Dear All,
1. I have created sales order with assigment WBS element (VA01)
2. Then I created Routing & BOM for Material (CA01 & CS01)
3. Generate MRP Run (MD51)
The problem the generated mrp run doesnt consume planned order .. i have set the planning strategy 21 or 40, but still doesnt works.. is there any other parameter that i should configure..???
Help Me...
MamaRara

Hello,
Hopefully, the following link can assist you.
- Re: After firming planned order, new planned order is generating in MRP run
- Basic Scheduling in MRP run
- Re: MRP run
- During MRP run unwanted plant and storage location include and exclude
- MRP run does not consider the common stock
Thanks & Regards
JP

Similar Messages

  • Production orders in place of planned orders in MRP run

    Hi,
    Please help me with this senario,
    we receive saleorders through CRM interface then these are chnged to redistribute to different plants by changing the plants in saleorders.
    we want to run and create production orders directly for these saleorders without creating planned orders.
    I tried using strategy 82 but it makes the production order online, but we want it to be created after mrp run.
    Is there a way to create production orders instead to planned orders in MRP run.

    Hi You used Right strategy only.Use Strategy '82',  Transfer requirement from CRM and execute MRP run in Background.It will generate Production order.But i didn't understand what you mean by 'Online' 3
    Pl.  Correct me If I am wrong.
    Edited by: Velmurugan S on Mar 4, 2008 10:02 AM

  • Problem in MRP run with Project/WBS Element

    Dear PP Gurus,
    I want to run MRP thro Project/WBS Element.
    I have created WBS Element & WBS BOM for Material. Then created sales order for that material and assign WBS element to sales order.
    Maintain Planning Strategy 21 ( Make to Order/Project) for Main Mtl.
    Now when I run MRP with MD51 then no requriements are generated for main material and its components.
    Is there any thing missing from PS-PP & SD point of view?
    Pl guide me for the same.
    Thanks in Advance.
    Umesh

    Dear Nagrajan,
    Thanks for your reply.
    There is no safety stock & un-restricted stock of that material.
    Also I don't want to assign this mtl to that wbs Network. If I assign the Material to WBS network then network req.is generated and thro Normal MD02 MRP generates the requirements.
    & in the plan order it will not show WBS Element
    But My req. is I want to run MRP with  MD51 & want WBS element as account asignment tab in plan order & production order too.
    IS there any config. missing from PP/ PS / SD ?
    Pl guide me for the same.
    Thanks ,
    Umesh

  • Capacity Booking by Planned orders from MRP

    Hey All,
    I would like to know how Capacity is booked on the Planned orders resulting from the MRP run.
    Regards.

    Hi Danish,
    On the basis of Delivery Date or requirement date system schedules the order either it is though Backward or Forward scheduling. For this calculation system considers the Inhouse Production Time , GR Processing Time , Routing data etc.And during this calculation system will ignore the available capacity on particular date means you have to perform Capacity Leveling later.
    And on the basis of that Routing which is selected during MRP run system generates the Capacity requirement on the relevant work centers / Resources.
    Refer below link,
    [Detail Scheduling|http://digilander.libero.it/vietrim/]
    Regards,
    Dhaval

  • Problem when creating planned order with MRP run

    Hello,
    I create a material with a fix reorder point, MRP type VB. When I run MRP with MD03 on this material I have several problems :
    - planned order is created with an opening date in the past, so I have error 'Opening date in the past' in MD04. How can I generate a planned order with opening date not in the past
    - when changing manually opening date, after running again MD03, I have error 'No BOM selected'. Material is configurable, has a text BOM, a routing and a configuration profile. What is the problem? When modifying planned order, I have message :
    Material requires configuration
    Message no. 61259
    Diagnosis
    Orders and requirements for a configurable material must have characteristic values.
    Usually, you should create a variation for configurable materials managed in inventory management which has the default variant configuration.
    System Response
    MRP: Requirements without characteristic values for a material cannot be planned in MRP.
    Procedure
    Check requirements or orders.
    Create a configuration evaluation for the material in the material master record if necessary.
    Thanks in advance.

    Hi
    I am facing the problem. Could you please tell me if you have resolved the above problem? If yes, Could you please provide me as how you resolved? Thanks in advance.
    Thanks
    Nagesh.

  • To generate planned orders throught MRP even without forecast/sales orders

    Goor morning, we should send long term plan forecast to the suppliers, but in the system we're able to see just few weeks demand (lng term horizon is not still implemented). Do you think is possible to generate some planned order as MTS policy (based on the past consumption), even without any sales order or forecast inside the system? Tks in advance

    1) create a Plan IN MD61 with inactive version select the period as you want & enter  W- week in initial screen
    2) create a plan In MS31 and assign the created in active version plan in MS32 assign the plant and activate  independent requirement
    3) Run MRP in MS01, system will create a plan order for LTP
    4) and do the evaluation for created plan order in MS38.

  • Creating purchase requisitions instead of planned orders after MRP run in MDBT

    When running regenerative planning in MDBT for plant with following details ,The system has to provides planned orders for the materials .
    Processing key:NEUPL
    Create Purchase requisition :3
    Schedule lines:3
    Create MRP list:1
    Planning Mode:1
    Scheduling :1
    But sometimes it provides purchase requisitions for certain materials.The problem happens for different materials at different times.
    I checked the material master and found that procurement type is external procurement.Business need to create planned order for the materials and then want to convert it to purchase requisition.
    MRP group is assigned to the materials but no creation indicator maintained for the MRP group.
    Please tell me why this run creates purchase requisitions suddenly and in the next run it disappears?

    Hello
    Maybe someonelse is running MRP in another transaction, such as MD02, with a different parameter. Check on transaction MD05 when was the last MRP execution and the user that ran it.
    Also check if there is any active implementation of BAdI MD_MRP_PARAMETERS.
    If you don't have a cretion indicator, maybe it would be useful to set it for your MRP group, with the parameter 3, in order to make sure that planned orders will be created.
    BR
    Caetano

  • Multiple planned orders in MRP run

    Hi All
    I have a requirement where I need to create multiple planned order for the same material during MRP run. I understand that once I run MRP a planned order creates. If I run again for the same material, the quantity will be changed for the same planned order. Do we have any configuration so that system creates multiple planned orders for same material for each MRP run.

    Hi Adithya
    Planned orders may be changed by MRP until they are firmed. Therefore, what you need to do is to firm the planned orders after the MRP execution.
    You can use for example, transaction MD19 to mass firm planned orders after each MRP run.
    Otherwise, you can user BAdI MD_PLDORD_CHANGE to automatically firm the planned orders created by MRP.
    BR
    Caetano

  • Wrong Planned Order dates - MRP Run

    Dear Experts,
    Please guide to resolve the following problem:
    I have uploaded the PIRs for 3 months. When I take the MRP run, the system is scheduling the planned orders for first 2 months only. For the 3rd month's PIR the planned order are created for the PIR dates only. 
    For example, if the PIR (for 3rd month) is maintained on 25th of the month. The planned orders for FG & SFGs are being created for 25th only. While for 2 months the Planned orders are properly scheduled.
    What could be the reason for such behavior.
    The planning horizon is 90 days.
    Regards,
    Rohit.

    Dear Rohit,
    If you are running MRP with NETPL, then the Lead time scheduling will be carried out only for the planning harizon.
    Try executing MRP you can select NETCH key.
    or
    If you want to run MRP with NETPL key, then please give In-house production time in workscheduling view as per the routing values. For example 1 day is the processing time and give the quantity for for 24 hr production. Then the sceduling will be carried out as per this values.
    And change the planning harizon for detailed scheduling in OPU5 transaction.
    Thanks and regards
    Murugesan

  • Excluding storage location from MRP run in Long Term Planning

    Hi,friends,
         In my scenario , i want to exclude storage location from MRP run in long term planning.When i set storage location MRP indicator "2" in SPRO and SLoc MRP indicator "1" MRP4 in material master, i can exclude the storage location after run MRP with MD01/MD02,and i can see the expected result in MD04.But in Long Term Planning scenario the storage location can not be excluded after run MRP with MS01/MS02,and the requirements list in MS04 include the stock in the storage location i want to exclude. i dont know if i miss something.Plz give me some advice.
    Regards
    Joey

    Hi,
    Refer the OSS Note 208017 - LTP: Long-term planning and storage locations
    ==========================================================================
    Symptom
    In long-term planning (Transactions MSBT / MS01 / MS02 / MS03), the MRP indicator of a storage location for a material is not taken into account (material master, view MRP 2 [up to and including Release 3.1I] or MRP 4 [as of Release 4.0A]).
    The storage locations excluded by MRP or planned separately are also planned in the plant segment.
    Additional key words
    LTP, MM01, MM02, MM03, master data, MRP indicator, LGORT ...
    Cause and prerequisites
    The MRP indicator for a certain storage location of a material is only taken into account in operative planning (requirements planning, MRP).
    The long-term planning occurs exclusively at plant level.
    Solution
    This is no error. The system works as intended.
    The individual storage locations should not be distinguished in the long-term planning, in order to perform a comprehensive long-term planning.
    This is important, for example, within the kanban processing where the storage locations with kanban MRP are excluded from the MRP, but in spite of that should be included in the long-term planning.
    ==========================================================================
    Regards,
    Siva

  • No planned order created when run MRP for Sale Order

    As I have told on the subject. My problem is system does not generate planned order for components in BOM
    Some more information is: requirement class in SO is 043
    I have choose "2" in tab MRP 4 for individual/collective and all component and finish product have MRP type is PD and Strategy is 20 - make to order
    Please help me to solve this
    Thanks

    Hi Hoai Vu,
    Please check in OPPQ plant parameters in SPRO weather you maintained for the plant conversions of planned order to production order.
    SPRO-> Production> material requirement planning> plant parameters--> carry out plant parameters or over all maintenance of plant parameters (OPPQ)
    Then check the for the material did you maintained the work scheduling view or not.
    I hope helps you any queries please revert me back.
    Regards,
    Madhu.G

  • Standard Purchase order from MRP

    Hi
    I am trying to create standard purchase order from MRP using quotation, asl,sourcing rule ,assigement sets, but it is only going upto Requisition.For the same item if i run the min-max planning it does generate Req as well as standard PO.
    Am i correct that i can create standard po by using Quotation etc ?? if so what is wrong with setup ??
    Thanks
    Anshuj

    Sorry for posting. works fine.
    anshuj

  • Number Range for PR converted from MRP Run

    Dear Experts,
    We are experiencing problems with our number range when converting our MRP generated planned orders into PRs. We convert planned orders to purchase requisitions using MD03. We have 1 Plant with 2 MRP Groups which assigned to specific document types and number ranges as well. For example:
    In T-code OMI8:
    Plant AAAA --> Number Range 1111111111
    (Because 1 Plant only able to have 1 number ranges)
    In T-code OPPZ:
    Plant AAAA, MRP Group : A01--> PR Document Type : ZZZZ
    Plant AAAA, MRP Group : A02 --> PR Document Type : XXXX
    In T-code SPRO "PR Document Types" and "PR Document Ranges"
    PR Document Type : ZZZZ --> Number Ranges 1111111111
    PR Document Type : XXXX --> Number Ranges 2222222222
    When I run MD03, the result is:
    MRP Group : A01 --> PR Document Type : ZZZZ --> Number Ranges : 1111111111
    MRP Group : A02 --> PR Document Type : XXXX --> Number Ranges : 1111111111 (Why the number ranges is not 2222222222 ???????)
    Does anyone have idea? Please help. Thanks a lot..

    Hi Mallinath,
    thanks for your info.
    Note 46919 has been implemented in the system, and also i have maintain Tcode - OMI3:
    * Object Type : 2 (PR) --> PR Document Type : ZZZZ --> Internal number range : 1111111111 --> external number range : " " (blank) --> Reservations : 01
    * Object Type : 2 (PR) --> PR Document Type : XXXX--> Internal number range : 2222222222 --> external number range : " " (blank) --> Reservations : 01
    But still system pick wrong number ranges (1111111111, instead of 2222222222 ) for PR Document Type XXXX if generated from MRP run.
    Do you have any other idea? Thank you.

  • Quota arrangement in R/3 for APO generated planned order materials?

    Quota arrangement for the planned order materials generated from APO and when
    it is at the inbound side of R/3 while in CIF i.e.
    u2022 Once the Planned order is created in APO and when it is at the inbound side of R/3 while in CIF u2013 the system will first check in the table(EQUK) against the material and plant whether there is any valid u201CQuota arrangement numberu201D(EQUK-QUNUM) .
    u2022 Then from the table (EQUIP) against the u201CQuota arrangement numberu201D the system needs to calculate the percentage quota(from QUOTE field) of the material concerned against each production version.
    u2022 Finally the Planned order of the material needs to be converted into more than one Planned orders as per the production versions and in the ratio as mentioned in the quota arrangement.
    Actually Functionality exists today in R/3 whereby MRP will generate more than 1 planned order if production version quota arrangements exist. For example if via MEQ1 a quota arrangement exists to split requirements 60-40 between production version 1 and production version 2 then MRP will generate 2 planned orders using the 60-40 split.
    Does this still occur if APO generates the order materials and CIFs it to R/3?
    *I mean I had a requirement where APO generated planned orders to be split automatically and the correct PVs(Production version EQUP-VERID) to be assigned if quotas(EQUP-QUOTE) exist in R/3 side??*
    please help me asap this will b really appreciated and high points will be given....

    Quota arrangement for the planned order materials generated from APO and when
    it is at the inbound side of R/3 while in CIF i.e.
    u2022 Once the Planned order is created in APO and when it is at the inbound side of R/3 while in CIF u2013 the system will first check in the table(EQUK) against the material and plant whether there is any valid u201CQuota arrangement numberu201D(EQUK-QUNUM) .
    u2022 Then from the table (EQUIP) against the u201CQuota arrangement numberu201D the system needs to calculate the percentage quota(from QUOTE field) of the material concerned against each production version.
    u2022 Finally the Planned order of the material needs to be converted into more than one Planned orders as per the production versions and in the ratio as mentioned in the quota arrangement.
    Actually Functionality exists today in R/3 whereby MRP will generate more than 1 planned order if production version quota arrangements exist. For example if via MEQ1 a quota arrangement exists to split requirements 60-40 between production version 1 and production version 2 then MRP will generate 2 planned orders using the 60-40 split.
    Does this still occur if APO generates the order materials and CIFs it to R/3?
    *I mean I had a requirement where APO generated planned orders to be split automatically and the correct PVs(Production version EQUP-VERID) to be assigned if quotas(EQUP-QUOTE) exist in R/3 side??*
    please help me asap this will b really appreciated and high points will be given....

  • How to exempt a storage location from MRP run

    Hi all,
    How do I exempt a storage location and all its materials from MRP run.
    I am creating a new storage location and this should not be considered for MRP and  no idoc should be generated if a purchase order or a delivery is created from this storage location( should we stop entering this storage location in BD64 filters or anything more to prevent triggering of the idoc).
    Can somebody please through some light on these issues. 
    Kind Regards
    Chakradhar
    <REMOVED>

    Hi
    You need to set up master data for that material.In Mrp-4 View  set  storage location indicator as 1(one) .In this case your storage location stock will be exclude from MRP .
    Hope this will help
    Dilip

Maybe you are looking for

  • Iphone 3G not recognized by iTunes 8.0

    Hi all, I recently upgraded to iTunes 8.0, and it no longer recognizes my 16GB iPhone 3G. However, the USB connection seems to be working fine. I'm running Windows XP Pro, and have tried restarting both the phone and the computer, but nothing seems t

  • My Camara won't focus how do I fix it

    My iPhone camera won't focus how do I fix it?

  • Error with hyperlink to open a form in Workflow Notification

    Hi All,   I am trying to create a hyperlink to open a form in Workflow Notification. I want to open "Prepare Mass Additions" form from my workflow. I am in R12 (12.1.3) and there is no parameters defined for this function.   So i am trying the method

  • Release procedure for ASSET

    Hi SAP guru I am having the requirement for release procedure as follows Purchase order with  Asset (Item category)   - Value  Up to 50,000/-  will be approved by GM                               Asset (Item category)   - Value  more than 50,000/-  w

  • Adding a new system to the transport domain

    Gurus ,    currently our landscape is a 3 system landscape . We are SAP BUSINESS SUITE users  . we are using ECC 6.0 on AIX with AS ABAP .    we are planning for one sand box system on AIX with both AS ABAP and AS JAVA . but we  have certain confusio