Goods Receipt through the RF menu, open delivery?

I am trying to do a good recepit through the RF menu. Once I click on the goods receipt , it takes me to the screen which asks for PO/delivery #, Material # and quantity.
When I enter in the PO, mat # and Qty , it gives me the error message "No Open Delivery"
So I went through the RF screen overview documentation which also says that "Material must exist in the order and in the open delivery"
Can anyone please explain what this means and how can I create an open delivery?
Thanks

Hi, The issue may be due to this - the component is batch managed but the batch data is blank in the component list of the Purchase Order Item. Or a batch is maintained in the PO item component list but the stock for the same batch is not available with Vendor, i.e. stock with some other batch may be available.
In a receipt for Sub-cont PO, 101 happens for FG and 543 happens for component. But there is no option to provide the component details in a delivery. So in standard system, when 101 happens via a delivery, 543 will be posted in the background. So any error in posting 543 will result in a blank screen without any error message.
You can fix this by maintaining correct batch in the PO component list.
But there is another issue - you cannot do 'cancel posting' and 'return delivery' for this receipt. Only you can reverse the inbound delivery and you should know that the  recevied stock shouldn't have been processed to do reversal of inbound delivery.

Similar Messages

  • Components were not consumed while posting the goods receipt through VL32N

    Hi Experts,
    We are into technical upgrade. We are upgrading from 4.7 to ECC 6.0. We are facing one issue. The issue is while posting the goods receipt for the subcontracting shceduling agreement through VL32N (Inbound Delivery) component materials were not consumed. While displaying the material document for the GR, could not find any compponent materials consumed with movement type 543, where as if I use the MIGO transaction code for the same inbound delivery, I could see the component materials were consumed with movement type 543.
    Could anybody tell us how to fix this issue if they come across.
    Appreciate your reply.
    Regards
    Bala

    Hi,
    Try checking below SAP notes
    Note 645119 - Problems with subcontracting using delivery
    338119 - Goods receipt in inbound delivery for SC order
    Hope this helps
    Reg
    Dheeraj

  • Goods receipt through Inbound delivery for Sub-Contracting Purchase order

    Hi
    I am trying to do goods receipt for the inbound delivery /shipping notification created for a sub -contracting Purchase order. The Finished product and the component part are batch managed, When I try to perform PGR in VL32N , I am getting a blank screen as error message and Goods receipt is not getting triggered . I checked for OSS note and found 645119 close to my issue but not an exact match . We are in ECC 6.0 with EHP 4. Can some one clarify whether it is possible to post GR through inbound delivery for a Subcon Purchase order .
    Thanks in advance for your immediate response.
    with regards,
    Joseph Anand B

    Hi, The issue may be due to this - the component is batch managed but the batch data is blank in the component list of the Purchase Order Item. Or a batch is maintained in the PO item component list but the stock for the same batch is not available with Vendor, i.e. stock with some other batch may be available.
    In a receipt for Sub-cont PO, 101 happens for FG and 543 happens for component. But there is no option to provide the component details in a delivery. So in standard system, when 101 happens via a delivery, 543 will be posted in the background. So any error in posting 543 will result in a blank screen without any error message.
    You can fix this by maintaining correct batch in the PO component list.
    But there is another issue - you cannot do 'cancel posting' and 'return delivery' for this receipt. Only you can reverse the inbound delivery and you should know that the  recevied stock shouldn't have been processed to do reversal of inbound delivery.

  • Make goods receipt for the items w/difference after the proof of delivery

    Hello experts,
    I do like to know how finish the process of proof of delivery, when I does have items with differences over the quantities that arrived to my client. For example, one sales order for 20 units. I did the delivery note, and posted the goods issue. Then I did the Proof of Delivery, confirming 19 units and the deviation reasons, saving the document. Then I made my billing document for 19 units of material.
    The deviation reasons was a damage material, my questions is: How does make goods receipt for the items with difference over the quantities after the confirming of proof of delivery?
    Thanks in advance
    Edited by: Johnattan Company on Sep 8, 2009 3:45 PM
    Edited by: Johnattan Company on Sep 8, 2009 3:59 PM

    Hello Chetan,
    Thinking in the process, I have found a solution to do it. If the differences was caused by unknowing reasons, like stolen or whatever reasons and the material will not enter again in the warehouse, we donu2019t need to make any process.
    But if the causes was a broken material, a lapsed date expired or unknowing others reasons as a consequence the material will enter again in the warehouse; I have customized a returns order, and a returns item with the option not relevant for billing to conclude the process.
    Thanks for your help.

  • New tabs dont pop up when I click to add a new tab, either by the tab bar or through the file menu.

    when I try to open up a new tab on my browser it doesn't do anything. I've tried the add a tab button on the tab bar, I've tried right clicking on the tab bar to add a tab, and I've gone through the file menu and nothing happens, like the command was never made....all other features work just fine..is there something wrong in my settings that I need to change??

    Try the Firefox SafeMode. <br />
    ''A troubleshooting mode, which disables most Add-ons.'' <br />
    ''(If you're not using it, switch to the Default Theme.)''
    # You can open the Firefox 4/5/6/7 SafeMode by holding the '''Shft''' key when you use the Firefox desktop or Start menu shortcut.
    # Or use the Help menu item, click on '''Restart with Add-ons Disabled...''' while Firefox is running. <br />
    ''To exit the Firefox Safe Mode, just close Firefox and wait a few seconds before using the Firefox shortcut (without the Shft key) to open it again.''
    If it is good in the Firefox SafeMode, your problem is probably caused by an extension, and you need to figure out which one. <br />
    http://support.mozilla.com/en-US/kb/troubleshooting+extensions+and+themes

  • Reg., Quality Inspection at the time of Goods Receipt against the P.O.

    Hi
    Pls provide the procedure for the "Quality Inspection at the time of Goods Receipt against the P.O."
    Thanks in advance.
    Regards
    Ravi

    Answers:
    1.Our client wants that he want to send back to Vendor, In which way we have to do in SAP?
    In QM,Raise notification for rejected qty in special stock, this will carry task of return delivery.
    2. Without Quality inspection User shouldn't do the MIRO?
    User discipline only it will be solved or
    Prepare user exit with help of ABAP'r
    while goods receipt(MIGO) for all scenarios(under delivery/over delivery/rejected) in development,
    Check MIRO for QC passed qty is allowed for bill booking, give meaningful messages for all scenarios.
    3. Quantity was certified by 13 only, so the user should do the MIRO for 13 only, Kindly suggest iIn which way we have to configure in SAP?
    Do return delivery for rejected quantity(2),if there excise,reverse it thru J1IS.
    After finishing above steps,Wheu u do IV only Quantity 13 will flow.
    Invoice verification will be done only for the accepted quantity.
    Above solution will solve problem.
    Edited by: Jeyakanthan A on Jan 11, 2010 12:01 PM
    Edited by: Jeyakanthan A on Jan 11, 2010 12:02 PM

  • Restriction of Good Receipt on the basis of Latest GR Date...

    How we can restrict the Goods Receipt against the Purcahse Order with reference to the Latest GR Date in reflecting in the Purcahse Order.
    Latest GR date reflects in the Delivery tab of the Item details in the Purcahse Order.

    Hi,
    To prevent goods from being accepted in the case of delayed delivery, youmust specify the latest possible goods receipt date for the item in the purchase order. This field is in the item detail data on the Delivery tab page. You also have to set
    message 163, Last possible delivery date was... (work area M7), as a warning or error message in Customizing.
    If you have set the message as an error message for delayed delivery, you can post the delivered goods to the GR blocked stock and then post a return delivery from the GR blocked stock.
    Hope Help U !
    Regards,
    Pardeep malik

  • PO with FREE of charge position - goods receipt change the average price

    Hi Experts,
    in our SAP system we have a special situation concerning the PO with free of charge (FOC) items.
    We set the flag "Free" in the PO position for all FOC items. When we book the good receipt for these FOC items SAP creates no accounting document and the average price is changing.
    for example: 1 pce is on stock with the value 100; we receive 1 pce for FOC
    new average price: (100 + 0) / (1 + 1) = 50
    this is a big problem for us.
    for us - the goods receipt for the FOC articles must be with the actual average price (table MBEW) similar to a return goods booking in the SD Module - movement type 653 !
    this means for our example: 1 pce is on stock with the value 100; we receive 1 pce for FOC
    new average price: (100 + 100 (acutal average price)) / (1 + 1) = 100
    I read a lot of OSS notes and many entries in the forums and I think many other companies have the same problem.
    is there any solution possibility to do that in this way?
    thank you for your help
    Peter Lechner

    it is logical that the moving average price changes.  if you dont want that, then you either have to have an extra material master for your free of charge stock, or you need to implement split valuation and can then have batches that are not valuated.
    But if you have 10 on hand with a value of 20 $, then the moving average is 2$
    if you then get another 10 free of charge, then you have 20 on hand with total value of 20$, which just means 20$ div by 20 quantity = 1 $ MAP.
    if SAP would not change the MAP in that moment, then the goods receipt is valuated with the current MAP and the total value of your stock increases to 40. but this is then not a free of charge case.

  • Goods receipt at the time of confirmation

    Dear all,
    At the time of confirmation only i want to do goods receipt in the goods movement screen. So please suggest me the configuration setting by which i can do GR at the time of order confirmation.
    Thanks,
    Aravind.

    Hi,
    As others have mentioned, auto GR can be done in the below listed manner:
    1. Maintain control  key with auto GR. If you want only auto GR in last operation then create a new control key for which only auto GR is checked in SPRO T. Code: OP00
    2. If you want auto GR only for few order types then for the respective order type create a production scheduling profile and assign that order type in production scheduling profile and in work scheduling view of material master maintain this production scheduling profile with auto GR checked in SPRO t. Code: OPKP.
    Hope it will help you.
    Regards,
    Alok Tiwari

  • I am having problems interacting with Microsoft Office programs since the last update:cannot create a pdf through the 'print' menu in exel and both Word and Exel docs sent in Mac Mail end up being received as .dat files.

    I am having problems interacting with Microsoft Office programs since the last update:cannot create a pdf through the 'print' menu in exel and both Word and Exel docs sent in Mac Mail end up being received as .dat files.
    Both these situations have cropped up on my MacBook Pro since the last update.
    Thanks for your help.
    Cheers
    Bob

    The 'Winmail.dat' problem has been extensively covered in these forums, I would search for that (a Google search works well) and unfortunately I have not seen the pdf print problem before, but assuming the software is current and functions normally (other than the pdf print problem) I have no suggestion other than the obvious (but time consuming) re-installation of Office.
    I wish I had more

  • Cross-intercompany purchasing --about goods receipt in the receiving plant

    Hello, everyone.
    In cross-intercompany purchasing process, the goods receipt in the receiving plant can not posted at the same time as the goods issue in the issuing plant, but i have done  the relevant custom design in system, the path as below:
    Material managementPurchasingPurchase orderSet up stock transport orderAssign document type, one step-procedure, underdelivery tolerance.
    I selected the one step-procedure.
    Anyone can tell me that's why ? thanks.
    xinzhou.

    There is no doupt that it is possible to do either a 1step or a 2step transfer between to companies.
    you usually choose the one or the other based on the time needed for the transfer.
    I have 2 legal entities at the very same physical place. So the goods do not even move physically while the ownership changes.  In this case I use 1step.

  • Can I chnge the context menu "open in new tab / window" options back to the previous version (reverse order)?

    In Firefox 4, the context menu "open in new tab / open in new window" options are in reverse order compared to 3.6. Can this be "fixed," i.e. change the menu item order? I use this feature constantly and it's a matter of habit, also still use some 3.6 machines.

    You can use the Menu Editor extension to re-arrange the menus - https://addons.mozilla.org/firefox/addon/menu-editor

  • HT202157 I just downloaded 5.2 and both my Apple TV shows and movies won't come up. Hulu and Netflix works fine, but when I go to select a purchased move or show through the apple menu, spiral comes up for about 10 seconds and then brings me back to the m

    I just downloaded 5.2 and both my Apple TV shows and movies won't come up. Hulu and Netflix works fine, but when I go to select a purchased move or show through the apple menu, spiral comes up for about 10 seconds and then brings me back to the main page

    StagLemoore wrote:
    Thank you everyone for your suggestions and help.  Ended up logging out of my apple ID account.  Of note, when I did I did a quick test and checked out both the movies and tv show options, and it all worked perfectly.  I then logged back in, and now all my purchased and rentals are available which makes sense.  I guess with the update there was some weird bit of trons that required one to log out then back in.  Probably doing a rest in between may not hurt for some.  Thanks again for all the assistance. Cheers.
    It looks like there is a Apple doc for this problem here -> Apple TV: Unable to access Movies, TV Shows, or other iTunes features after updating

  • What is a Statastical Good Receipt for the Purchase Order?

    Hi,
    What is a Statastical Good Receipt for the Purchase Order?
    What are the effects of the same in the documents like the po,stock (quantity and value), invoice verification etc?
    Thanks
    Regards

    Hi,
    In general the Statical GR done for Thirdparty Purchase Order.
    As no stocks updated at plant, its only record purpose.
    If you don't  done this GR , also you can able to do MIRO.
    The MIRO passed without any error.
    Regards

  • When doing goods receipt and the movement from QA to unrestricted use there

    Dear all,
    when doing goods receipt and the movement from QA to unrestricted use there is an yellow error message
    Error in EXIT_ SAPMM07_004 : Object 10462311E06/52,Char."LOBM_UDCODE,Value 01 A0,error"VALUE_NOT_FOUND"
    Inspection Lot : 10000283512
    System Status : UD ICCO SPRQ

    Hi,
    Did you use the follow up action in the UD code selection? It looks from the error that program is unable to find the UD code.
    Kindly check the configurations in QM and see that everything is working fine?
    Alternatively, if you are using the follow up action, then remove that first. Do the GR using MIGO -- this will create the inspection lot. Confirm the inspection using QA11 by entering the UD code for acceptance. Thereafter the the stock will rest in QI status. Use MB1B and perform the transfer posting with movement 321 to bring the stock to unrestricted use.
    Regards,
    Sushant

Maybe you are looking for

  • How to migrate old Sync (Weave) account/login to the new Sync service?

    I can login fine here... https://account.services.mozilla.com/ But before I did, it said I must use this page if I have FF29 or newer: https://accounts.firefox.com/signin I tried to enter the u/n + pwd that's always worked, but it says I must use an

  • Can't remove Acrobat 7.0 when Installing Acrobat 9.0

    I must have uninstalled Acrobat 7.0 Pro improperly and so now when I go to install Acrobat 9.0 Standard the installation wizard tells me I must remove Acrobat 7.0 before installing 9.0.  As it is trying to uninstall the rest of 7.0 during the 9.0 ins

  • 2010 Mac Mini Server & iLife

    Hello, I am thinking of buying the Mac Mini Server so I can do some hosting from home. But am I able to install iLife and other apps such as CS5 just so I can do some things on the side? Or is there some issues with running client software on the ser

  • User lock failed.SU10

    Dear experts, I locked a mass users using SU10, one of the user locked and immediately prompted for pwd change. USER1          31.01.2011     09:15:02     ADMIN           Lock Changed     0     Not locked     64     Administrator Lock               S

  • How to determine shipping company from trackcode format?