GIS Upgrade in an SAP Lanscape

All,
I would like to see if anybody has experiance with ugprading a GIS environment withing a SAP Landscape.
Current Environment
Application = GIS 4.1 on Windows Server 2003
Database = MS SQL Server 2000 on Windows Server 2003
Target Environment
Application: Sterling Integrator (GIS 5.1)
Application Server: Linux Red Hat 5
Database: MS SQL Server
We have around 30 interfaces going through GIS. I got a quote that this is a 9 month effort and around US$1 Mio. Does this sound right to anybody? Also what is the opinion about Linux and a MS SQL environment?
Thanks,
Alex

I have recenty upgraded the GIS application last month and it is working fine. I am not familiar with SQL Server so cannot tell you the exact complexicity on that.
Initial Version
GIS 4.3 on Wndows 2003 Server with Oracle 10G
After Upgrade
Sterling Integrator 5.1 with Patch on Windows 2003 with Oracle 11g
I dont remember the exact number of interface but is was more then 30 and i have not found so much Complexicty which needs 9 month. I have done it in 1 month and upgraded the Test/Prd environment of GIS
Regards,
Subhash

Similar Messages

  • Upgrade project : from SAP R/3 4.6C to ECC 6.0 by using SAP Data Services

    Hi All,
    My client is upgrading from SAP R/3 4.6C to ECC 6.0
    We are planning to use SAP Data Services(Data Integrator) in the upgrade plan from SAP R/3 4.6C to ECC 6.0 for Data Migration.
    we have no idea whether we can use this SAP Data Services(Data Integrator) in SAP upgrade data migration.
    The bottom line is we have to make use this Data Services (Data Integrator) product in our upgrade plan for Data Migration.
    Please tell us if anybody already used it such kind of scenario in a data migration project with Data Services(Data Integrator).
    If we can use Data Service(Data Integrator) what are the pros and cons in using this Data Services(Data Integrator).
    Thank You,
    Ashok

    My opinion is you would want to utilize SAP tools to port the data - our SAP BASIS administrator is out this week but we can provide exact tool names when he returns.  ELM (External List Management), IDOC are some of the tools.
    You could use DS/DI to export, cleanse, deduplicate the records prior to importing with SAP tools if that is your end goal.
    We also offer a data quality tool that extends DS/DI to cleanse/deduplicate name/address records as they are entered into the system.  It also comes with batch tools to cleanse/dedup the entire systems name/address information.  See Data Quality Management for SAP for further details.

  • SAP R/3 System analysis before upgrade 4.6C -- SAP ECC 6.0

    Hello!
    Before the upgrade from R/3 4.6C to ECC 6.0 I would like to execute SAP R/3 system analysis.
    The following functions should be included in this program:
    - detailed analysis of system modifications (effort driver and risk factor during an Upgrade)
    - comparison against a SAP ERP 6.0 reference system
    - extension SAP tools, including RBE and conflict lists (SPAU/SPDD)
    - syntax analysis of program code with respect of adjustement need
    - quality control of own development
    - control of amount of transports within different company areas
    - control of user information, such a user type, logon date, etc.
    - basic control, whether a sufficient authorization concept is available
    - Identification of objects that should be considered for the archiving in oder to decrease the db-size
    My question are:
    - which tasks can be convered with SAP standard transactions what are the names of the transactions?
    - which effort do I investigate for these tasks?
    Thank you very much!
    regards

    Dear Thom,
    To know the functionality changes u can refer http://solutionbrowser.erp.sap.fmpmedia.com/
    http://www.sap.com/solutions/business-suite/erp/pdf/BWP_ERP2006_Upgrade.pdf
    http://service.sap.com/releasenotes and  http://service.sap.com/upgrade  for functional changes.
    Need to consider the following things:
    For Reports…it’s custom developed program …so unless there is any kind of change in requirement from the client regarding the layout…nothing needs to be changed…I think it will work fine in ECC 6.0 to…except few things may needs to be changed..so you need to discuss whether they want the reorts as it is right now…or want to change the layout (adding some new info/fields etc) of any report…so u need to modify the program for those…and estimate accordingly…for a medium complexity’s Report dev it takes approx 9 pd (FRSTDSCoding+Unit Testing)…so to modify it will be less than that (depending upon the scope of changes)
    Now say for Batch Inputs(interface/Data Migration) using BDC…you need to see how many BDCs are there…again if the field lengths and layouts are not changing…then no need to change anything (except the main thing…..you need to change the obsolete function modules…there are some in 4.6 c like for data upload ws_upload_*** is there 4.6C but obsolete in ECC6.0…there are some new with enhanced functionality so you need to modify the BDCs…and many cases it happens that the whole transaction screen changes for process…in that case better to develop new BDCs…so you have to consider those parameter…look into and estimate accordingly…modifying a BDC should not take more than 1 PD…
    Now say for Forms…there was no Smart form in 4.6C…form printer was there..though the same option is there in ECC 6.0 too..but better to go for/should go for Smart form…in that case…it’s complete new dev…so estimate accordingly…a medium complexity’s form should take 8 PD (FRSTDSCoding+Unit Testing)…you can take it as 10 PD too…even if client wants to keep it is as it was in older version…you have to redevelop the layout in ECC 6.0 again…as form printer is even client dependent…maximum you can copy the program associated with that form in the new version too…and your effort will be saved…again you have to consider if clients wants to change the layout too…
    Now for enhancement…so in that case u need to see individual cases…for a medium complexity enhancement it should take max 15 PD (FRSTDSCoding+Unit Testing)…
    One more important thing is that the Unicode Compatibility…this needs to be done….needs to change the code (variable name) accordingly….also Version management tool is used for the standard programs…
    Also pls find the following forums:
    Re: Data Migration from 4.6C to ECC 6.0
    List of transations supported in SAP 4.6c and not in ECC6.0
    Re: Upgradation from 4.6C to ECC  6.0
    Re: what's the advantage to upgrade 4.6c to ECC5.0...
    RE: Help required regarding to upgrade from R/3 4.6c to mySAp ERP 2005
    Upgrade batch inputs from 4.6C to mySAP ERP 2005
    /thread/317225 [original link is broken]
    Upgrade from SAP R/3 to ECC 6.0
    Hope it will help you.
    Thanks,
    Atin
    <b><b>Reward points if it helps.</b></b>

  • Upgrade CFM from Sap R/3 Enterprise (4.7) Sap to ECC 6.00

    Hello,
    We are in a project of upgrade Sap from Sap R/3 Enterprise (4.7) to Sap ECC 6.00. Our question is particularly for CFM component migration/upgrade.
    As we checked we have activate the extension set:
    EA-FIN: Financials Extension
    EA-FS: Financial Services
    According with the Component Version Data the extension set EA-FINSERV has the release 2.00. However, in order to execute the CFM migration with transaction TPM_MIGRATION we are not sure if our CFM installation is on release 1.00 or 2.00.
    In the other OSS note 858966 mentions the following conditions to start points migration:
    1. The start release of the upgrade is SAP R/3 Enterprise 4.70 with SAP
    R/3 Enterprise extension set 1.10 or earlier.
    2. The target release of the upgrade is SAP R/3 Enterprise 4.70 with SAP
    R/3 Enterprise extension set 2.00 or higher.
    Do you know a transaction o report Sap which provides this information?
    Thank in advance.
    Sergio

    Within SAP, select System -> Status...  In the pop-up box, click the details button in the SAP System data section and you'll get another pop-up with system component information.  It's been a couple of years since I did the Treasury migration for our upgrade from 4.7 to 6.0, but I believe the component you're looking for is EA-FIN.  The Release column will have either 110 (for extension set 1.10) or 200 for (2.00).
    Regards,
    Shannon

  • Upgrade of Sourcesystem SAP EHP3 SAP ECC 6.0 to SAP EHP4 SAP ECC 6.0

    Hi,
    I noticed there is a lot of questions on the testing procedures for BI side when Upgrading the source system from R/3 to ECC 6.0. But noticed there aren't many posts on when doing Ehancement Packs. But I believe the process would be more or less the same?
    My project is doing an Upgrade of SAP EHP3 SAP ECC 6.0 Stack03 to SAP EHP4 SAP ECC 6.0 Stack07. BI Side is also upgraded, but I am more interested in the impact of the Upgrade's Source System (ECC) on BI.
    I believe the amount of impact is less as compared to an upgrade from R/3 to ECC, but there still should be impact to BI somehow.
    Basically, from what I have researched, there correct procedure is as below:
    Pre-Upgrade
    1 - Lock users in ECC
    2 - ensure that the Delta queue is cleared in RSA7
    3 - check the PI in ECC6.0 ( What is PI???)
    3 - stop all loads from BW
    Post-upgrade
    1 - Check Source System connections
    2 - replicate all data sources in ECC (when I do a check connection in RSA1 I get the message "No metadata upload since upgrade" which I believe is due to this step not done yet? Is it ok to replicate all datasources??)
    3 - activate all rules thru program (RS_TRANSTRU_ACTIVATE_ALL. Is it ok to activate all transfer strucs?)
    4 - run Init w/o Data Transfer for deltas
    5- run and then check extraction for full & delta loads
    Appreciate if I could your expert inputs on the procedures above? Maybe a more detailed step by step procedure or comments are most welcomed.
    Thanks.

    Additional information:
    I start the upgrade from SAP ECC 6.0 with a dual stack.
    SAP advised me to download the following file to start the upgrade
    SAPehpi_68-10005800.SAR from the SMP
    Download path: Browse our Download Catalog-->  Additional Components --> Upgrade tools --> SAP EHPI Installer --> SAP EHP Installer 7.00.
    Start the upgrade without the jce_policy_zip extension. This was written in note 1302772 .
    Have more luck with it.

  • Upgrade strategy for SAP ECC 6.0 SPS 12 to EHP4

    Hi!
    I would like to update a SAP ECC 6.0 system with EHP4. 
    I am on Windows 64 Bit with Oracle.
    My current SP stack of SAP ECC 6.0 is 12.
    What is the best timesaving approach to update SAP ECC 6.0 SPS 12 to EHP4?
    a) to patch manually with SPAM/SAINT til SAP ECC 6.0 highest SPS (18?) and run SAP EHP Installer to upgrade to EHP4
    b) to run SAP EHP Installer that updates SAP ECC 6.0 with highest SPS and upgrade the system to EHP4
    Any helpful information will be very appreciated!
    Thank you!

    Hi Holger,
    It's better to start upgrade with EHPI tool only so that downtime will be minimized instead of first doing via SAINT to highest SPS and then EHPI tool.
    Also, while starting upgrade with EHPI tool, make sure of below thing:
    1) Number of R3trans processes
    2) Memory parameter optimization
    Also. check SAP note 1143022
    Check link: https://websmp201.sap-ag.de/~sapidb/011000358700000293582009E.PDF
    Thanks
    Sunny

  • Upgrade process to SAP Solution Manager 7.1

    Hello!
    We use SAP EHP 1 for SAP Solution Manager 7.0 (SPS 26) and plan to upgrade to the new SAP Solution Manager 7.1.
    We currently do not have Java Stack there.
    Some questions about Upgrade process
    1) Can a direct Upgrade from SAP EHP 1 for SAP Solution Manager 7.0 (SPS 26)  to SAP Solution Manager 7.1 be realized?
    2) Should we first install Java Stack and then proceed with the Upgrade or otherwise?
    3) Will Windows 32 Bit and None-Unicode Version of SAP Solution Solution Manager be supported?
    It will be great to get some helpful information.
    kind regards

    Hello!
    Trying to answer your question
    1)  As described in note 1244225, there no restriction to upgrade the Solman EHP1 to solman 7.1. Refer to the section:
    In case you do not participate in this current Solution Manager 7.1 beta shipment there are no  restrictions for implementing now SP stack 25 and upgrading in the future to an equivilant SP stack of release 7.1."
    2)  The Solman EHP1 must always be a dual stack system, I am not sure,  how you are  running the Solman EHP1 without a Java Stack, you should have one.
    3) I am not sure if there will be a Solman 7.1 32Bit Non-UNICODE version. But,  SAP recommends to run Solution Manager on Unicode (see also customer letter on http://service.sap.com/Unicode).  At solman EHP1 there are some issues when running the system as Non_UNICODE, refer note 1383407.
    I am not sure if I could clarify all your doubts.
    You may check the following URL:
    http://service.sap.com/instguides
    - SAP Components
    - Solution Manager 7.1
    As this is a very new software there is few documents in it, but soon you should see a upgrade guide here.
    Regards,
    Allam

  • Upgrade: Adapters for SAP NetWeaver PI 1.1

    Hello!
    By the upgrade to SAP NetWeaver PI 7.3 we get (within Solution Manager Maintenance Optimizer) a addon  Adapters for SAP NetWeaver PI 1.1.
    Question
    Do we need this addon when we go to SAP NetWeaver PI 7.3 or can we install this after the upgrade with SAINT?
    thank you!

    Many thanks!
    I also have been asked (within Solution Manager Maintenance Optimizer) to update following contents:
    EHP Component XI CONTENT ESM ERP 604
    EHP Component XI CONTENT IS-H_IC 604
    EHP Component XI CONTENT IS-H 604
    Makes it sence to update with the upgrade process or can it wait?
    Thank you!

  • Error in Upgrading 'Upgrade Commom' in SAP B1 2007 PL08

    Hello Experts,
                       I am trying to Update B1 2007 B Patch 00 to 08
    First install server tools
    When I Upgrading 'Upgrade Commom'
    Then System  Throws Error  Massage :
    *'Connect Database Failed , May be you have not start your Database ! Please Check Your Database Status and try run this upgrade installer by manually*
    please give me a solution
    Regards
    Pravin Baji

    Hi Pravin,
    This issue seems to be related to the SAP Business One Integration Platform Setup.
    Please refer to the SAP note [1107410|https://websmp130.sap-ag.de/sap(bD1odSZjPTAwMQ==)/bc/bsp/spn/sapnotes/index2.htm?numm=1107410] to get the details information about this issue.                                                                      
    In case you do not use SAP Business One Integration please confirm this error message by clicking "OK". The SBO-COMMON upgrade should then be completed successfully.
    hope it helps,
    Regards,
    Ladislav
    SAP Business One Forum Team

  • PROBLEM UPGRADING SBODEMOUS IN SAP HANA

    Hello,
    I'm trying to upgrade SBODEMOUS database in a SAP HANA DB (created directly in HANA DB) but when it tests the upgrade fails with error:
    "Parameter type error in stored procedure SBO_SP_TransactionNotification; contact SAP support".
    It points to this note: 1343078 - Upgrade Wizard Precheck:Transaction notification parameters
    But solution is for SQL Server, the procedure SBO_SP_TransactionNotification does not exist in my database.
    Any suggestion?
    Thanks.

    Hi Angel,
    Procedure "SBO_SP_TransactionNotification" is a stored procedure created by B1 automatically, should be in each one of your company databases. You cannot find it in SBODEMOUS database?
    You need to modify the stored procedure in SQL server before proceeding with the migration to HANA.
    Was SBODEMOUS company database an old SQL company database or is it a new company database created directly in HANA version?
    Regards,
    Trinidad.

  • SAP BPC Upgrade Review by SAP

    Will SAP  provide any kind of review of on the SAP BPC Upgrade from 4.2 to 7.0 M done by Partners

    Yes, it's possible to arrange for a review by SAP Consulting. You should contact your local SAP office, either through your existing contacts, or speak to the Consulting Services organization. They can direct you to the BPC experts in your region of the world.
    If the partner doesn't have prior experience with BPC upgrades (and Outlooksoft 4.2 in general), I'd recommend that you involve SAP as early as possible, before starting the upgrade if possible.

  • Kernel Upgrade for old SAP Ides system

    HI,
    How I need to install 4.6c Kernel 4.6d patch level 948 on the following system
    SAP Ides - R/3 4.C
    SAP Package level 534
    Support Package Manager  version 4.6c/0028
    Oracle 8.1.7.0.0
    ABAB Load 1258
    Kernel 46D
    Could someone please tell me what I need to download and the steps
    THanks in advanced.

    Hi Tin,
    FYI, per SAP marketplace support site information:
    "Mainstream maintenance for SAP R/3 4.6C ended on December 31, 2006.
    From January 01, 2007 to December 31, 2009, SAP offers extended maintenance for this release."
    To download the support packages for your R/3 4.6C release:
    1- Got the area <a href="http://service.sap.com/patches">SAP marketplace Patches download area</a>
    2- In the left side navigation, select '<i>Archive for Support Packages and Patches</i>', then '<i>Entry by Application Group</i>'
    3- In the component list, select '<i>SAP Application Components --> SAP R/3 -> SAP R/3 4.6C'</i>
    4- You should then see the list of patch components for 4.6C and add them to your download basket
    Hope this helps.
    Regards,
    Joseph

  • Upgradation project in sap xi

    hi expects ,
         i want to know about what would the problem or process in upgradation project.please help me.
                                                                                    thank u

    Hi,
    As an XI Developer one has the following responsibilities
    SLD developement is depends upon the Organization.
    1)  Developing Interface Objects
    2) Developing maping objects
    3) Developing Config objects like Creation of Communication channels , Sender and Receiver agreemnets, Interface data and    Receiver  data.
    In Addition to this he has to check whether the files are correctly picking and the files are correctly placing in the Target.
    Any Mapping related error means he has to look into those
    what are the responsibilities of an XI Developer?
    A) Steps are as follows.
    1) Receives functional specs.
    2) Understand the business requirements.
    3) Check whether are the required information is provided in Functional specs or not information like, source sturucutre,target strucutre,Transformation rule, test files, validation rules, error handling, data size etc.
    4) Raise issue log if there are issues and resolve it with functional team.
    5) Start building or designing the tech specs with all the required details like IR and ID part.
    6) Develop the object as per the design.
    7) Follow the naming convention as per the doc.
    8) Test the developed object with test cases and prepare UTC.
    9) Then review will happen with other team members.
    Regards
    Mohammed

  • I want a brife intro on the upgradation procedure in SAP ?????

    pls reply me ........

    Check out this link...
    http://www.thespot4sap.com/upgrade_guide_v2.pdf
    Reward point if helpful.
    Venkat

  • Upgrade SAP NetWeaver Portal 7.0 to 7.3 - Custom coding

    Dear all,
    we would like to upgrade an existing SAP NW Portal 7.0 to the latest version 7.3. The current installation contains a number of custom coded portal and Web Dynpro applications. As far as I understand SAP's upgrade guides, documents and notes:
    - Web Dynpro applications of NW 7.0 are source compatible to version 7.3 but not binary compatible and thus need to be manually migrated to the new platform. The manual migration consists of an import of the respective artifacts (DCs) to NetWeaver Developer Studio 7.3 in order to rebuild, re-archive and re-deploy the software.
    - Portal applications developed with Java 1.4.2/J2EE 1.3 (default version of SAP NW 7.0) are generally source and binary compatible to those developed with Java EE 5 (JDK 5/6) in SAP NW 7.3 and thus do not need to be manually migrated. However, the KMC-API and the UME-API used therein have been changed. In case an application uses these APIs, it is necessary to adjust the source code before rebuilding and re-deploying the application.
    Is the summary presented above correct? If not, could you please point out which assumption is wrong?
    Furthermore, could you please give me any details about changes regarding the portal frameworkpage? We have a highly customized frameworkpage and would like to know in how far the latter will be running on the new portal version.
    Thanks for your help and best regards,
    Markus

    Hi Markus
    Its been long period since last reply on your reply. In case you haven't yet solved your issues, I hope my reply would help you to some extent.
    As per SAP, all those WD Java applications that were developed on NW 7.0 needs to be migrated on NW 7.3 if you plan to make further modifications (on new environment) in these applications.
    For migration, all you need to do is migrate the development track, import the track into NWDS 7.3 and migrate the DCs one by one.
    However in case of Portal applications, some of our custom portal applications (TLN), worked as it is on NW7.3 but some are not working even after defining new dependencies. Since some of the Classes have been removed, we are working around them.
    Deepak
    Edited by: Deepak Salokhe on Feb 6, 2012 12:37 PM

Maybe you are looking for

  • Problem with Adobe Reader X on a Windows XP

    When I try to open a PDF my screen blacks out for a second then comes back on and everything is huge and distorted. Does anyone know a fix for this? Should I download an older version of Adobe?  Thank you for any assistance. 

  • Help please - moving tracks within iTunes

    I've imported some audio books into my iTunes library but it's gone into the Music folder instead of Audio Books folder. Why can't I drag them from one folder to the other? Thanks

  • Sharing presets in FCE 4

    Is there a way to share presets in final cut express, i am able to drag a custom video filter into a bin ive created, but is it possible to share that preset with other people. I cant find a files anywhere that resembles my preset, so i assume it mus

  • Reconstruct has goofed up my users mail

    I had a single user with a POP problem. I found some advice on using reconstruct to cure mail problems I did: /usr/bin/cyrus/bin/reconstruct -i and now none of my users can get into their mail boxes. I get this error: -ERR [SYS/PERM] Unable to locate

  • Will this ever happen

    will Apple ever make it so us canadians can get movies and tv on our ipod's because not being able to do this makes me angry at america for getting better things then canada