GL Account 92358 requires an assignment to a CO Object

Hello,
Can anybody help me in resolving the above issue ?
We have posted one document in Oct. 2007 with the Transaction Code  - CO15. That document has debited "GL 92358 - Inventory Change-Finished Goods" in the "Non Business Area" with the Posting key 91.
Now we are in the Year End closing and want to post a JV for transferring an amount from "Non Business Area" to "Business Area".
While doing so through TCode - F-02, we were debited the GL - 92358 by "Posting key 81" but this debit entry require Cost Center (CO Object) as a require field and Business Area is attached to particular Cost Center.
We have made the Business Area compulsory through Posting Keys & Field Status Group which we can release, for posting this entry ( Means we can make the Bness Area field as optional for passing this JV). After doing that also still entry, require CO Object.
Problem is what we have check the Cost Center (KS03) also from where we cannot remove Business Area. Hence when we are putting Cost Center in a JV (F-02) automatically it is picking Business Area attached to that particular Cost Center.
Above GL is also an Cost Element. Can we make Cost Center as an optional field by which avoiding Business Area as a required field or is there any way ?
Please give a guidence on this. Points will be assigned to appropriate answer.
Thanks & Regards,
Shridhar Sawant
FICO

Hi,
We have solved our problem. Actully we wanted to make the manual FI entry from  "Non Business Area" to "Business Area".
While doing so system has generated the subjected message.
Since it requires "Co-Object" we were concentrating on the  Cost Center  / Cost Element option only, where the Business Area is linked. We do not wanted to put Cost Center since Business Area would had got selected alongwith Cost Center.
Ultimately when we tried the "Internal Order" - (Which is also a Co-Object) option, which has not asked for a Business Area (since that is not linked with Internal Order directly) by which we were able to post the required entry.
This is for everybodies information.
Regards,
Shridhar Sawant
FICO
Edited by: Shridhar Sawant on Apr 18, 2008 10:31 AM

Similar Messages

  • Account 555555 requires an assignment to a CO object

    I am receiving following error in posting:
    account 555555 requires an assignment to a CO object
    please help

    Hi,
    For  the GL account  Cost center is the mandatory feild for posting to accounts.
    Check IT0001or IT0027 if cost center is attached to the employees associated to the GL account.
    Regards,
    Hemant V. Mahale

  • Account 1910116 requires an assignment to a CO object

    Hi,
    I had error: Account 1910116 requires an assignment to a CO object when i tried to post to GL Account 1910116.  Then I input the cost center.  Then i got Enter a true account assignment object with revenues error.
    Please advice me on the matter.
    I would appreciate if also can advice where is the setting for tru account assignment.

    Hi,
    it shows that ,You made an account assignment for A/C 1910116, a revenue element, in controlling area 4444 to a cost center or profit center.
    Cost centers and profit centers can carry revenues in the SAP system as statistics only. To ensure reconciliation between FI and CO for revenue element 1910116, a CO account assignment object must record the revenues as a real value. This object type is used for updating to the reconciliation ledger.
    In principle, it is possible for the SAP system to automatically derive this CO account assignment object, the reconciliation object. However, all postings made in CO for costing-based Profitability Analysis are logged in the reconciliation ledger under "reconciliation object". In this manner, the reconciliation ledger identifies the exact values flowing into the operating profit. If you post reconciliation objects during revenue postings to cost centers or profit centers, you must do so while keeping the interpretation of the reconciliation ledger reports in mind. The sums of revenue postings to profitability segments, cost centers, and profit centers cannot be broken down further.
    To avoid posting to reconciliation objects, make account assignments to a real CO account assignment object.
    or else, you can change the message controll ,following below mentioned path :
    Controlling --> General Controlling --> Change message control
    Hope it helps.
    Dhara.

  • Account 300000 requires an assignment to a CO object  while I am trying to

    Dear Experts,
    Account 300000 requires an assignment to a CO object  while I am trying to do posting from billing doc to acc doc .
    When I am  trying in KA01 to create  cost element  then sym will ask  in default acc asst  cost centre .After when I do trying create cost centre in KS01 sym giving error message u2018  Controlling area XXX does not have a standard hierarchy (please assign one)u2019
    Again if I trying to create  std hierarchy in (OKEON u2013 Change) getting message u2018
    u2018You have not yet created a cost center standard hierarchy for COAr xxxx
    So  wt should I do  for this error to clear.?
    Regards
    Ishikesh

    Hi Ishikesh,
    First of all are you using a make-to-order scenario or scenario where there is linkage to controlling?
    This is an error because the G/L account which you have assigned in the customisation is requiring an assignment to any of the parameter which can relate it to the Controlling for e.g. Cost center or WBS element.
    For this you have to have some guidance of Controlling customisation as this is not the directly an issue of SD module.
    If the G/L is for Revenue then it will be a secondary cost element and not primary. If the G/L is a revenue element , then account needs a profit center. If a cost element , then account needs a cost center.
    Please check first the field status of the account in Transaction: FS00.
    If this account requires CO object as mandatory then check whether a cost element is created or not , this error normally occurs when CO object is mandatory but relevant cost element is not created.
    You have a cost account defined in accounts determination (Transaction: OBYC), and every cost account must have a cost object associated (say, internal order, cost center, etc..).
    You must decide what is the cost object to 'receive' the cost value on the account
    Now, Look at Transaction: OKB9 - Display View "Account assignment" : Overview
    In OKB9 specify weather this cost element give impact to cost center or profitability segment. If it is give impact to cost center then assign cost center against to cost element or assign it to PA.
    OR, Alternatively -
    Go to, Transaction: KA04 and delete the cost elements for your g/l accounts.
    Regards,
    Karthik.

  • Account 411655 requires an assignment to a CO object

    Hi
    Account 411655 requires an assignment to a CO object
    Message no. KI235
    Diagnosis
    You have not defined a CO account assignment for an account that is relevant to cost accounting.
    Pls help to solve this issue............
    Regards
    K

    Hello,
    This account is one of cost element while making posting system not able to identify the cost object for this like cost center, internal order.
    Check with OKB9 or 3KEH.
    Regards,
    sankar

  • Account 410100 requires an assignment to a Co object

    Hi Team,
    I am Trying to post one entry T code F-02 ( fast entry screen) , In the fast entry screen we require WBS element  as Co object ,
    we added  WBS element  but system still gives  error message  Account 410100 requires an assignment to a Co object
    Account number 410100 is also Revenue Cost element , while posting the entry this account number has 50 posting key,
    if i post entry using normal process with WBS element  system was accepted   only Fast data entry is the problem
    I found posting key field status and Account number fields status field status group both are having  WBS element is optional entry
    can any one Guide me where I am Doing mistake
    thanks
    Rana

    Hi,
    Check if you WBS is true or statistical, because revenure accounts require true CO objects for posting.
    Regards,
    Eli

  • Account 715090 requires an assignment to a CO object

    Hi Friends,
    During Release of an invoice document system is prompting an error as follow.
    Account 715090 requires an assignment to a CO object
    LongText
        Detail
         Diagnosis
             You have not defined a CO account assignment for an account
             that is relevant to cost accounting.
         System Response
             Account 715090 is defined as a cost element.
             This means that you must always specify a CO account
             assignment.
         Procedure
             Enter one of the following CO account assignments
             o   Order
             o   Cost center / cost center/ activity type
             o   Sales order item (for a project or cost relevant)
             o   Project / WBS element
             o   Cost object (Process manufacturing)
             o   Network/ Network activities
             o   Business process
             o   Profitability segment
             o   Real estate object
             The posting row affected is 0000001004, account 715090.
    Technical data
        Tech. data details
         Client
         Group Number
         Sales Document Number                  0064002233
         Item Number of the SD Document         000000
         Schedule Line Number                   0235
         Counter in Control Tables              00
         Message Identification                 KI
         System Message Number                  235
         Output Type                            E
         Message Variable 01                    715090
         Message Variable 02                    0000001004
         Message Variable 03
         Message Variable 04
         Group Type
    We are having Profit Center assignment with each line item and is also having configurations in VKOA Transaction.
    Can you please suggest how can we post this document in G/Ls.
    Rgds, Krishan Raheja

    Hi Krishan,
    There are four possibilities, please check
    Go to T-code: KA02: enter G/L account (Cost element) ---> default acct assignment TAB -->assign the Cost Centre ---> save.
    Now try your transaction.
    OR
    Check the field status of the account in FS00. If this account requires CO object as mandatory then check whether a cost element is created or not, this error normally occurs when CO object is mandatory but relevant cost element is not created.
    Example: CO object may be cost centre, cost element, WBS element
    OR
    Use t.code OKB9 --> assign G/L account to cost object with your company code ---> save.
    OR
    Go to your biiling document --> Item level --> On item detail page --> check the "Profit center --> If its not ther then maintain the require entry in GGB1 and Material master
    OR
    For more check the link
    http://www.sap-img.com/financial/requires-an-assignment-to-a-co-object.htm
    Hope this helps,
    Regards,
    MT

  • Account 3100005001 requires an assignment to a CO object

    Account 3100005001 requires an assignment to a CO object
    Message no. KI235
    Diagnosis
    You have not defined a CO account assignment for an account that is relevant to cost accounting.
    System Response
    Account 3100005001 is defined as a cost element.
    This means that you must always specify a CO account assignment.
    Procedure
    Enter one of the following CO account assignments
    Order
    Cost center / cost center/ activity type
    Sales order item (for a project or cost relevant)
    Project / WBS element
    Cost object (Process manufacturing)
    Network/ Network activities
    Business process
    Profitability segment
    Real estate object
    The posting row affected is 0000000002, account 3100005001.
    ple any body help in this issue

    thanks for giveing reply
    hear i am posting through ko88 actual settlement:Production/process ordre
    at this time system is give this error
    in OKB9 some cost centers and profit centers are assigned
    Account 3100005001 requires an assignment to a CO object
    Message no. KI235
    Diagnosis
    You have not defined a CO account assignment for an account that is relevant to cost accounting.
    System Response
    Account 3100005001 is defined as a cost element.
    This means that you must always specify a CO account assignment.
    Procedure
    Enter one of the following CO account assignments
    Order
    Cost center / cost center/ activity type
    Sales order item (for a project or cost relevant)
    Project / WBS element
    Cost object (Process manufacturing)
    Network/ Network activities
    Business process
    Profitability segment
    Real estate object
    The posting row affected is 0000000002, account 3100

  • Account 6311010 requires an assignment to a CO object Account 6311010 requ

    Hi All,
    I assigned different cost center in asset class. Then i removed default cost center in OKB9 for below GL account.
    While running the AFAB i am getting below error.
    Account 6311010 requires an assignment to a CO object
    I checked below configuration everything looks fine. But still i am getting error message.
    Checked in field status group OBC4 Cost center is optional and also checked OB41 for posting  key 40 Cost center is optional.
    a. spro-Finacial Accounting-Asset accounting-Integration with General ledger-Additional account assignment objects-activate account assignment objects- ACSET
    Activated the Cost cenet(KOSTL)
    b. spro-Finacial Accounting-Asset accounting-Integration with General ledger-Additional account assignment objects-SPECIFY Account assignment type for account assignment objects
    After maintaining the above steps still error message.
    Can you please let me know what could be the reason?
    Thanks!

    Hi Amit,
    Below are details which i mapped in ACSET:
    Acc *** obj:   KOSTL  cost center
    Transaction:   500       post deprecation
    Acc *** type: depreciation run
    Acc assignment: Check box tick marked.
    Also : Activate Account Assignment Objects  KOSTL  cost center 'Active and Agreement check box tick marked.
    Pl correct me anything wrong in the above configuration.
    Thanks!

  • Account 123456 requires an assignment to a CO object

    Dear all,
    We want to do a manual posting into the Excise Duty on Sales G/l through F-02 but system is throwing an
    error Account 123456 requires an assignment to a CO object even if give a cost center then also the problem exists.We have maintained Default Cost center & Cost Element in OKB9 & then when we are doing entry then the system is through error complete PA transfer structure Fi Message no. KF018.
    Regards
    D RANA

    Dear SAP Student,
    Is the data of with element category 1 do not flow to COPA??? & if yes how can we change the cost element category as we have already data posted with cost element category 12.
    Waiting for your reply....
    Regards,
    D Rana
    Edited by: Deepak Rana on Mar 13, 2009 10:04 AM
    Edited by: Deepak Rana on Mar 13, 2009 11:38 AM

  • Accounting  12546 requires an assignment  to a CO Object

    Hello Gurus
    I am getting the error Accounting  12546 requires an assignment  to a CO Object   Please ignore the number it is my G/L number for which primary cost element is also the same.
    I happens when i do transfer posting in MB1B movement stock from one material to other material
    the reason for this error is the price in material master is different for two material so because of this PRD account key is called
    i have checked all the options by assignment of cost elements and still it is not solved
    This account is used in Account key in MM PRD - price difference  automatic account assignment
    and the error is raised only one when i post large value say around above 10,000 rs in value
    for less qty means value the error is not generated
    Any solution for this
    ( I have checked all the forums message related to this before posting )
    Thanks for Advance
    Rajesh

    Hi Rajesh,
    the answer is very simple.
    for all automatic postings or automatic account assignments, you need to maintain the default cost object in OKB9.
    For that particular GL account you need to main the automatic account assignments in OKB9 settings
    Please do let me know if you need further clarifications
    Best Regards
    Surya

  • Re : Account 893010 requires an assignment to a CO object

    Hi
             While doing purchase order the following error is coming
    " Purchase order item 00010 still contains faulty account assignments
    Item 10 Acct.assgt 1
    Account 893010 requires an assignment to a CO object "
    How to solve this.
    Thanks
    Anto

    Dear,
    Is Message no. KI235??
    As you have created GL as cost element.
    Now you have to assign it in OKB9 - Display View "Account assignment" : Overview
    In OKB9 specify weather this cost element give impact to cost center or profitability segment.
    If it is give impact to cost center then assign cost center against to cost element or assign it to PA.
    have you  cost account defined in accounts determination (OBYC).?
    Regards,
    R.Brahmankar

  • Account  455150 require as assignment to a Co object

    Dear Expert,
    when i do the Release GR Bloked stock with the Reffrance off Material Document in MIGO at that  time system give Error
    1.     Account  455150 require as assignment to a Co object.
    Thanks in advance.
    Regards
    Mahendra.

    Hi,
    For you G/L account in tcode FS00 assign the cost object by giving your G/L account and click on edit cost element and then open the tab Default Acct Assgmt where in provide the cost center over there and save it.This will workout for sure.
    Thanks
    Edited by: Madhavi.n on Dec 13, 2011 8:46 AM

  • FBCJ : 'Account 302024 requires an assignment to a CO Object'

    Dear All Experts,
    This is regarding error getting while POsting document in tcode FBCJ
    Getting error 'Account 302024 requires an assignment to a CO Object'
    I have enter data in FBCJ for cash payment and saved it. But while posting tht document it's giving error.
    I have enter Cost center also in that entry.
    My GL 302024 is 'Insurance claim' of Other income group and defined as Cost element account in FS00.
    Cost element category is '1' i.e Primary cost-reducing revenues."
    Also checked field status group in FS00. Cost center is an optional field in Field status group.
    For your information, i have different Profit center concept with diff. Cost center.
    So i cannot assigend one cost center to all Profit center automatically through OKB9.
    Pl required your help urgently.
    Regards
    Swati Shah

    Dear,
    As you said Insurance claim account is created in Other Income group but actually it should be created in other asset group. May be you have created this account as Balance Sheet account so that system expects profit center to be filled in the document. Cost center is never required in Income and balance sheet account.
    And please make sure because lot of ambiguity appears in your problem since this is created in Other Income group and cost element is created with category 01.
    Try entering profit center.
    Regards,
    Chintan Joshi.

  • Transfer Posting (MB1B): Account XYZ requires an assignment to a CO object

    Hi,
    Iam doing a Sales order to Sales order transfer using MB1B (Transfer Posting) and movement type 413 (E). However i get an error "Account 526020 requires an assignment to a CO object".
    Can someone advise as to where i need to assign the Costobject.
    Please advise.
    Thanks,
    Safi

    Do you really need to post something to a Cost Centre? If its a SO to SO transfer, what kind of cost is posting to the Cost Centre?
    I would suggest you analyse the GL Account (why it needs an assignment to a CO Object?) and consider changing the Field Status Group or assigning a GL that is not a Cost Element.
    If you really have to assign a Cost Centre, then OKB9 is your best alternative. Enter a Common CCtr that will collect the costs and maybe let you allocate the same later.
    Cheers.

Maybe you are looking for

  • Is anyone using testing seeing compiler lock-ups? [SOLVED]

    As the title says, is anyone using testing seeing compiler lock-ups? I've been seeing them for about two or three days. Sometimes the system will hang for a few seconds at "Starting make" with 100% CPU usage, then will continue normally. Other times

  • How can I add a new row in a JTable dynamically?

    Dear Sir(s) I want to add a new row in a Jtable as I press enter key the time focus is on the last cell of the row? pls help

  • Issue with REUSE_ALV_HIERSEQ_LIST_DISPLAY

    Hello All, I am trying to use REUSE_ALV_HIERSEQ_LIST_DISPLAY and am passing header and item level data in tables to the FM. It is displaying  the header fine, but when we click on the + sign the item level is not displaying any data. It seems the FM

  • Adding a listener to Active directory for user creation using Java

    Hi, I would like to add a listener to active directory such that when a user is created to the "Users" container, I should be notified or informed. I would like to do this with Java. What should I do ? Regards, Anand Kumar D

  • DPM 2012 R2 cannot backup VM online

    Hi Everyone, I'm having a problem trying to backup a VM with DPM, as it shows "offline" backup only (not online). Our environment: DPM 2012 R2 server with UR5, running on Windows 2012 R2. This server backs up all Virtual Machines running on a Windows