Generate Delivery Schedules via MRP Planning run

The company wants to create Scheduling Agreements and generate the Delivery Schedules from the MRP Planning run - MRP 2 view via JIT.
Can you generate Delivery Schedules from Schedule Agreements if the company does not have an EDI server or APO set up?
Thanks,

Shirley Globe,
You seem to be putting the experts to the test.
As it was told you, you can generate schedule lines via MRP run. MRP run can be done (e.g.) trough MD01 /MD02 / MD03. Of course, you have to use the proper selection parameters to achieve your goal.
http://help.sap.com/erp2005_ehp_04/helpdata/EN/f4/7d2da044af11d182b40000e829fbfe/frameset.htm
As for how to use SA with MRP please check SAP online help:
http://help.sap.com/erp2005_ehp_04/helpdata/EN/3b/66596eda7b11d1b6330000e8a738dc/frameset.htm
Regards,
Csaba
Edited by: Csaba Szommer on Apr 9, 2009 7:40 PM

Similar Messages

  • Why GR performed on MRP generated delivery schedule line (unconfirmed)?

    Hi Gurus,
    Need some advice from you all, I have a scenario here which MRP generated the delivery schedule lines for material A on 10.08.2011 - 124 KG.
    User review the MRP result and didnt confirm the line, but she added in manual line on 11.08.2011 - 124KG.
    On 11.08.2011, warehouse performed GR on the delivery schedule lines. It's found that GR was actually updated into the delivery schedule line generated by MRP (10.08.2011) and not the manual line confirmed by user. (11.08.2011).
    User is questioning now why the GR able to be performed on MRP generated line which had not been confirmed? Any guru can share with me the fact and good note regarding this on MRP? Thanks!
    Michelle

    Hi,
    Since we are talking here about schedule lines, these are open for GR when the delivery schedule is send to the vendor.
    In your case you had a quantity open for 10/08/2011 generated by MRP, then the user added manually another line on 11/08/2011. After this the user will have transmitted the delivery schedule which makes that both the items where marked as transmitted and thus open for GR.
    Now when the goods come in the system will post against the first open schedule line that is found until this is fulfilled and then switch to the next open line at the moment of GR. So this is why the GR was put against the MRP generated schedule line as this one was the one with the earlier date.
    Regards,
    Peter

  • Safety stock not covered by schedule lines in planning run

    Hi !
    In our organization we are trying to implement scheduling agreements and automatic creation of delivery schedule lines through MRP. We have MRP type PD and it considers the reservations created by PM orders and Production orders as requirement elements. When I do the planning run, it creates schedule lines for the PM order reservations and purchase requisition for safety stock. I need it to create schedule lines for all scenarios. Kindly help and suggest a solution.
    Regards,
    Satya

    Hi,
    Please refer the below links.
    Schedule Lines not getting created in MRP
    Re: No Scheduling line is generated when RUN MRP
    Hope it helps you.
    Thanks.

  • Plor not generated  for components during Heuristic planning run

    Hi experts,
                     i had run planning run PP_02 run in PPDS and i am able to see dependent requirment for componenets but my question is its not generating planned order for my components. Please let me know if i had missed any config.
    Second point is i am planning to run 1. Infinit planning runa nd then finit planning run ( PP-02 and MRP_02).please suggest.
    Third is when i run planning run  (Product heuristic its giving me an error saying it space constrains.Please suugest me.
    Thanks
    Raj

    Hi,
    With the heuristics  SAP_MRP_002: Product planning (plan comp. immediately) , components that are defined as being planned automatically and immediately are planned using a simple lot-sizing heuristic.
    SAP_PP_001 is for Changing orders manually. Better choice may be to use SAP_PP_002: Planning standard lots. We  use this heuristic to create new receipt elements in order to cover product requirements
    regards
    Datta

  • MRP planning run

    Hi experts,
                 During MRP run for  a material ,  open PO quantity is not considered   If  delivery date mentioned in that open PO exceeds 110 days from planning date(MRP run date). If it is less , it considers open PO quantity.  
                 What could be the reason for it? Pls help me out.
    Thanks in advance,
    Rgds,
    jay

    The Planning Horizon entry for your plant must be 110 or more. Check it out in OMI8. Click on the 'Maintain' button after entering ur plant, click on 'Planning Horizon' to see the entry.
    For open PO qty to be considered, try running MRP run with processing key as 'NETCH' in MD02 or whichever t-code u use this doesn't take planning horizon into account.
    Amit G

  • Vendor Delivery schedules

    Dear Experts,
                          We are generating delivery schedules thru MRP .The Schedule agreement doc type is LP.
    No JIT or FRC schedules is applicable as the delivery schedules are generated through MRP.
    now how can i release these delivery schedules to the vendor without workflow.Because vendor is not having SAP.Also client need details of the delivery schedules once sent to the vendor.
    Pls guide me in this matter.
    Regards,
    Anil.

    Hi
    You can take the print out by using transaction code ME9E and send it to the vendor if the message set up is there for message type LPET.
    Hope it helps.
    Thanks/Karthik

  • To generate Schedule lines for scheduling Agreement when MRP is run.

    Hi,
    Please help advise on my following requirement:
    When I run the MRP for 'Single Item - Multi level' (MD02) for a material, I want MRP to generate delivery schedule lines for that material in Scheduling agreement.
    Please advise as to how i can go about with this.
    Regards,
    Manju

    Hi Manju,
    For this you need to set creation indoactor for planning run in SPRO.
    The path is spro-MM-CBP-Carry out overall maintenance of plant parameters-Click on maintain-give your plant-click on external procurement under planning run-here you can give your option for the schedule line creation.
    Traction code is omi8. Hope this will help you.
    Cheers
    Ravi

  • MRP creating multiple delivery schedule lines in PR

    Hi,
    We have activated MRP (type PD) where Purchase requiesition is auto created by system for requirement quantity. We require to optimize delivery schedule in such a way that entire PR quantity is broken into various delivery schedule based on planned delivery time and requirement.  Scenario can be further explained with following example.
    Material Requirement for a month is say 1,25,000 units
    Closing Stock say 25,000 units
    PR Generated by system for 1,00,000 units. The entire quantity is schdulled with only one delivery schedule line as per planned delivery time. 
    The requirement is to generate multiple delivery schedule lines automatically in Purchase requisition based on planned delivery time so that Purchase orders can be placed with system generated delivery schedule lines.
    How can it be achieved ?
    Regards,
    Nirav Kinkhabwala

    Dear
    Are you dealing with Single vendor  where you want Multiple Schedule Line item through single PR  which should be generated through MRP run ??
    What you will have to do is to set up the Outline Agreement or Info Record for your vendor and material and then create the source record for this vendor- material relationship and make sure that this source record is set as MRP relevant. Once MRP is run, the vendor is automatically defaulted to your PRs. If in your material master, you have defined the same purchasing group for various material numbers, then with Transaction ME59, it is feasible that you can combine various PRs of the same purchasing group by flagging onto the 'Per Purchasing Group' indicator checkbox. Make a trial test and let me know how it goes.
    Or you can use Qouta arrabgement in that case for different vendor .Please refer : Multiple Requisition  line itme for Quota arrangement
    Just check and revert
    regards
    JH
    Edited by: Jiaul Haque on Dec 25, 2010 1:52 PM

  • Reg LPA Delivery schedules - MRP

    Hi
    Delivery schedules got created via MRP - LPA document type
    We haven't released to vendor [JIT or Forecast]
    When i manually change quantity in generated delivery schedule, Firmed indicator is ticked as expected
    i am unable to uncheck this indicator when go there change mode it is grayed out
    Please suggest

    SAP Help says 'You can only change it from the planning result. To do this, double-click on the schedule lines in the planning result.'
    Planning result ??
    How do i make changes to firm indicator, Please help

  • MRP delivery schedules when sheduling agreement out of validity

    Hi experts!
    Can anyone tell me how to prevent MRP from generating delivery schedules when the scheduling agreement is expired or the item quantity overtaken?
    Thanks.

    Hello,
    Change the following message from warning to Error and then try
    Application - 06
    Message no - 189 - Schedule line date outside scheduling agreement validity period
    Message no - 067 - Scheduled quantity & & greater than target quantity & &
    Regards,
    Shailesh

  • MRP delivery schedules vs scheduling agreements

    Hi experts!
    Can anyone tell me how to prevent MRP from generating delivery schedules when the scheduling agreement is expired or the item quantity overtaken?
    Thanks.

    hi,
    the data you need from master data are:
    customer: KNVV-EIKTO, supplier account at customer
    customer inforecord: correspondance between customer material and your material number
    Roberto

  • Making delivery date catagory in delivery schedule as week in Sch. agreemen

    Dear MM gurus,
    I am creating automatic delivery schedules in scheduling agreement via MRP run and i am using standard weekly lot sizing procedure. Delivery schedule so created  have 'D' as delivery date category. My requirement is to create schedule via MRP with delivery date category as 'W'. Kindly tell me where can i default delivery date category in delivery schedule lines to week (W). Please post of more information if required. I will be quick to respond.
    Thanks
    Avinash

    Hi,
    If the Lot Size is set to 'W', it instructs the MRP to group all the requirements in a week, considering it as single lot and create
    procurement element to cover these requirements. It has no influence on the delivery date category in the schedule line or date category in any procurement element.
    When the Schedule lines are generated by the MRP run, the default date category is always D (date format). There is no settings/customizing available to alter this behavior.
    Kind Regards,
    Suneet

  • Schedule Line(Delivery Schedule) generation stopped

    Dear Experts,
    We are using Scheduling Agreeements to procure materials from Vendor.We are using MRP(type PD) to generate our requirements.We have noticed that ,for a Schedule Agreement- MRP generates Delivery Schedules accordingly,but if user will try to interven the process by entering a manual schedule line with some quantity,and Fix Indicator is getting fixed,after that MRP is not able to generate Schedule Lines,henceforth.
    We had done the same things earlier,but MRP was able to generate Schedule Lines even after manual intervention by user.We have not maintained Fix indicator in Source List also and the particular material and the Agreement both have been marked as MRP relevant against that Vendor in Source List.
    If we will remove the open delivery schedules having Fix indicator fixed ,after that we run MRP,then the Schedule Lines are getting generated,but for those Schedule Lines(Manual or thorough MRP) having Fixed Indicator fixed and have GRN transaction completed,we would not be able to delete those and also MRP will not be able to generate Delivery Schedules.Please advice what is the reason behind this and share the full concept of Fixed Indicator against the same?
    Regards,
    Soumick

    It looks we encountered very similar problem,one item line in our Scheduling Agreeements can't be driven by MRP MD02/MD41,but if we add another same line item under this SA, this new line can be driven by MD02,and generated delivery schedule line.
    I don't know why. Please give me some light! Thanks!

  • Delivery schedule line number in make to order

    Hi all,
    i am doing make to order scenario with 20 strategy group. In sales order we r defining the different delivery schedule lines.when i run the MRP and getting the plan orders for all the FG material and semifinished material, the sale order number and sale order item number is getting updated in production order . Beside these two , delivery schedule line number is not populated and delivery date is not picking correctly in production order.
    please give your valuable suggestion .
    i would be highly thankful to u
    regards
    piyush

    Hi
    When you do the MRP Run at MD02, maintain the Delivery Schedules as 3 (schedule lines), so when ever you do the MRP Run, it will run along with the delievry date.
    reward if it helps
    Regards
    Prasanna R

  • Delivery schedule line number in sales order is not populated in production

    Hi all,
    i am doing make to order scenario with 20 strategy group. In sales order we r defining the different delivery schedule lines.when i run the MRP and getting the plan orders for all the FG material and semifinished material, the sale order number and sale order item number is getting updated in production order . Beside these two , delivery schedule line number is not populated in production order.
    please give your valuable suggestion .
    i would be highly thankful to u
    Will reward points.
    Regards
    Kumaraguru

    Hi Kumar,
    Some changes done in your PRD server.If yes then contact abap consultant regarding the same.
    Because these type of problem comes when you do transport or changes done in the system.
    Regards,
    Anil