIerarchy not reflected in STS

    Hello,
    I wonder if the changes that I made to say Funds Center hierarchy should be automatically reflected in STS. Currently when I upload new hierarchy to BW from R/3 my hierarchy never gets updated for STS. Is this a normal procedure that I have to manually re-import hierarchy in BW to STS, or this is abnormal?
    Thank you

    In my experience the changed hierarchy has to be re-imported to the STS subplan.
    (Even if the hierarchy was automatically changed, it would still be necessary to assign names, functions,  to the new elements).
    Regards Stephen

  • Extracting Funds Center Hierarchy from R/3 to BW

    Hello Experts,
    The goal is to extract Funds Center hierarchy defined in R/3 table FMHISV, field FISTL (Funds Center) to BW.
    On the BW side we have 0FUNDS_CTR InfoObject setup which is compounded with 0FM_AREA (Financial management area), which is FIKRS field in FMHISV table in R/3).
    I have tried this document -
    http://www.bwexpertonline.com/archive/Volume_03_(2005)/Issue_08_(September)/V3I8A2.cfm
    ad this SAP note - 134975.
    I seem to setup everything that is asked in those 2 documents,  but when I run the load, nothing gets loaded (only the top text node).
    Am I missing any step? Do I have to define a set in R/3 manually, etc. Do i need to mofidy my ABAP code?
    Any help would be aprpeciated, esp step by step guide.
    Thank you

    In the tcode GS03, click on F4 help of set. Now in reference table name/field name enter your field name. If hierarchy is Set hierarchy you will get it in the F4 help list.
    KJ!!!

  • Fund Center Hierarchy Extraction

    Hi all, we are trying to extract all the fund centers under a node maintained in the fund center hierarchy. Anyone can advise any SAP standard function module can be use to achieve this result. Kindly advise. Thanks.

    Hi,
    You can try using FM_FICTR_READ_MULTIPLE.
    Regards,
    Eli

  • Fund Center Hierarchy was messed

    Dear all FM expertise,
    I don't know what happens with the Fund Center Hierarchy. I test create fund center and delete fund center. I don't know what happens to the system then now i can't recover the fund center hierarchy. When i use transaction FMSD , now the status of all fund center (excluding top fund center) is no assigned (red label) and is in the same level as top fund center. when i activated it and move it to the right place, the system gives error as "Function not allowed: Budget was assigned for funds center ..." . I check the individual fund center, the hierarchy set is correctly. when display the hierarchy, shows only top fund center. I tried to activate it and save but the system shows Error in the ABAP Application Program.
    Have anybody a good advice?

    Hi,
    I am not sure how familiar are You with sap internal functionality and if it is allowed to use it just so. Look e.g. in the thread
    https://forums.sdn.sap.com/click.jspa?searchID=6455527&messageID=3489098
    Be very carefull with the table fmhisv - if one hierarchy "connection" looses, the hierarchy will be missed. It is very important that parent,next and sibling have correct data in this table. Perform the editing just on Your own risk.
    Good luck
    Alexey

  • Budget carry forward- giong up in the fund center hierarchy

    Hi,
    We are about to close year 2008 in the FM. We work with the former budget, and we don't have budget structure.
    When carry forward the commitment u2013 the receiver is the same as the sender.
    But, when I carry forward budget for commitment, the receiver is the upper fund center in the hierarchy.
    The budget is not where the commitments are.
    What can I do?
    best regards,
    Edit.

    Hi,
    The budget of year 2008 was entered at the subordinate FC.
    If there is budget in year 2009 at the subordinate FC, the budget carry forward is right (the sender and the receiver are the same).
    Only if there is no budget on the subordinate FC, the budget runs upwards the hierarchy.
    Thanks,
    Edit.

  • How to create a funds center hierarchy

    Could somebody tell me how to create a funds center hierarquy ?
    My idea is to create a hierarchy vaious funs center , not only to create and assign.
    Thanks in advance
    Olga

    Hi Olga,
    Please, use FMSD transaction for this. If you want to create several groups, use FM_SETS_FICTR1 transaction.
    Regards,
    Eli

  • Fund center Hierarchy - automatic refresh in BW possible?

    Hi Friends,
    I have an issue with fund center heirarchy data load.
    Whenever the heirarchy is changed in R/3, the BW load is not picking the new hierarchy instead the old values are getting in BW loads.
    If we refresh the infopackage with the available hierarcy from OLTP, and trigger the load, it brings the latest data.
    Is there by any chance make this automated without manual intervention?
    Please provide your suggestions.
    Regards,
    Ramesh

    Hi Ramesh,
    I have a similar issue.
    I am using a hierarchy created on Funds Center and I have refreshed the data from R/3.
    The new data I get to see in the Query while restricting but when the query is run I still see the old Hierarchy.
    Same is the case with workbook.
    Do you have any input to solve this problem?
    Thanks & Regards,
    Savitha

  • Fund Center & Commitment Item

    What is the difference between Funds Center and Commitment Item ?
    Thank you
    Ravi

    HI
    <b>Commitment Item:</b>
    Commitment items represent the functional grouping of an organization within a financial management area (FM area). Commitment items classify budget transactions and business transactions affecting liquidity into revenue, expenditure, and cash balance items. You can assign budget for particular responsibility areas (funds centers) to the commitment items. Budget is used up as postings commitment items and funds centers with commitment and actual values. Funds reservations and business transactions entered in the feeder systems also affect the budget.
    <b>Fund Center</b>
    Organizational unit within an FM area which represents the structure of an organization (areas of responsibility, departments, projects) in the form of a hierarchy.You can assign budget to funds centers in Funds Management. Budget is used up as postings are made to funds centers with commitment and actual values. Budget is even consumed in Funds management through a reservation of funds or by business transactions entered in the feeder systems of Funds Management (such as financial accounting, materials management).Funds centers in Funds Management are arranged in hierarchies. You can define only one funds center hierarchy per FM area. There is only one top funds center in a funds center hierarchy. Every other funds center has exactly one superior funds center. A superior funds center is defined in the master record of a funds center.
    Cheers
    V.Krishnan
    (Assign Points if useful)

  • Consume budget from upper level fund center

    Hi ,
    PSM-BCS / ECC6.00
    I have created a fund Center Hierarchy,
    I have defined Level 1 fund centers as Budget address and level 2 & 3 fund centers as posting address. I want level 2 and 3 fund centers to consume the budget of level 1 fund center.
    what settings are required to make the above scenario work. Also the otherway, can i restrict  level 2 or 3 fund centers from consuming budget assigned to level 1 fund center.
    I don't know if this is a right approach. Please advice how can i make this work.
    Thanks
    Shekhar

    Hi,
    I have created a strategy for derivation of Budget address and assigned it to the Budget Structure.
    Derivation RULE
    Fund Center --> Fund Center
    FC-B (level 2)  =  FC-A (Level 1)
    FC-C (level 2)  =  FC-A (Level 1)
    Then I have maintained budget for Fund/FC-A/Committment Item in FMBB.
    But when I am posting(FB50) to FC-B, i am getting an error "annual budget exceed for Fund/FC-B/Committment.
    Do I have to do some other configuration or reconstruct or reinitialize or any other steps I should to do?
    Please advice.
    Best Regards
    Chandarshekhar Y.

  • Unable to post FR50 (Original Budget) for New Fund Center

    Dear All,
    We are in ECC6.0 and using Former Budgeting, Our business team created a new fund center and assigned it to cost center in the derivation rule.
    Before they granted original budget using FR50, the business users started posting various invoices, expenses, POs, PRs against the cost center accordingly the Available Budget became Negative.
    Now they are trying to post Original Budget for the new fundcenter using FR50, however system gives an error saying Payment Budget exceeded.
    Please advice how to grant budget in such situations, we had an alternative to reverse all commitments and actuals posted against the fundcenter and grant budget, this worked in our test environment. However in Production we will not be able to do this due to too much volume already posted.
    Is there a way to fix this, note that Availability control is active and not sure why system allowed to post without budget.
    Any pointers, is this how standard SAP behaves or are we missing something.
    We have also checked on master data elements of commitment item/fundcenter.. everythign looks fine.
    request your inputs.
    regards
    Diwakar

    Hi,
    I believe you are using Former Budgeting. Please check below if this is not the cause for your issue:
    Please check the following customizing that you have done in your system:
    SPRO -> Public Sector Management -> Funds Management Government -> Former Budgeting -> Availability Control -> Define Parameters for Availability Control
    See if you have set the flag: Check on lowest budget object with budget in your customizing.
    Please check the documentation about this flag, specially this part:
    "If you do not set the indicator, availability control runs against the first budget object, even if it has received NO BUDGET. This is the setting in the system as delivered."
    You can check also report BPINDAN2_NEW.
    This means that the budget is going to be checked in the first object with budget in your budget hierarchy.
    If this is your case, you have only two options:
    1.- Remove the negative budget you have in the combination of funds center/commitment item.
    2.- Add the Combination funds center/commitment item to the exemption list of AVC.
    I will prefer that you do the first option, as for me sounds strange to have negative budget, but this is one decision that you need to discuss it internally in your company.
    If you choose any of the 2 options above, please do not forget to reconstruct your budget and assigned values AFTER you have done one of the options above, with the following transactions (in this order):
    1.- Run transaction FMBV in order to reconstruct Budget values.
    2.- Run report RFFMRC04 in Test mode in order to check if there is still some inconsistency.
    3.- If RFFMRC04 shows inconsistencies, then run this report in Update Mode.
    4.- Reconstruct distributed values with transaction FM9P
    5.- Reconstruct Total values with transaction FM9Q
    6.- Reconstruct assigned values with FMBV again.
    I hope this helps.
    Best Regards,
    Vanessa.

  • Funds Mangement - Superior Fund Center ?

    Hi
    What is the use of superior fund center, When do we have to use it. I have seen in some of the treads that budget of superior fund center exceeded etc ( coudnt understand why it happens). In cost center hierarchy each node is a cost center group. In this case each node is going to be superior fund center. In what way these hierarchy mechanisms are different and why. Please clarify i am in the process of finializing master data, wondering to consider a superior fund center or not.
    Thanks in Advance
    Chris

    Thank you Eli -
    Can't i derive a budget address if it is not a superior fund center.
    When you say reporting - is it like this - When i run for a superior fund center, does it give me a report considering the subordinate fund center's budget and commit /actuals ?
    Please bear the inconvenience, I wish to test before posting a question but I am in the decision making stage to implement all these.
    Kind regards
    Chris

  • Funded Program Hierarchy

    Hi Gurus,
    My requirement is to extract the 'Funded Program Hierarchy'.
    I could not find the standard Data source available. I checked the Business content, specifically at SAP R/3->PSM->PSM_FM->PSM_FM_IO where Fund, Fund Center, Functional area etc are available.
    I could not find any related post in this forum. Some related post stated that in R/3 ABAP report to upload to the flat file and from there loading into the BW...
    Is that the only solution?
    Appreciate your inputs.
    Thanks in advance.
    Regards,
    Peesu.

    Hi,
    If you want to extract data from Public Sector industrial solution (PSM-FM) then please look at:
    http://help.sap.com/saphelp_nw04/helpdata/en/bf/17b63c71f41d5ce10000000a114084/frameset.htm
    In case of Financials (FI-FM) see here:
    http://help.sap.com/saphelp_nw04/helpdata/en/71/d3143cb1b8be00e10000000a114084/frameset.htm
    Best regards,
    Eugene

  • Unable to derive funds center in F-90 Asset purchase from vendor

    Dear All,
    I have maintained the fund center value in the asset master and also maintained the derviation rule in FMDERIVER for a combination of Cost Center > Funds Center.
    When i try to post asset purchase using F-90 t-code, it is asking me for funds center in the asset line item. The system is not deriving the value from asset master or derivation rule maintained. I am unable to maintain the funds center in the posting as the field is grayed out.
    Request you to kindly provide your valuable suggestion.
    Best regards
    Abishay

    Hello,
    The fund center has to be activated for Account Assignment Type 01 (APC Value Posting)                                                                               
    Maybe note 437076 could help to check the settings in the following IMG activity :
       Activate the account assignment elements for each transaction and 
       account assignment type:                                          
       Asset Accounting -> Integration with the General Ledger ->        
       Additional Account Assignment Objects -> Define Account           
       Assignment Types for Account Assignment Objects                                                                               
    I hope it helps,
    Hélène

  • Derivation of Funds Center from cost center for Asset PR/PO in FM

    Hello Experts,
    We configured new FM area and relevant BCS settings. It is working fine except PR or PO for Account assignment category A.
    Issue: system is not able derive funds center from cost center in the asset master. cost center is not updated in EBKN table for Asset PR.
    we have maintained the following;
    1. Funds center is activated in Asset account assignments
    2. Maintained derivation rule with function module: FMDT_READ_MD_ASSET
    3. Derivation rule for cost center to funds center also maintained
    If maintain funds center manually in PR it is working fine and consuming budget also.
    Requirement: How derive funds center from cost center assigned in asset. I have verified all tickets raised in this forum, but nothing has answered my question.
    Request you to provide solution for above issue.
    Thanks in advance for support.
    Regards,
    Chalapathi

    Hi Venkata,
    You have two derivation rules, first related to Asset function module and second one is related to CC and FC combination.
    You need to maintain the function module derivation rule first then you need to maintain the derivation rule related to combination of CC and FC. Because first you need to derive CC from asset master and then you need to derive fund center with reference to this CC.
    Regards,
    Ankit Agarwal

Maybe you are looking for

  • Printing Problem  Photoshop CS 6

    On my MacBook OSX 10. 8.2  I can't print with my Epson printer. Yet I can print with Photoshop CS 5. Thank's for your help. Nicolas

  • How to stop time machine from backing up encrypted lion partition

    I am using 10.6.8 but I created a Lion partition on the same disk. I am trying out Lion and I do not want Time Machine to back it up. I was able to exclude the Lion volume until I encrypted the Lion partition using Filevault 2. Now when I'm using Sno

  • Photos from computer to empty card for digital photo frame?

    I've downloaded 1,000 photos from my camera to the computer and want to empty the card and use it afresh. Is it possible to then load a selection of photos from iPhoto 6 onto an empty card so that I can play a short selection in a digital photo frame

  • My Pound key is a hash tag

    On my keyboard my NO.3 key shows a pound sign above it............when I 'shift+3' I get a hash sign. How do I change this to a pound sign as showing on the key? thanks.

  • Will iPhone 5 come with old software prior to 7.1 update

    I have the ability with AppleCare to replace iphone5 with bad battery...anyone know if the new iPhone already come with iOS 7 pre loaded or will I have to load it myself?